American Aluminum Products Co. v. Binswanger Glass Co.

391 S.E.2d 688, 194 Ga. App. 703, 11 U.C.C. Rep. Serv. 2d (West) 1126, 1990 Ga. App. LEXIS 307
CourtCourt of Appeals of Georgia
DecidedMarch 5, 1990
DocketA89A2142, A89A2143
StatusPublished
Cited by9 cases

This text of 391 S.E.2d 688 (American Aluminum Products Co. v. Binswanger Glass Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Aluminum Products Co. v. Binswanger Glass Co., 391 S.E.2d 688, 194 Ga. App. 703, 11 U.C.C. Rep. Serv. 2d (West) 1126, 1990 Ga. App. LEXIS 307 (Ga. Ct. App. 1990).

Opinion

Beasley, Judge.

This appeal and cross-appeal involve a contract dispute about skylights at two commercial sites.

Binswanger Glass Company subcontracted with American Aluminum Products Company, Inc. (AAPCO) to furnish and install a metal framed entry skylight at Cumberland Center Office Building in Cobb County. Binswanger also subcontracted with AAPCO to manufacture and install metal frames for skylights at the Northern Telecom Plaza in Nashville, Tennessee.

AAPCO sued Binswanger alleging that it was indebted to AAPCO, on open accounts, $10,055 for manufacture and installation of the Cumberland skylight and $17,110 for the Northern Telecom skylights. AAPCO alleged that both debts were liquidated, the Cum *704 berland one due and payable on July 3, 1985, and the Northern Telecom one on May 15, 1985. AAPCO asked for 18 percent interest per annum from those dates and reasonable attorney fees for bad faith and stubborn litigiousness.

Binswanger counterclaimed. As to Cumberland, it contended that under the contract as set forth in the purchase orders, drawings, and specifications, AAPCO’s work was to be leak-free and that it failed to properly perform and complete its work. Binswanger alleged that leaks resulted from incomplete and defective work; it had incurred costs to complete, test, and correct AAPCO’s work; and it was backcharged by the general contractor for repair work due to the leaking water falling on the terrazzo. It maintained that the remedial measures cost $13,921.03, exceeding the balance owed on the contract by $3,866.03 and entitling it to a set-off of $10,055. It denied that AAPCO was entitled to any sum under the contract and sought an affirmative recovery from AAPCO of $3,866.03 plus interest at 18 percent per annum.

Binswanger further contended that AAPCO failed to pay for $3,100.04 in materials purchased from it and demanded that amount plus interest for an open account or, in the alternative, for quantum meruit.

Regarding the Northern Telecom project, Binswanger alleged that under this contract also, as set forth in the purchase orders, specifications, and drawings, AAPCO’s work was to be leak-free, and that AAPCO failed to properly perform and complete its work and failed to furnish the required written warranty. Binswanger maintained that the skylights leaked, causing it to incur costs to test, correct and complete the work. It claimed it was backcharged by the general contractor for repairs due to the leaks, repairs to the roof, and additional work caused by AAPCO’s furnishing of improperly fitting skylight frames. These costs and backcharges allegedly totalled $55,755.33, exceeding the balance in the contract by $38,645.33. Thus, Binswanger claimed entitlement to a $17,110 set-off, zero for AAPCO and affirmative recovery on the Northern Telecom project for $38,645.33 plus interest at 18 percent per annum.

Binswanger further contended that on both projects, AAPCO breached the warranties that the materials and work would conform to the drawings and specifications, would be merchantable, of good material and workmanship, free from defects and fit for the intended purposes; AAPCO was liable for the costs asserted in the counterclaim under the indemnification provisions of the purchase orders; and AAPCO was liable for the costs claimed due to its negligent performance of its work, including unsatisfactory, improper, defective, and incomplete performance.

It asked for a total affirmative recovery on the counterclaim of *705 $45,611.40 plus 18 percent interest, plus the set-off.

Following a lengthy bench trial, the court issued its findings of fact and conclusions of law. It specified that as to the Northern Telecom project, AAPCO was entitled to $17,110 on its claim and Binswanger to $32,762.65 on its counterclaim, as to the Cumberland project, AAPCO was entitled to $10,055 on its claim and Binswanger to $16,156.98 on its counterclaim. The court awarded AAPCO a total of $27,165 and Binswanger a total of $48,919.63. It also concluded that certain damages, namely $3,748.06 in man hours and $3,912.67 in materials provided by Binswanger on the Northern Telecom job and $3,100.04 in materials purchased by AAPCO from Binswanger on the Cumberland job, were liquidated, entitling Binswanger to 7 percent interest from November 4, 1985, on these amounts.

AAPCO’s appeal challenges eight of the court’s specific findings and the court’s admission of certain evidence. Binswanger’s cross-appeal contends that pursuant to OCGA § 7-4-16 it was entitled to interest at 18 percent per annum rather than 7 percent per annum on the liquidated amounts.

Case No. A89A2142

1. “A trial judge sitting without a jury is entitled to have his judgment considered as a verdict by a jury, and if there is any evidence to support the finding, it should be affirmed. Also the evidence must be construed most strongly in favor of the prevailing party. [Cit.]” Anchor Sign Co. v. ITT Terryphone Corp., 138 Ga. App. 742, 743 (2) (227 SE2d 492) (1976).

AAPCO contends that the trial court erred in finding that as to both projects Binswanger’s purchase orders constituted the contract between the parties. Its argument in this regard, is focused solely on the Northern Telecom project. Any such contention about the Cumberland contract is considered abandoned. Court of Appeals Rule 15 (c) (2); Melton v. Gilleland & Sons, 176 Ga. App. 390 (1) (336 SE2d 315) (1985).

There were two purchase orders. The first, dated October 29, 1984, called for “skylites per plans and specs” based on shop drawings to be submitted within two weeks and approved die drawings submitted by AAPCO. The second, dated March 13,1985, called for AAPCO to furnish labor to install the “skylite metal frames” and all “flashings and brake shapes” per AAPCO’s approved shop drawings.

AAPCO’s position is that the first purchase order shows that the contract to manufacture and ship the skylights was a sale of goods covered by the Uniform Commercial Code so that the court should have considered the oral agreement and understanding of the parties that Binswanger wanted skylights like certain “Fisher drawings.” *706 AAPCO concedes that the second purchase order is not governed by the UCC. It argues that it had no substantial deviations from the Fisher drawings, that Binswanger’s counterclaim was based on specifications that AAPCO was not furnished, that in light of AAPCO’s initial proposal ambiguity arose in the first purchase order because of the use of the terms “plans” and “specs,” and that to incorporate the “specs” as contended by Binswanger would give the contract a totally unreasonable and unconscionable construction.

If the two purchase orders constitute but a single contract between the parties which involves furnishing both labor and materials, the UCC would not apply. The “UCC applies only to certain contracts for the sale of goods. [OCGA § 11-2-102.]” Dixie Lime &c. Co. v. Wiggins Scale Co., 144 Ga. App. 145 (2) (240 SE2d 323) (1977).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Discrete Wireless, Inc. v. Coleman Technologies, Inc.
422 F. App'x 777 (Eleventh Circuit, 2011)
Hampshire Homes, Inc. v. Espinosa Construction Services, Inc.
655 S.E.2d 316 (Court of Appeals of Georgia, 2007)
Southern Tank & Equipment Co. v. Zartic, Inc.
471 S.E.2d 587 (Court of Appeals of Georgia, 1996)
Crosby v. Spencer
428 S.E.2d 607 (Court of Appeals of Georgia, 1993)
Dalcor Management, Inc. v. Sewer Rooter, Inc.
423 S.E.2d 419 (Court of Appeals of Georgia, 1992)
City of Atlanta v. Atlantic Realty Co.
421 S.E.2d 113 (Court of Appeals of Georgia, 1992)
Ramey v. Leisure, Ltd.
421 S.E.2d 555 (Court of Appeals of Georgia, 1992)
Renshaw v. Feagin
404 S.E.2d 457 (Court of Appeals of Georgia, 1991)
Sunderland v. Vertex Associates, Inc.
404 S.E.2d 574 (Court of Appeals of Georgia, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
391 S.E.2d 688, 194 Ga. App. 703, 11 U.C.C. Rep. Serv. 2d (West) 1126, 1990 Ga. App. LEXIS 307, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-aluminum-products-co-v-binswanger-glass-co-gactapp-1990.