Whitehall Wind, LLC v. Montana Public Service Commission

2010 MT 2, 223 P.3d 907, 355 Mont. 15, 2010 Mont. LEXIS 1
CourtMontana Supreme Court
DecidedJanuary 5, 2010
DocketDA 09-0108
StatusPublished
Cited by15 cases

This text of 2010 MT 2 (Whitehall Wind, LLC v. Montana Public Service Commission) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Whitehall Wind, LLC v. Montana Public Service Commission, 2010 MT 2, 223 P.3d 907, 355 Mont. 15, 2010 Mont. LEXIS 1 (Mo. 2010).

Opinion

JUSTICE MORRIS

delivered the Opinion of the Court.

¶1 The Montana Public Service Commission (PSC) and Northwestern Energy (Northwestern) appeal an order of the Fifth Judicial District Court, Jefferson County, reversing and remanding the PSC’s order setting a standard tariff rate for Northwestern Energy’s purchase of electricity from Whitehall Wind (Whitehall). We affirm.

¶2 We review the following issues on appeal:

¶3 Was the District Court’s order for remand a final judgment under M. R. App. P. 6(1)?

¶4 Did the District Court properly determine that the PSC’s tariff was unlawful and unreasonable?

¶5 Did the District Court properly allow Whitehall to augment the record?

¶6 Did federal law preempt the PSC’s order setting the standard tariff rate?

FACTUAL AND PROCEDURAL BACKGROUND

¶7 Congress enacted § 210 of the Public Utility Regulatory Policies Act (PURPA) in 1978 to encourage development of small electrical generation facilities. 16 U.S.C. § 824a-3 (2006). PURPA requires large *17 utilities to purchase energy from smaller qualifying facilities at rates that allow the small facilities to become and remain viable suppliers of electricity. Whitehall is a qualifying facility under PURPA. 18 C.F.R. § 292.204 (2008).

¶8 Whitehall attempted unsuccessfully to negotiate a contract with Northwestern for the sale of wind-generated electricity from Whitehall’s 50 megawatt wind generation facility near Whitehall, Montana. Whitehall petitioned the PSC in August of2002 to determine the rates and conditions for the sale following the unsuccessful negotiations with Northwestern.

¶9 State utility regulatory agencies implement PURPA through rulemaking. As the state utility authority for Montana, the PSC must set rates for electric utilities over which it has authority. The Montana Legislature enacted §§ 69-3-601 through 604, MCA, to facilitate the PSC’s implementation of PURPA. Section 69-3-603, MCA, requires the PSC to set rates and conditions for sales between qualifying facilities and large utilities.

¶10 The PSC determined that Whitehall constituted a qualifying facility under PURPA. This determination entitled Whitehall to sell electricity to Northwestern at the wholesale rate. The PSC held a contested case proceeding to determine the wholesale rate. The PSC set the rate for the sale at the short-term standard avoided cost tariff rate for transactions between Northwestern and qualifying facilities. Northwestern had not submitted a least cost plan since 1996. As a result, the PSC considered avoided cost data from 1996 when it set the 2002 rate. The PSC’s Order no. 6444c set a rate of $10,639 per megawatt hour (MWh).

¶11 Whitehall petitioned for judicial review. Whitehall claimed that the PSC had reached an unreasonably low rate determination in light of data submitted by Whitehall and the PSC that supported a higher rate. Whitehall argued that a reasonable 2002 rate should have been between $31 and $40 per MWh.

¶12 Whitehall moved to augment the record. Whitehall claimed that the PSC’s failure to require Northwestern to produce avoided cost data since 1996 in compliance with statutory and regulatory provisions constituted a procedural irregularity that supported its effort to augment the record. Whitehall further requested permission to conduct limited discovery to produce evidence of NorthWestern’s current avoided costs. The District Court granted Whitehall’s motion to augment.

¶13 The PSC’s staff economist submitted a report in response to the *18 District Court’s order to augment the record. The report confirmed that a reasonable 2002 rate would have been approximately $31 to $32 per MWh. Whitehall requested that the District Court remand the case to the PSC with instructions to set a new rate based on current data for the project’s rescheduled completion date of 2009. The PSC and Northwestern argued that the District Court’s jurisdiction extended only to a review of the 2002 rate data.

¶14 The District Court found that the PSC’s rate determination was unreasonable because it was not supported by substantial evidence. The court found that the evidence of the PSC’s own staff economist contradicted the PSC’s rate determination. The District Court determined that the PSC had not based the rate determination on current avoided cost data. The court remanded the case with instructions to the PSC to set a new rate that would take into account the avoided cost data submitted by Whitehall and the PSC.

STANDARD OF REVIEW

¶15 A district court reviews an administrative decision in a contested case to determine whether the agency’s findings of fact are clearly erroneous and whether its interpretation of the law is correct. Clouse v. Lewis and Clark County, 2008 MT 271, ¶ 23, 345 Mont. 208, 190 P.3d 1052. We employ the same standard when reviewing a district court order affirming or reversing an administrative decision. Clouse, ¶ 23.

DISCUSSION

¶16 Was the District Court’s order for remand a final judgment under M. R. App. P. 6(1)?

¶17 Whitehall argues as a threshold issue that the District Court’s order constitutes an interlocutory judgment that should not be appealable by the PSC. An interlocutory judgment determines a preliminary issue, but does not finally decide the case. M. R. App. P. 4(l)(b). Whitehall emphasizes the fact that the District Court’s order did not set a rate or direct the PSC to set a particular rate. Whitehall contends that the PSC must amend its rate determination in compliance with the District Court’s order before it may appeal.

¶18 A party may appeal only a district court’s final judgment. M. R. App. P. 6(1). A “final judgment” conclusively determines the rights of the parties and settles all claims in controversy. M. R. App. P. 4(l)(a). Section 2-4-702, MCA, provides for judicial review of an agency decision in a contested case. The District Court reviewed Whitehall’s *19 case and decided in Whitehall’s favor based on the standards set out at § 2-4-704, MCA. The District Court’s review of the whole record led it to conclude that the PSC’s rate was unreasonable. To force the PSC to recalculate the rate in accordance with the District Court’s specific instructions before allowing it to appeal would undermine the PSC’s right to appeal under § 2-4-711, MCA. The District Court’s order constitutes a final order from which the PSC has a right of appeal. M. R. App. P. 4(l)(a).

¶19 Did the District Court properly determine that the PSC’s tariff was unlawful and unreasonable?

¶20 Federal law requires that rates for utility purchases of qualified facility-generated electricity must be reasonable. 16 U.S.C. § 824a-3(b)(1) (2006); 18 C.F.R.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

CED Wheatland v. MPSC
2022 MT 87 (Montana Supreme Court, 2022)
Armstrong v. Personnel Appeals
2020 MT 301N (Montana Supreme Court, 2020)
MTSUN v. PSC
2020 MT 238 (Montana Supreme Court, 2020)
Vote Solar v. PSC
2020 MT 213 (Montana Supreme Court, 2020)
Northwestern v. PSC
2016 MT 239 (Montana Supreme Court, 2016)
Whitehall Wind, LLC v. Montana Public Service Commission
2015 MT 119 (Montana Supreme Court, 2015)
Williamson v. Montana Public Service Commission
2012 MT 299 (Montana Supreme Court, 2012)
Headapohl v. Missoula City-County Board of Health
2011 MT 209 (Montana Supreme Court, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
2010 MT 2, 223 P.3d 907, 355 Mont. 15, 2010 Mont. LEXIS 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/whitehall-wind-llc-v-montana-public-service-commission-mont-2010.