NorthWestern Corp. v. Montana Department of Public Service Regulation

2016 MT 239, 380 P.3d 787, 385 Mont. 33, 2016 Mont. LEXIS 885
CourtMontana Supreme Court
DecidedSeptember 27, 2016
DocketNo. DA 15-0612
StatusPublished
Cited by9 cases

This text of 2016 MT 239 (NorthWestern Corp. v. Montana Department of Public Service Regulation) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
NorthWestern Corp. v. Montana Department of Public Service Regulation, 2016 MT 239, 380 P.3d 787, 385 Mont. 33, 2016 Mont. LEXIS 885 (Mo. 2016).

Opinion

JUSTICE RICE

delivered the Opinion of the Court.

¶1 Appellants Northwestern Corporation, doing business as Northwestern Energy (Northwestern), the Natural Resources Defense Council (NRDC), and Human Resources Council, District XI (HRC), appeal the decision of the Second Judicial District Court affirming the Final Order of the Montana-Public Service Commission (Commission), which disallowed $1,419,427 in claimed excess electric regulation costs and adjusted energy efficiency savings calculations. We affirm, considering the following issues:

1. Did the Commission apply the correct legal standard in reviewing NorthWestern’s claim for excess outage costs?
2. Were the “free ridership” and “spillover”calculations adopted by the Commission supported by substantial evidence?

FACTUAL AND PROCEDURAL BACKGROUND

¶2 This matter involves a challenge to the Commission’s Final Order in NorthWestern’s 2011-2012 annual tracker filing.1 Therein, Northwestern requested, inter alia, a $1,419,427 increase in rates for [35]*35unexpected electricity supply costs due to an outage at its Dave Gates Generating Station (DGGS), located near Anaconda.2 As part of the proceeding, the Commission also ordered Northwestern to present evidence for purposes of conducting a “true-up” to actual costs for lost revenues that had been previously estimated in NorthWestern’s demand-side management (DSM) programs. Ultimately, the Commission (1) denied NorthWestern’s request to include the DGGS outage costs in customer rates, and (2) rejected NorthWestern’s expert’s conclusion that the “free ridership” and “spillover” values of its DSM programs were perfectly offsetting, adopting instead the same expert’s actual calculations used in a draft report.

DGGS Outage Costs

¶3 In 2008, Northwestern sought Commission approval to build the DGGS. The DGGS was intended to provide regulation and frequency response service in NorthWestern’s service area. The Commission approved the project in 2009, and the DGGS commenced commercial operation on January 1, 2011.

¶4 The DGGS was a first-of-its-kind facility that Northwestern presented as having “the potential to be a model facility for the supply of regulation service.” It consisted of three generation units made by Pratt & Whitney Power Systems, Inc. (PWPS) and was an application of a simple cycle natural gas turbine generator designed to increase or decrease generation (ramp) in response to variations in NorthWestern’s load, “on a moment-by-moment basis.” NorthWestem’s General Manager of Generation testified that the plant had a “very unique” control mechanism and “early on we knew that the plant was going to have a very unique control application.”

¶5 Northwestern was aware that the ramp capabilities of the DGGS were critical to its operation and that the DGGS was a first-of-its-kind application, stating:

[The DGGS] is one of the first power plant installations to be built specifically for electrical transmission grid regulation duty. The design requirements for grid regulation are stringent since they require the plant to continually change load in a short time frame (seconds to minutes).

This load requirement was necessary because Northwestern “anticipated variable operating conditions,” largely due to wind generation variations, and the DGGS needed to be able to ramp up or [36]*36down by at least 15 mega-watts (MW) per minute per unit to “offset the continuous variation between system generation and system load.”

¶6 The contract between Northwestern and PWPS included a waiver of consequential damages, but Northwestern purchased, with customer revenue, an extended warranty to cover the innovative technology. Northwestern did not purchase or evaluate the feasibility of outage insurance in case the DGGS had an operational failure.

¶7 On January 31, 2012, thirteen months after Northwestern brought the DGGS online, it suffered a complete outage. Unit cycling had caused “thermal stresses” by going from a cold state to a very high temperature, damaging the rotating equipment. PWPS concluded the outage resulted from ramp rates “much greater” than anticipated, excessive temperatures, and cycle-related hardware failures. The Commission was unable to precisely examine the ramp data because Northwestern failed to maintain minute-by-minute records.

¶8 Pursuant to the extended warranty, PWPS repaired the damaged turbines at its cost, including removal, installation, and shipping costs. However, due to the waiver of consequential damages in the contract, PWPS was not obligated to cover the costs associated with purchasing replacement regulation service during the outage. On February 3, 2012, Northwestern began purchasing replacement service from Powerex Corp. (Powerex) and Avista Corp. (Avista). PWPS took “extraordinary measures” to repair the DGGS as soon as possible. Individual generators were put back online as PWPS restored them and Northwestern proportionally decreased its regulation service purchases accordingly. The DGGS was fully back online on May 1, 2012.

¶9 During the outage, Northwestern customers continued to pay the fixed costs for the operation of the DGGS ($6,742,625), including NorthWestern’s usual rate of return, as well as the variable costs ($1,527,714) Northwestern did not actually incur, but would have incurred had the plant been operational. However, the outage caused Northwestern to incur an additional $1,419,427 in charges to Powerex and Avista for regulation service. Northwestern requested reimbursement of these costs, arguing they were reasonably incurred because it obtained an extended warranty that covered all repairs, it purchased regulation service on the competitive market at 2011 rates, it structured its regulation market purchases to enable it to incrementally reduce the purchases as generators were repaired, and it had worked quickly to get the DGGS back online.

¶10 The Montana Consumer Counsel (MCC) opposed reimbursement [37]*37of the replacement service costs, contending that Northwestern failed to undertake risk mitigation by failing to investigate whether outage insurance was available. The MCC offered the testimony of Dr. John Wilson:

No. I don’t fault the company for not procuring it [outage insurance]. What I think was imprudent was not looking into it, not evaluating it, not finding out whether it was available and what the cost would be for a plan like this. I think you have to do that before you make a determination as to whether you acquire it or not.

The MCC argued that evaluation of insurance was fundamental to risk management where the contract contained an exclusion for consequential damages:

[T]he most imprudent thing that occurred here, is the failure of the company to take steps to protect itself against the outage, given the fact that they had this exclusion under the warranty, given the fact that they knew... that there were unknowns about this plant and where it was going to go and how it was going to operate.

¶11 Northwestern responded by providing evidence that in its experience it had never purchased replacement power insurance and, instead, always relied on the market for replacement power.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Estate of Athy v. Edgewood
2026 MT 3 (Montana Supreme Court, 2026)
MEIC v. Westmoreland Rosebud Mining
2023 MT 224 (Montana Supreme Court, 2023)
CED Wheatland v. MPSC
2022 MT 87 (Montana Supreme Court, 2022)
Gruba v. PSC
2021 MT 186N (Montana Supreme Court, 2021)
Vote Solar v. PSC
2020 MT 213 (Montana Supreme Court, 2020)
Mcgree Corp. v. Mont. Pub. Serv. Comm'n
2019 MT 75 (Montana Supreme Court, 2019)
Northwestern v. PSC
2016 MT 239 (Montana Supreme Court, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
2016 MT 239, 380 P.3d 787, 385 Mont. 33, 2016 Mont. LEXIS 885, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northwestern-corp-v-montana-department-of-public-service-regulation-mont-2016.