Northwestern v. PSC

2016 MT 239
CourtMontana Supreme Court
DecidedSeptember 27, 2016
Docket15-0612
StatusPublished

This text of 2016 MT 239 (Northwestern v. PSC) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northwestern v. PSC, 2016 MT 239 (Mo. 2016).

Opinion

09/27/2016

DA 15-0612 Case Number: DA 15-0612

IN THE SUPREME COURT OF THE STATE OF MONTANA 2016 MT 239

NORTHWESTERN CORPORATION, doing business as NORTHWESTERN ENERGY,

Petitioner and Appellant,

v.

THE MONTANA DEPARTMENT OF PUBLIC SERVICE REGULATION, MONTANA PUBLIC SERVICE COMMISSION,

Respondent and Appellee,

NATURAL RESOURCES DEFENSE COUNCIL, HUMAN RESOURCE COUNCIL, DISTRICT XI, and MONTANA CONSUMER COUNSEL,

Intervenors.

APPEAL FROM: District Court of the Second Judicial District, In and For the County of Butte/Silver Bow, Cause No. DV-13-399 Honorable Brad Newman, Presiding Judge

COUNSEL OF RECORD:

For Appellant:

Al Brogan, NorthWestern Corporation d/b/a/ NorthWestern Energy, Helena, Montana

For Appellee:

Jason Brown, Jeremiah Langston, Justin Kraske, Montana Public Service Commission, Helena, Montana

For Intervenors:

Robert A. Nelson, Montana Consumer Counsel, Helena, Montana Charles Magraw, Human Resource Council, District XI, Natural Resources Defense Council, Helena Montana

Submitted on Briefs: August 10, 2016

Decided: September 27, 2016

Filed:

__________________________________________ Clerk

2 Justice Jim Rice delivered the Opinion of the Court.

¶1 Appellants NorthWestern Corporation, doing business as NorthWestern Energy

(NorthWestern), the Natural Resources Defense Council (NRDC), and Human Resources

Council, District XI (HRC), appeal the decision of the Second Judicial District Court

affirming the Final Order of the Montana Public Service Commission (Commission),

which disallowed $1,419,427 in claimed excess electric regulation costs and adjusted

energy efficiency savings calculations. We affirm, considering the following issues:

1. Did the Commission apply the correct legal standard in reviewing NorthWestern’s claim for excess outage costs?

2. Were the “free ridership” and “spillover” calculations adopted by the Commission supported by substantial evidence?

FACTUAL AND PROCEDURAL BACKGROUND

¶2 This matter involves a challenge to the Commission’s Final Order in

NorthWestern’s 2011–2012 annual tracker filing.1 Therein, NorthWestern requested,

inter alia, a $1,419,427 increase in rates for unexpected electricity supply costs due to an

outage at its Dave Gates Generating Station (DGGS), located near Anaconda.2 As part of

the proceeding, the Commission also ordered NorthWestern to present evidence for

purposes of conducting a “true-up” to actual costs for lost revenues that had been

previously estimated in NorthWestern’s demand-side management (DSM) programs.

Ultimately, the Commission (1) denied NorthWestern’s request to include the DGGS

1 In re NorthWestern Energy’s 2011–2012 Electricity Supply Tracker, Mont. Pub. Serv. Comm’n, Dkt. D2012.5.49, Order No. 7219h (Oct. 28, 2013). 2 The DGGS was formerly called the Mill Creek Generating Station. 3 outage costs in customer rates, and (2) rejected NorthWestern’s expert’s conclusion that

the “free ridership” and “spillover” values of its DSM programs were perfectly offsetting,

adopting instead the same expert’s actual calculations used in a draft report.

DGGS Outage Costs

¶3 In 2008, NorthWestern sought Commission approval to build the DGGS. The

DGGS was intended to provide regulation and frequency response service in

NorthWestern’s service area. The Commission approved the project in 2009, and the

DGGS commenced commercial operation on January 1, 2011.

¶4 The DGGS was a first-of-its-kind facility that NorthWestern presented as having

“the potential to be a model facility for the supply of regulation service.” It consisted of

three generation units made by Pratt & Whitney Power Systems, Inc. (PWPS) and was an

application of a simple cycle natural gas turbine generator designed to increase or

decrease generation (ramp) in response to variations in NorthWestern’s load, “on a

moment-by-moment basis.” NorthWestern’s General Manager of Generation testified

that the plant had a “very unique” control mechanism and “early on we knew that the

plant was going to have a very unique control application.”

¶5 NorthWestern was aware that the ramp capabilities of the DGGS were critical to

its operation and that the DGGS was a first-of-its-kind application, stating:

[The DGGS] is one of the first power plant installations to be built specifically for electrical transmission grid regulation duty. The design requirements for grid regulation are stringent since they require the plant to continually change load in a short time frame (seconds to minutes).

4 This load requirement was necessary because NorthWestern “anticipated variable

operating conditions,” largely due to wind generation variations, and the DGGS needed

to be able to ramp up or down by at least 15 mega-watts (MW) per minute per unit to

“offset the continuous variation between system generation and system load.”

¶6 The contract between NorthWestern and PWPS included a waiver of

consequential damages, but NorthWestern purchased, with customer revenue, an

extended warranty to cover the innovative technology. NorthWestern did not purchase or

evaluate the feasibility of outage insurance in case the DGGS had an operational failure.

¶7 On January 31, 2012, thirteen months after NorthWestern brought the DGGS

online, it suffered a complete outage. Unit cycling had caused “thermal stresses” by

going from a cold state to a very high temperature, damaging the rotating equipment.

PWPS concluded the outage resulted from ramp rates “much greater” than anticipated,

excessive temperatures, and cycle-related hardware failures. The Commission was

unable to precisely examine the ramp data because NorthWestern failed to maintain

minute-by-minute records.

¶8 Pursuant to the extended warranty, PWPS repaired the damaged turbines at its

cost, including removal, installation, and shipping costs. However, due to the waiver of

consequential damages in the contract, PWPS was not obligated to cover the costs

associated with purchasing replacement regulation service during the outage. On

February 3, 2012, NorthWestern began purchasing replacement service from Powerex

Corp. (Powerex) and Avista Corp. (Avista). PWPS took “extraordinary measures” to

5 repair the DGGS as soon as possible. Individual generators were put back online as

PWPS restored them and NorthWestern proportionally decreased its regulation service

purchases accordingly. The DGGS was fully back online on May 1, 2012.

¶9 During the outage, NorthWestern customers continued to pay the fixed costs for

the operation of the DGGS ($6,742,625), including NorthWestern’s usual rate of return,

as well as the variable costs ($1,527,714) NorthWestern did not actually incur, but would

have incurred had the plant been operational. However, the outage caused NorthWestern

to incur an additional $1,419,427 in charges to Powerex and Avista for regulation service.

NorthWestern requested reimbursement of these costs, arguing they were reasonably

incurred because it obtained an extended warranty that covered all repairs, it purchased

regulation service on the competitive market at 2011 rates, it structured its regulation

market purchases to enable it to incrementally reduce the purchases as generators were

repaired, and it had worked quickly to get the DGGS back online.

¶10 The Montana Consumer Counsel (MCC) opposed reimbursement of the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Molnar v. Fox
2013 MT 132 (Montana Supreme Court, 2013)
City of Billings v. Public Service Commission
631 P.2d 1295 (Montana Supreme Court, 1981)
Montana Power Co. v. Public Service Commission
671 P.2d 604 (Montana Supreme Court, 1983)
Ward v. Johnson
790 P.2d 483 (Montana Supreme Court, 1990)
Johansen v. State, Dept. of Natural Resources
1998 MT 51 (Montana Supreme Court, 1998)
Montana Power Co. v. Montana Public Service Commission
2001 MT 102 (Montana Supreme Court, 2001)
Knowles v. State Ex Rel. Lindeen
2009 MT 415 (Montana Supreme Court, 2009)
Whitehall Wind, LLC v. Montana Public Service Commission
2010 MT 2 (Montana Supreme Court, 2010)
Johnson v. WESTERN TRANSPORT, LLC
2011 MT 13 (Montana Supreme Court, 2011)
State v. CARAPEZZA
272 P.3d 10 (Supreme Court of Kansas, 2012)
Schuster v. Northwestern Energy Co.
2013 MT 364 (Montana Supreme Court, 2013)
Whitehall Wind, LLC v. Montana Public Service Commission
2015 MT 119 (Montana Supreme Court, 2015)
Great Northern Utilities Co. v. Public Service Commission
293 P. 294 (Montana Supreme Court, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
2016 MT 239, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northwestern-v-psc-mont-2016.