MTSUN v. PSC

2020 MT 238
Montana Supreme Court·Decided September 22, 2020·No. DA 19-0363·Published·Cited by 4 cases

Opinion

09/22/2020

DA 19-0363 Case Number: DA 19-0363

IN THE SUPREME COURT OF THE STATE OF MONTANA

2020 MT 238

MTSUN, LLC,

Applicant, Petitioner, and Appellee,

v.

THE MONTANA DEPARTMENT OF PUBLIC SERVICE REGULATION, MONTANA PUBLIC SERVICE COMMISSION,

Respondent and Cross-Appellant,

and

NORTHWESTERN CORPORATION, d/b/a NORTHWESTERN ENERGY,

Intervenor, Respondent, and Appellant,

THE MONTANA CONSUMER COUNSEL,

Intervenor.

APPEAL FROM: District Court of the Eighth Judicial District, In and For the County of Cascade, Cause No. BDV-17-0776 Honorable James A. Manley, Presiding Judge

COUNSEL OF RECORD:

For Appellant NorthWestern Energy:

Ann B. Hill, NorthWestern Energy, Helena, Montana For Cross-Appellant Montana Public Service Commission:

Zachary Taylor Rogala, Luke Casey, Justin Wade Kraske, Montana Public Service Commission, Helena, Montana

For Appellee MTSUN, LLC:

Michael J. Uda, Christine McMurry, Uda Law Firm, PC, Helena, Montana

For Intervenor Montana Consumer Counsel:

Jason T. Brown, Montana Consumer Counsel, Helena, Montana

Submitted on Briefs: January 15, 2020

Decided: September 22, 2020

Filed: oe,,6tA- -if __________________________________________ Clerk

2 Chief Justice Mike McGrath delivered the Opinion of the Court.

¶1 The Montana Public Service Commission (“PSC”) and NorthWestern Energy

(“NorthWestern”) appeal an order of the Eighth Judicial District Court, Cascade County,

reversing and remanding the PSC’s order setting terms and conditions of MTSUN, LLC’s

(“MTSUN”) proposed 80 megawatt (“MW”) solar project near Billings, Montana.

¶2 We restate the following issues on appeal as dispositive and do not address other

issues raised:

Issue One: Whether the District Court erred in determining that the PSC arbitrarily and unlawfully found that MTSUN did not establish a legally-enforceable obligation under PURPA and therefore was not entitled to agreed-upon contract terms.

Issue Two: Whether the PSC exceeded its authority in upending the parties’ agreed- upon contract terms established by MTSUN’s legally-enforceable obligation.

Issue Three: Whether the District Court erred when it concluded that the PSC arbitrarily and unreasonably calculated MTSUN’s capacity contribution in determining avoided costs.

¶3 We affirm.

FACTUAL AND PROCEDURAL BACKGROUND

¶4 Before addressing the merits of the case, we contextualize the issues presented by

providing necessary background information on the governing laws, practices of the PSC,

and the relevant factual and procedural history of the present action. Regarding the

background of applicable federal and state law, as well as the historical practices of the

PSC, we incorporate by reference this Court’s discussion in Vote Solar v. Mont. Dept. of

Pub. Serv. Regulation, 2020 MT 213, ¶¶ 4-17, 401 Mont. 85, ___ P.3d ___.

3 PURPA Background

¶5 In addition to the Public Utility Regulatory Policies Act (“PURPA”) background

provided in Vote Solar, ¶¶ 3-17, it is necessary to discuss another component of PURPA

that was not at issue in Vote Solar but is in this case. PURPA and Montana’s

implementation of PURPA requires that for larger qualifying facilities (“QFs”)—those

between three and 80 MWs—avoided-cost purchase prices be established between the QF

and the purchasing public utility through a negotiated contract, on an “as available” basis,

or pursuant to a “legally-enforceable obligation” (“LEO”), whereas smaller QFs—less than

3 MWs—receive a standard avoided-cost rate that is set by the PSC itself every two years.

16 U.S.C. § 824a-3(a), (m)(6); § 69-3-601(3)(c), MCA; 18 C.F.R. § 292.304(c), (d);

Admin. R. M. 38.5.1902(5), 38.5.1909. This dispute is centered on PURPA’s legally-

enforceable obligation component.

PURPA’s Legally-Enforceable Obligation

¶6 Under its PURPA authority, see 16 U.S.C. § 824a-3(a), the Federal Energy

Regulatory Commission (“FERC”) has established that a QF can sell power to a utility via

a LEO, rather than under a contract. 18 C.F.R. § 292.304(d)(2); see Midwest Renewable

Energy Projects, LLC, 116 FERC ¶ 61017, 61073 (July 7, 2006) (holding “[t]hat Congress

used the term ‘contract or obligation’ in drafting section 210(m)(6) [16 U.S.C.

§ 824a-3(m)(6)] suggests that Congress intended that the Commission continue to protect

both contracts and obligations that had not yet ripened into contracts but were ‘in effect or

pending approval’”). A LEO is a “non-contractual, but binding” commitment from a QF

to sell power to a utility. Cedar Creek Wind, LLC, 137 FERC ¶ 61006, 61023 (Oct. 4,

4 2011). The phrase is used to prevent an electric utility from avoiding its PURPA

obligations by refusing to sign a contract, or “from delaying the signing of a contract, so

that a later and lower avoided cost is applicable.” Cedar Creek Wind, 137 FERC at 61024.

Accordingly, the establishment of a LEO turns on “the QF’s commitment, and not the

utility’s actions,” and when a QF commits itself to sell to an electric utility, it “also commits

the electric utility to buy from the QF.”1 FLS Energy, Inc., 157 FERC ¶ 61211, 61730-31,

(Dec. 15, 2016) (emphasis in original). Importantly, the date that a LEO is formed is the

date that the QF has the right to have its avoided-cost rate determined. 18 C.F.R.

§ 292.304(d)(2)(ii).

¶7 The primary legal issue surrounding the LEO provision of PURPA is whether and

when a QF has committed itself to sell to an electric utility. Relevant here, FERC provides

that a QF commits itself to sell electricity to a utility through either a signed contract or

when the QF petitions a state utility commission because “the electric utility refuses to sign

a contract” or “delay[s] the signing of a contract.” Cedar Creek Wind, 137 FERC at 61024;

JD Wind 1, LLC, 129 FERC ¶ 61148, 61633 (Nov. 19, 2009); New PURPA Section 210(m)

Regulations Applicable to Small Power Production and Cogeneration Facilities, 71 Fed.

Reg. 64342, 64345, 64368 (Nov. 1, 2006) (hereinafter New PURPA Section 210(m)

Regulations), aff’d sub nom., Am. Forest and Paper Ass’n v. FERC, 550 F.3d 1179, 384

1 While the establishment of a LEO turns on the QF’s actions and such commitment also commits the utility to buy electricity from the QF, the utility has the option of petitioning FERC under 18 C.F.R. § 292.310 for relief from its mandatory purchase obligation. 5 U.S. App. D.C. 73 (D.C. Cir. 2008).2 Upon petitioning, “a non-contractual, but still

legally-enforceable obligation will be created pursuant to the state’s implementation of

PURPA.” JD Wind 1, 129 FERC at 61633.

The Proposed Energy Project

¶8 The proposed energy project at issue in this case is MTSUN’s 80 MW single-axis

tracking solar energy project near Billings, Montana. Since the proposed project is 80

Free access — add to your briefcase to read the full text and ask questions with AI

MTSUN v. PSC, 2020 MT 238 (Mo. 2020).

2020 MT 238 (MTSUN v. PSC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

CED Wheatland v. MPSC
2022 MT 87 (Montana Supreme Court, 2022)
MTSUN v. PSC
2020 MT 238 (Montana Supreme Court, 2020)