Westinghouse Electric Corp. v. Pennsylvania Department of Environmental Protection

745 A.2d 1277, 2000 Pa. Commw. LEXIS 49
CourtCommonwealth Court of Pennsylvania
DecidedFebruary 10, 2000
StatusPublished
Cited by13 cases

This text of 745 A.2d 1277 (Westinghouse Electric Corp. v. Pennsylvania Department of Environmental Protection) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Westinghouse Electric Corp. v. Pennsylvania Department of Environmental Protection, 745 A.2d 1277, 2000 Pa. Commw. LEXIS 49 (Pa. Ct. App. 2000).

Opinion

SMITH, Judge.

Westinghouse Electric Corporation (Westinghouse) petitions for review of the March 26, 1999 order of the Environmental Hearing Board (Board) on remand that assessed penalties and costs of investigation against Westinghouse for violations of The Clean Streams Law, Act of June 22, 1937, P.L. 1987, as amended, 35 P.S. §§ 691.1 — 691.1001, and of regulations of the Department of Environmental Protection (DEP) implementing The Clean Streams Law. Westinghouse questions whether the Board erred in assessing a multimillion-dollar civil penalty under The Clean Streams Law based principally upon its purported deterrent effect. Further, Westinghouse questions whether the penalty “reasonably fit” the violations where those violations were neither willful nor reckless, the violator has expended millions of dollars to remediate the contamination and the penalty assertedly far exceeded other Clean Streams Law penalties assessed for egregious and willful misconduct.

The history of this protracted litigation is detailed in Westinghouse Electric Corp. v. Pennsylvania Department of Environmental Protection (Westinghouse I), 705 A.2d 1349 (Pa.Cmwlth.), appeal denied, 556 Pa. 717, 729 A.2d 1133 (1998). A panel of this Court affirmed the adjudication of the Board which determined that Westinghouse had violated Sections 301, *1279 307(a) and 401 of The Clean Streams Law, 35 P.S. §§ 691.301, 691.307(a) and 691.401, and regulations at 25 Pa.Code §§ 101.2(a), 101.2(b) and 101.3(a). The Court concluded, however, that part of the Board’s penalty analysis was based upon the assumption that all illegal discharges proven resulted in contamination, although the Board had expressly declined to find that all discharges actually contaminated waters. As a result, the Court vacated the Board’s $5,451,238 civil penalty and remanded for calculation of a new penalty based only upon matters that the Board had found to be proven.

To summarize briefly, from 1968 to 1989 Westinghouse manufactured elevators at a plant that it erected near Gettysburg, Pennsylvania. Trichloroethylene (Tri) and 1,1,1-trichloroethane (Ta) were used to degrease parts before painting or welding. On August 16, 1988, the then Department of Environmental Resources (DER) filed a complaint for civil penalties alleging that Westinghouse had unlawfully discharged Tri and Ta. After extensive hearings, the Board determined that Westinghouse had caused: numerous releases from leaking drums of spent degreaser in an old drum storage area outside the plant between 1971 and 1978; leaking of spent degreaser from scrap hoppers on to the railroad loading dock area then running to the soil outside several times a week between 1973 and 1978; at least one release from employees in the welding area pouring spent degreaser onto grass adjacent to the building; a one-time discharge of approximately 50 gallons of Tri and rainwater from a 275-gallon tank onto the ground behind the building; and release of wastewater containing Tri and Ta into a storm drain resulting from cleaning of floor grates from the painting booth.

The Board imposed penalties of $61,500 for violations of Sections 301, 307 and 401 of The Clean Streams Law, $2,677,384 for failure to notify DER and downstream users of releases under 25 Pa. Code § 101.2(a) and $2,677,384 for failure to prevent injury to downstream users by removing residual substances from the ground under 25 Pa.Code § 101.2(b) and failure to take measures to prevent polluting substances from directly or indirectly reaching the waters of the Commonwealth under 25 Pa.Code § 101.3(a). In addition, the Board imposed $35,015 as the cost of investigation, for the total civil penalty of $5,451,238. On remand, the Board assessed the same amounts for violations of The Clean Streams Law and costs and assessed a penalty of $1,600,000 for the violations of 25 Pa.Code § 101.2(a) and an equal amount for the violations of Sections 101.2(b) and 101.3(a) for a new total civil penalty of $3,296,515, or a reduction of $2,154,723.

Westinghouse acknowledges that the only issue before the Court on the current petition for review is the propriety of the two penalties of $1,600,000 each. 1 Westinghouse first asserts that the Board’s “principal motivation” in assessing the penalty of $3,200,000 for violations of the regulations was deterrence. It quotes the Board’s statements that it was concerned that the penalty be “large enough to deter other potential violators” and that it “provide industrial managers with a credible deterrent to failing to comply with the notice and remediation requirements” so as to “convince members of the industrial community that they cannot simply ignore the regulations or write off the resulting penalties as ‘the cost of doing business.’ ” Board’s Remand Adjudication at p. 21. In the Board’s original adjudication, Westinghouse notes, it stated that there was “no basis for considering deterrence if we choose to apply it,” Westing *1280 house Electric Corp. v. Department of Environmental Protection, 1988 E.H.B. 1144, 1289 (1996), 2 and no further evidence of deterrent effect was introduced.

Westinghouse refers to Department of Environmental Resources v. Lawrence Coal Co., 1988 E.H.B. 561, where the Board declined to consider deterrence in fashioning a remedy despite the dramatic effect of acid mine drainage discharges on streams with delicate ecosystems because of the total absence of evidence on which to base a meaningful decision that would act as a deterrent to the violator involved. Westinghouse further asserts that there was no evidence that its conduct was likely to recur or to be committed by others or that unlawful releases of chlorinated solvents such as Tri or Ta are now such a problem as to justify such a harsh penalty for deterrent purposes. It notes that the Board did not characterize its conduct as willful or reckless, and it quotes the opinion of a treatise writer, whose texts are not of record, that it was not until 1981 or even later that the environmental hazards of chlorinated solvents were understood.

DEP has counter-stated the question involved as whether the civil penalty of $8,200,000 is a reasonable fit for the 4356 days during which Westinghouse breached its duty to notify the Department and nearby users of its more than 1000 toxic releases, as well as its failure to take remedial action, its failure to notify promptly resulting in long-term damage and serious health hazards, its hindrance of DEP’s investigation and its effort to remediate only when requested. In essence DEP responds to Westinghouse’s deterrence arguments by pointing out that the number and duration of the violations are primarily responsible for the size of the penalty, which is only slightly over $350 for each day of violation. 3

DEP notes that Section 605(a) of The Clean Streams Law, 35 P.S. § 691.605(a), provides that a civil penalty assessed for a violation of the act or any regulation “may be assessed whether or not the violation was wilful.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Penn Film Group LLC v. Com. of PA, SEC
Commonwealth Court of Pennsylvania, 2023
EQT Prod. Co. v. Dep't of Envtl. Prot.
193 A.3d 1137 (Commonwealth Court of Pennsylvania, 2018)
Office of the District Attorney of Philadelphia v. Bagwell
155 A.3d 1119 (Commonwealth Court of Pennsylvania, 2017)
Pines at West Penn, LLC v. Pennsylvania Department of Environmental Protection
24 A.3d 1065 (Commonwealth Court of Pennsylvania, 2011)
Eureka Stone Quarry, Inc. v. Department of Environmental Protection
957 A.2d 337 (Commonwealth Court of Pennsylvania, 2008)
Sunoco, Inc. v. Department of Environmental Protection
865 A.2d 960 (Commonwealth Court of Pennsylvania, 2005)
City of Erie v. Department of Environmental Protection
844 A.2d 586 (Commonwealth Court of Pennsylvania, 2004)
Leeward Construction, Inc. v. Commonwealth, Department of Environmental Protection
821 A.2d 145 (Commonwealth Court of Pennsylvania, 2003)
Browning-Ferris Industries, Inc. v. Department of Environmental Protection
819 A.2d 148 (Commonwealth Court of Pennsylvania, 2003)
Department of Environmental Protection v. North American Refractories Co.
791 A.2d 461 (Commonwealth Court of Pennsylvania, 2002)
F.R. & S., Inc. v. Department of Environmental Protection
761 A.2d 634 (Commonwealth Court of Pennsylvania, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
745 A.2d 1277, 2000 Pa. Commw. LEXIS 49, Counsel Stack Legal Research, https://law.counselstack.com/opinion/westinghouse-electric-corp-v-pennsylvania-department-of-environmental-pacommwct-2000.