Leeward Construction, Inc. v. Commonwealth, Department of Environmental Protection

821 A.2d 145
CourtCommonwealth Court of Pennsylvania
DecidedApril 2, 2003
StatusPublished
Cited by8 cases

This text of 821 A.2d 145 (Leeward Construction, Inc. v. Commonwealth, Department of Environmental Protection) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Leeward Construction, Inc. v. Commonwealth, Department of Environmental Protection, 821 A.2d 145 (Pa. Ct. App. 2003).

Opinion

OPINION BY

Senior Judge MIRARCHI.

Leeward Construction, Inc. (Leeward) petitions this Court to review the order of the Environmental Hearing Board (Board) assessing a civil penalty of $258,500 against Leeward for violations of The Clean Streams Law. 1 We affirm.

Leeward is an earthmoving contractor and, in 1997-98, was a subcontractor on a project to develop a site for the construction of a Wal-Mart store in Wayne County. The site is in close proximity to Hol-bert Creek, adjacent wetlands, and an unnamed tributary to Holbert Creek. Holbert Creek flows for a short distance from the site into the Lackawaxen River. These waterways have been designated “High Quality, Cold Water Fishery, Migratory Fishery Waters,” and as such are entitled to special protection. 25 Pa.Code § 93.9b; Board’s Finding of Fact No. 22. The project involved the movement of nearly 900,000 cubic yards of silty soils and other earth immediately adjacent to these protected waters.

In July 1996, the Department of Environmental Protection (Department) issued a National Pollutant Discharge Elimination System (NPDES) permit to Wal-Mart authorizing the discharge of storm water from construction activities at the area where the store will be built (Wal-Mart site). The permit requires the implementation of a Department-approved, site-specific erosion and sediment (E & S) control plan. Sediment-laden runoff is defined as pollution in Section 1 of The Clean Streams Law, 35 P.S. § 691.1. 2 Thereafter, the Department modified the permit to allow for discharge of storm water from construction activities at an adjacent 23-acre parcel known as the Waste site. An E & S plan was also required for this site. Approved E & S plans were developed for both the Wal-Mart and Waste sites, which required the construction and maintenance of numerous E & S controls throughout the sites. Because the Wal-Mart store was to be built on the side of a hill, thousands of yards of material needed to be removed from the Wal-Mart site and taken to the Waste site. Also, rock needed to be taken from a third site, called the Borrow site, to repair a slope at the Wal-Mart site.

Wal-Mart hired Milnes Construction Co. as its general contractor, who in turn hired Leeward to conduct earth work at the sites. Leeward became a co-permittee un *148 der the NPDES permit, and thus assumed joint and several liability for all duties and obligations under the permit. Leeward also certified on the co-permittee application:

I certify, under the penalty of law that this transfer agreement was prepared by me or under my direction and supervision. I also acknowledge and agree that the Best Management Practices (BMPs), including the Erosion and Sedimentation (E & S) Control Plan, the Preparedness, Prevention and Contingency (PPC) Plan, and other storm water pollution prevention and minimization strategies already installed for or on behalf of the current permittee will continue to be implemented and maintained. I further acknowledge, under penalty of law, that I have read, understand, and agree to abide by the terms and conditions of the Individual or General NPDES Permit requirements, as applicable, to ensure that water quality standards and effluent limits are attained. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for known violations.

The Department inspected the sites a number of times after work commenced, from September 1997 until January 1998, and found numerous violations regarding Leeward’s failure to install or maintain erosion and sediment control facilities. Nearly half of the project was found to be unprotected by such facilities, and sediment-laden water was being discharged from the sites into the protected waters of the Commonwealth. Accordingly, the Department, on January 16, 1998, issued two compliance orders upon Leeward ordering immediate compliance and revisions to the E & S plans. Leeward did not appeal these orders. The Department later determined that Leeward continued to fail to implement the E & S plans and issued two “stop work orders” upon Leeward on February 20,1998. These orders required the cessation of all construction activity except for those actions necessary to implement and maintain erosion and sediment control facilities. The orders also required additional revisions to the E & S plans. On April 15, 1998, the Department issued another “stop work order” upon Leeward with regard to the Borrow site. The Department determined that Leeward ignored that order.

Leeward appealed the stop work orders to the Board. Following a hearing, the Board dismissed Leeward’s appeal on June 13, 2000, finding that the project was causing polluted discharges and that Leeward failed to comply with the unappealed compliance orders. Thereafter, the Department filed a complaint against Leeward requesting the Board assess civil penalties as authorized by The Clean Streams Law. Following a hearing, the Board found significant noncompliance with erosion and sediment control by Leeward and the Board issued an adjudication assessing a total of $258,500 of civil fines. The fines were delineated as follows: $109,000 for Leeward’s chronic failure to install and maintain effective erosion and sediment control facilities and for operating without an approved E & S plan; $49,000 for Leeward’s discharge of sediment pollution into the waters of the Commonwealth; and $100,000 for Leeward’s deliberate violations of the Department’s stop work orders. This petition for review followed.

This Court’s scope of review is limited to whether the Board’s findings of fact are supported by substantial evidence and whether constitutional violations or errors of law were committed. Martin v. Department of Environmental Resources, 120 Pa.Cmwlth. 269, 548 A.2d 675 (1988). 3 *149 In reviewing the Board’s penalty assessments, this Court may not substitute its judgment for that of the Board, and so long as the penalties reasonably fit the violations, the Board must be upheld. Id. Further, credibility determinations are made by the Board as fact finder. Id.

Leeward raises the following issues: (1) whether the penalty is reasonable in relation to Leeward’s conduct; (2) whether the Board erred by allegedly refusing to allow Leeward to introduce evidence of its costs and expenses incurred in attempting to comply with the Department’s orders and maintaining erosion and sedimentation controls; (8) whether Leeward’s conduct was negligent as opposed to reckless or intentional, as found by the Board; (4) whether the Board erred by finding that E & S plans were “professional guesswork” with uncertain results; and (5) whether the Board erred by not considering the “fact” that the Department approved a defective E & S plan prior to Leeward’s involvement. Leeward argues these issues in somewhat reverse order as they are stated, however, and we shall address them in the order raised in the Argument section of Leeward’s brief.

At the outset, it must be observed that the Board’s decision is detailed, thorough, and exhaustive.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brandywine Village Associates, L.P. v. DOT
Commonwealth Court of Pennsylvania, 2025
H. Becker v. DEP
Commonwealth Court of Pennsylvania, 2017
Pines at West Penn, LLC v. Pennsylvania Department of Environmental Protection
24 A.3d 1065 (Commonwealth Court of Pennsylvania, 2011)
Stambaugh v. Department of Environmental Protection
11 A.3d 30 (Commonwealth Court of Pennsylvania, 2010)
Bishops, Inc. v. Penn National Insurance
984 A.2d 982 (Superior Court of Pennsylvania, 2009)
Capital Bluecross v. Pennsylvania Insurance Department
937 A.2d 552 (Commonwealth Court of Pennsylvania, 2007)
R.L. Insulation Co. v. Prevailing Wage Appeals Board
923 A.2d 550 (Commonwealth Court of Pennsylvania, 2007)
Groce v. Department of Environmental Protection
921 A.2d 567 (Commonwealth Court of Pennsylvania, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
821 A.2d 145, Counsel Stack Legal Research, https://law.counselstack.com/opinion/leeward-construction-inc-v-commonwealth-department-of-environmental-pacommwct-2003.