F.R. & S., Inc. v. Department of Environmental Protection

761 A.2d 634, 2000 WL 1283804
CourtCommonwealth Court of Pennsylvania
DecidedDecember 1, 2000
Docket1512 C.D. 1999
StatusPublished
Cited by1 cases

This text of 761 A.2d 634 (F.R. & S., Inc. v. Department of Environmental Protection) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
F.R. & S., Inc. v. Department of Environmental Protection, 761 A.2d 634, 2000 WL 1283804 (Pa. Ct. App. 2000).

Opinion

FLAHERTY, Judge.

F.R. & S., Inc., doing business as Pioneer Crossing Landfill (Pioneer) petitions for review from an adjudication of the Environmental Hearing Board (EHB) which affirmed a civil penalty of $334,500.00 assessed by the Department of Environmental Protection (Department) against Pioneer for violations of the Solid Waste Management Act (Act) 1 Department regulations and Pioneer’s facilities permit. We affirm.

Pioneer owns a municipal waste landfill which operates under a Solid Waste Permit issued by the Department. The landfill is approximately 92.4 acres in size and is located in a residential area. Approximately fifteen acres in an older section of the landfill are at issue in this case.

In August 1994, the Department determined that disposal was complete in the older portion of the landfill and notified Pioneer that under the Department’s regulations Pioneer was obligated to cap the fifteen acres in the older portion within *636 one year. In September 1995, Pioneer requested an extension of time in which to cap the fifteen acre portion of the landfill. When requesting the extension, Pioneer assured the Department that the project could be started around July 1, 1996 and be completed by September 15, 1996. In response, the Department modified Pioneer’s permit to require that the capping be completed by December 31, 1996 and that a gas extraction system be installed in conjunction with the cap because of the potential for gas migration. The gas extraction system had to first be approved by the Department before being installed and Pioneer was aware that Department approval was needed.

During 1996, various inspections of Pioneer’s landfill were conducted by the Department. In addition, letters were sent to Pioneer inquiring about the capping plan and discussions were held with Pioneer concerning the capping plan. On October 4, 1996, the Department issued an Administrative Order to Pioneer requiring, among other things, that Pioneer submit an application for plan approval of the gas management system for the acreage in question within fourteen days. This order was not appealed by Pioneer and a plan was submitted. On November 6,1996, the Department issued another Administrative Order requiring Pioneer to install gas collection wells within twenty days, in accordance with the plan it had submitted to the Department in October. Pioneer did not appeal this order.

Also, during 1996 and 1997 odors emanated from the landfill causing nearby residents to complain. 2 In addition, a Department witness testified that the gas levels at the landfill during this time presented a potential danger to the adjacent structures and occupants of nearby properties. During an August 26, 1996 inspection, samples from Pioneer’s gas monitoring wells indicated that the wells contained explosive levels of combustible methane gas. These problems were attributed to the fact that Pioneer had not installed a gas ventilation system in the fifteen acre portion of the landfill which was to be capped.

Pioneer did not complete the required capping project on the fifteen acres in question by the December 31, 1996 deadline set by the Department. The capping project was finally certified as completed on May 12,1997.

On October 14, 1997, the Department issued a civil penalty of $352,000.00 against Pioneer which, in part, imposed a $315,000.00 penalty for missing the December 31, 1996, capping deadline. 3 Pursuant to 25 Pa.Code § 271.411(d)(2) the Department is required to issue a civil penalty against a person who fails to cap its landfill within the time required by applicable regulations and the approved operation plan.

Pioneer appealed to the EHB. 4 Pioneer did not dispute that a civil penalty was appropriate in this instance because it admitted that it did miss the capping deadline. However, Pioneer did dispute whether the $315,000.00 penalty for missing the capping deadline was reasonable. The *637 EHB affirmed the $315,000.00 civil penalty for missing the capping deadline. However, it reduced the overall penalty from $352,000.00 to $334,500.00. 5 Pioneer then petitioned this Court for review of the reasonableness of the $315,000.00 portion of the penalty for missing the capping deadline.

Pioneer raises two issues for our review related to the reasonableness of the penalty. First, Pioneer asks whether the EHB committed an error of law by excluding relevant evidence relating to the reasonableness of the assessed penalty for missing the capping deadline, and second, it asks whether the EHB committed an error of law by failing to make sufficient findings of fact necessary to resolve issues raised by the evidence which are relevant to the reasonableness of the assessed penalty. 6

First, Pioneer argues that the EHB erred when it would not allow Pioneer to introduce evidence at the hearing concerning other landfills in the same region that had missed their capping deadlines by periods of time in excess of the number of days that Pioneer had missed its deadline, but were assessed no penalty or a smaller penalty than Pioneer. The Department argues that Pioneer has waived review of this issue because the EHB granted the Department’s motion for summary judgment on the issue of discriminatory enforcement and Pioneer did not specifically raise the summary judgment issue before this Court. After review of the record we must agree with the Department.

The record indicates that Pioneer raised in its notice of appeal to the EHB the issue of discriminatory enforcement, ie. that the Department did not assess other landfills in the region penalties in the amount that Pioneer had been assessed. The Department filed a motion for summary judgment on the issue of discriminatory enforcement. In a decision and order dated September 3, 1998, the EHB granted the Department’s motion for summary judgment on the issue of discriminatory enforcement finding that Pioneer had not provided any evidence that these other landfills were significantly similar to Pioneer. The EHB also found that all Pioneer had shown was that under different facts and circumstances the Department acted differently in prosecuting two other landfills.

Again at the hearing before the EHB, Pioneer attempted to introduce evidence that other landfills had been treated differently by the Department in assessing penalties and had been given lower penalties. Again, the EHB denied the admission of the evidence because the issue had already been decided by the grant of the motion for summary judgment.

In its brief to this Court Pioneer makes no mention of the Department’s motion for summary judgment, the EHB’s grant of that motion or that the grant of summary judgment was in error. It is not in the procedural or factual history, in the Statement of Questions for Review or in the Argument section of the brief.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sunoco, Inc. v. Department of Environmental Protection
865 A.2d 960 (Commonwealth Court of Pennsylvania, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
761 A.2d 634, 2000 WL 1283804, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fr-s-inc-v-department-of-environmental-protection-pacommwct-2000.