Sunoco, Inc. v. Department of Environmental Protection

865 A.2d 960, 2005 Pa. Commw. LEXIS 14
CourtCommonwealth Court of Pennsylvania
DecidedJanuary 7, 2005
StatusPublished
Cited by9 cases

This text of 865 A.2d 960 (Sunoco, Inc. v. Department of Environmental Protection) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sunoco, Inc. v. Department of Environmental Protection, 865 A.2d 960, 2005 Pa. Commw. LEXIS 14 (Pa. Ct. App. 2005).

Opinion

OPINION BY Senior

Judge JIULIANTE.

Sunoco, Inc. (R&M) (hereinafter “Suno-co”) petitions for review of the April 12, 2004 order of the Environmental Hearing Board (EHB) that denied Sunoco’s appeal from a $3,465,660 civil penalty assessed under Section 9.1 of the Air Pollution Control Act (APCA) 1 based upon Sunoco’s failure to install Reasonably Available Control Technology (RACT) on a timely basis on Boilers 6 and 7 at its Marcus Hook Refinery in Delaware County. For the reasons that follow, we affirm.

Sunoco’s Marcus Hook Refinery (the Facility) is located within the Philadelphia Consolidated Metropolitan Statistical Area, which has been classified as a severe ozone non-attainment area. The Facility is a major emitter of nitrogen oxide compounds (NOx), which are subject to the RACT control program.

History of RACT Program

The RACT program, which has its origin in the 1990 amendments to the Clean Air Act, 2 is a statutory program designed to reduce ground level ozone by controlling emissions of two ozone precursors, NOx and volatile organic compounds (VOC). The States were required to submit their proposed RACT regulatory provisions to the Environmental Protection Agency (EPA) by November 1992 and to provide for implementation of the required measures by May 31,1995.

The Department of Environmental Protection (Department) published its proposed RACT regulations in August 1992 and ultimately promulgated its revised RACT regulations in January 1994. 3 The Department’s RACT program is focused on technology rather than emission limits. Under the program, a RACT determination is made for the use of a specific control technology for each individual affected source.

The Department’s RACT regulations require the operator of an affected facility to identify the sources to which the regulations apply and to ascertain through emission testing the total potential to emit and the actual emissions of NOx and VOC for the 1990 calendar year for each source at the facility. In other words, a baseline emission rate for both potential and actual emissions must be established for each source.

By July 15, 1994, each operator of a major NOx or VOC emitting facility was required to submit a written proposal to the Department designating the operator’s preferred RACT for each affected source in the facility based upon a technical and economical analysis set forth in the regulations. Each RACT proposal was required to contain proper supporting documentation, a proposed schedule for implementing the RACT for each source, proposed testing procedures and an application for a plan approval and an operating permit.

The Department reviewed each RACT proposal and either approved, denied or modified the RACT selected for each source by the operator. After an operator received the Department’s determination of the appropriate RACT for each source, *963 the operator was required to install the RACT.

Sunoco’s RACT Compliance History

In the present case, Sunoco operates two industrial boilers at the Facility, ie., Boiler 6 and Boiler 7, which are the focus of the penalty assessment. Both boilers are NOx sources. In January 1994, Suno-co hired two consultants, an environmental firm and an engineering firm, to prepare a RACT proposal for the Facility. In July 1994, Sunoco’s environmental consultant submitted Sunoco’s initial RACT proposal. Sunoco’s RACT proposal was given high priority by the Department.

Sunoco’s 1994 RACT proposal listed eight potential control options, which included the installation of ultra-low NOx burners (ULNB) and low NOx burners (LNB) on Boilers 6 and 7. Sunoco’s preferred NOx RACT on Boilers 6 and 7 was combustion tuning, which involves only adjustments and upgrades to the current combustion system. Combustion tuning, however, was the least effective RACT for the two boilers.

Sunoeo’s July 1994 RACT proposal indicated a “control efficiency” for ULNB (reduction of NOx emissions) on Boiler 6 of 75% when the boiler was burning fuel gas, and 14% when burning fuel oil. For Boiler 7, which burned only fuel gas, the control efficiency was estimated at 75%. 4 Suno-co’s 1994 proposal also indicated that the cost for installing ULNB on Boilers 6 and 7 would be $1,550,554 for each boiler.

The Department determined that as a guideline, the appropriate RACT to be implemented for each source would be the control option that obtained the greatest control efficiency while not exceeding a cost effectiveness ratio of $1,500 per ton. Sunoco was aware at all times relevant to its 1994 RACT proposal that the Department had adopted the $1,500 guideline threshold for the RACT cost effectiveness ratio.

Although Sunoco’s July 1994 proposal calculated the ULNB control option at $1,516 per ton, the Department corrected an error in the calculation that resulted in a cost effectiveness ratio well below the $1,500 per ton guideline. Sunoco subsequently submitted a revised September 1994 RACT proposal indicating a ULNB cost effectiveness ratio of $1,202 per ton for Boiler 6 and $810 per ton for Boiler 7.

Nevertheless, Sunoco indicated in its September 1994 proposal that its first choice would be to install LNB as the control option on both boilers. The cost effectiveness ratio for LNB on Boiler 6 was $1,183 per ton on Boiler 6 and $815 per ton on Boiler 7. The control efficiency for LNB on both boilers was 50% (compared to 75% for ULNB).

Sunoco’s proposal was reviewed by George Monasky, an air pollution engineer for the Department. Monasky determined that ULNB should be installed on both boilers. On June 8, 1995, the Department issued Sunoco a final plan approval and compliance permit (1995 Plan Approval and Permit). The 1995 Plan Approval and Permit required Sunoco to install six ULNB on Boiler 6 and four ULNB on Boiler 7. That approval and permit also required installation by May 31,1996. Su-noco did not appeal from the 1995 Plan Approval and Permit.

Sunoco, nonetheless, failed to comply with the 1995 Plan Approval and Permit. On July 12, 1995, Sunoco submitted a re *964 vised RACT analysis which stated that Sunoco was withdrawing its application for ULNB. Monasky, however, did not find Sunoco’s analysis to be reasonable. In April 1996, Sunoco performed another RACT analysis which indicated a cost of between $800,000 and $900,000 for both boilers with a control efficiency of only 36%.

In May 1996, Sunoco became aware of a control technology known as “spud burners.” 5 Sunoco proffered the spud burner technology to the Department as an alternative to ULNB. In late May 1996, Sunoco submitted a revised RACT analysis proposing the installation of spud burners on Boiler 7. Sunoco submitted a plan approval application for the spud burners, but did not include any supporting documents.

In any event, Sunoco had done nothing to comply with the 1995 Plan Approval and Permit, which expired in November 1996. The Department did not extend or reissue the 1995 Plan Approval.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Senator K. Muth v. DEP & Eureka Resources, LLC (EHB)
Commonwealth Court of Pennsylvania, 2024
MOSS v. SAL LAPIO, INC.
E.D. Pennsylvania, 2020
United Refining Co. v. Department of Environmental Protection
163 A.3d 1125 (Commonwealth Court of Pennsylvania, 2017)
Lower Salford Township Authority v. Department of Environmental Protection
67 A.3d 50 (Commonwealth Court of Pennsylvania, 2013)
City of Philadelphia v. Int'l Ass'n of Firefighters, Local 22
29 Pa. D. & C.5th 35 (Philadelphia County Court of Common Pleas, 2013)
Eureka Stone Quarry, Inc. v. Department of Environmental Protection
957 A.2d 337 (Commonwealth Court of Pennsylvania, 2008)
Groce v. Department of Environmental Protection
921 A.2d 567 (Commonwealth Court of Pennsylvania, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
865 A.2d 960, 2005 Pa. Commw. LEXIS 14, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sunoco-inc-v-department-of-environmental-protection-pacommwct-2005.