Birdsboro & Birdsboro Municipal Authority v. Department of Environmental Protection

795 A.2d 444
Commonwealth Court of Pennsylvania·Decided March 28, 2002·Published·Cited by 14 cases

Opinion

ORDER

OPINION BY

Judge LEADBETTER.

AND NOW, this 28th day of March, 2002, it is ordered that the opinion filed January 31, 2002, shall be designated OPINION rather than MEMORANDUM OPINION, and that it shall be reported.

Birdsboro and Birdsboro Municipal Authority (petitioners) petition for review from an order of the Environmental Hearing Board (EHB) wherein EHB affirmed the decision of the Pennsylvania Department of Environmental Protection (DEP) to grant Haines and Kibblehouse, Inc. (H & K) a noncoal mining permit. For the following reasons, we affirm.

On July 31, 1997, H & K applied to the DEP for a noncoal mining permit for the Birdsboro Materials Quarry Site in Birds-boro. While the permit was pending, DEP designated the area as an Exceptional Value Watershed. 2 To be approved, DEP therefore required the proposed mining operation to be redesigned significantly. Among other alterations, DEP required H & K to raise the floor of a section of the mine and to split the mine into two geographic and temporal sections, Phase 1 and Phase 2. On March 4, 1999, DEP issued H & K a permit to begin mining with 35 special conditions. In special condition 30, DEP prohibits H & K from mining in Phase 2 until and unless H & K produces evidence that Phase 1 mining did not damage wetlands, surface water, or groundwater. 3 In special condition 33, DEP requires H & K to notify petitioners via certified mail when H & K formally seeks DEP permission to begin Phase 2.

Petitioners appealed to the EHB from DEP’s decision to grant a permit. The EHB held hearings wherein all parties presented extensive testimony regarding the mining area. Petitioners presented the testimony of Philip Getty, an environmental hydrologist. 4 Mr. Getty reviewed the permit application and other pertinent materials and performed independent re *447 search. He concluded, inter alia, that mining in Phase 2 will damage the environment by decreasing the area’s water quantity. Mr. Getty based his conclusion in part on test results obtained from a water pumping test performed adjacent to the mining site. Specifically, Mr. Getty calculated that if mining took place as planned under the permit, forty-six percent of the water currently flowing into the wetlands and stream channels around the mines will be effectively diverted. 5

H & K countered Mr. Getty’s testimony with the testimony of John Ross, a civil engineer with H & K, and Jeffrey Peffer, an expert in the fields of geology and hydrology. 6 Mr. Ross disputed Mr. Getty’s calculations, testifying that under Mr. Getty’s theory, only nineteen percent of the water would be diverted. Mr. Peffer testified that he disagreed with Mr. Getty’s conclusions regarding water loss, including those based on the pumping tests. The EHB credited Mr. Ross’s and Mr. Peffer’s testimony and found as fact that “H & K’s mining will not lower the water level,” Finding of Fact 57, and it will “increase the base flow of water,” Finding of Fact 58.

On appeal to this court, petitioners present four issues for our consideration. First, petitioners assert that the EHB improperly disregarded allegedly uncontested portions of Mr. Getty’s testimony without sufficient reason or explanation. Second, petitioners assert that DEP improperly applied 25 Pa.Code § 77.126(a)(3), arguing H & K failed to provide adequate proof that its mining activities would not cause pollution. Third, petitioners assert that DEP violated their due process rights by attaching permit conditions contingent upon future events that are incapable of being addressed in the current appeal or in later litigation. Finally, petitioners argue that EHB violated their due process rights because the ALJ who heard the evidence did not write the adjudication. We address petitioners’ arguments seriatim.

Petitioners’ first argue that Mr. Getty’s testimony regarding water loss in Phase 2 went uncontested and that therefore the EHB erred by not finding as fact that water loss will occur. Additionally, petitioners argue that the EHB erred by not adequately explaining why Mr. Getty’s testimony was not credited over Mr. Peffer’s. It is axiomatic that “[questions of resolving conflicts in the evidence, witness credibility, and evidentiary weight are properly within the exclusive discretion of the fact finding agency, and are not usually matters for a reviewing court.” Pennsylvania Game Comm’n v. Dep’t of Envtl. Res., et al., 97 Pa.Cmwlth. 78, 509 A.2d 877, 880 (1986). Petitioners fail to recognize that we do not accept invitations to reevaluate evidence and credibility determinations. Even assuming arguendo that Mr. Getty’s testimony was not contradicted, the EHB is not under an obligation to accept it. 7 See Feldbauer v. Dep’t of Pub. Welfare, 106 Pa.Cmwlth. 87, 525 A.2d 837, 839 (1987). Additionally, the EHB need *448 not provide specific reasons for finding one witness credible over another. 8 See Sherrod v. Workmen’s Comp. Appeal Bd. (Thoroughgood, Inc.), 666 A.2d 383, 385 (Pa.Cmwlth.1995).

Petitioners next argue that DEP erred in interpreting and applying 25 Pa. Code § 77.126(a)(3). That section reads as follows:

Criteria for permit approval or denial.
(a) A permit, permit renewal or revised permit application will not be approved, unless the application affirmatively demonstrates and the Department finds in writing, on the basis of the information in the application or from information otherwise available, that the following apply:
(3) The applicant has demonstrated that there is no presumptive evidence of potential pollution of the waters of this Commonwealth.

Free access — add to your briefcase to read the full text and ask questions with AI

Birdsboro & Birdsboro Municipal Authority v. Department of Environmental Protection, 795 A.2d 444 (Pa. Ct. App. 2002).

795 A.2d 444 (Birdsboro & Birdsboro Municipal Authority v. Department of Environmental Protection) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Gibraltar Rock, Inc. v. PA DEP
Commonwealth Court of Pennsylvania, 2024
D.C. v. DHS
Commonwealth Court of Pennsylvania, 2022
A.A. Jalil v. DHS
Commonwealth Court of Pennsylvania, 2021
United Refining Co. v. Department of Environmental Protection
163 A.3d 1125 (Commonwealth Court of Pennsylvania, 2017)
W.K. Baker v. DEP
Commonwealth Court of Pennsylvania, 2017
Maxatawny Twp. v. DEP
Commonwealth Court of Pennsylvania, 2015
Lower Salford Township Authority v. Department of Environmental Protection
67 A.3d 50 (Commonwealth Court of Pennsylvania, 2013)
Berks County v. Department of Environmental Protection
894 A.2d 183 (Commonwealth Court of Pennsylvania, 2006)
Sunoco, Inc. v. Department of Environmental Protection
865 A.2d 960 (Commonwealth Court of Pennsylvania, 2005)
Eagle Environmental, L.P. v. Department of Environmental Protection
833 A.2d 805 (Commonwealth Court of Pennsylvania, 2003)
Frye v. Workers' Compensation Appeal Board
823 A.2d 1063 (Commonwealth Court of Pennsylvania, 2003)
Leatherwood, Inc. v. Commonwealth, Department of Environmental Protection
819 A.2d 604 (Commonwealth Court of Pennsylvania, 2003)