Leatherwood, Inc. v. Commonwealth, Department of Environmental Protection

819 A.2d 604, 2003 Pa. Commw. LEXIS 156
CourtCommonwealth Court of Pennsylvania
DecidedMarch 18, 2003
StatusPublished
Cited by18 cases

This text of 819 A.2d 604 (Leatherwood, Inc. v. Commonwealth, Department of Environmental Protection) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Leatherwood, Inc. v. Commonwealth, Department of Environmental Protection, 819 A.2d 604, 2003 Pa. Commw. LEXIS 156 (Pa. Ct. App. 2003).

Opinion

OPINION BY

Judge SIMPSON.

Leatherwood, Inc. (Leatherwood) appeals an order of the Environmental Hearing Board (EHB) revoking the executory solid waste permit (Permit) issued by the Department of Environmental Protection (DEP) to permit construction and operation of a solid municipal waste landfill (Landfill) near DuBois — Jefferson County Airport (Airport). Agreeing that DEP failed to properly resolve a known risk of bird/aircraft collisions, we affirm revocation of the permit.

I.

The complex procedure of this litigation requires explanation. In May 1995, DEP issued the executory Permit to Leather-wood pursuant to its authority under the Solid Waste Management Act (SWMA). 1 The Jefferson County Commissioners, the Jefferson County Solid Waste Authority, and Clearfield Jefferson Counties Regional Airport Authority (collectively Local Government Officials) responded by filing an appeal of the Permit, the first appeal involving the Permit.

In 1996, Congress enacted the Federal Aviation and Reauthorization Act of 1996 (FARA), regulating, among other things, the placement of landfills near airports. Section 1220(d) of FARA, 49 U.S.C. § 44718(d), prohibited Leatherwood from constructing the Landfill. After the enactment of FARA, DEP issued an order suspending Leatherwood’s Permit. Leather-wood appealed DEP’s suspension order to the EHB, the second appeal.

Another landfill operator with a landfill near the Airport challenged the constitutionality of Section 1220(d) of FARA. Both appeals were stayed pending that separate but significant litigation. Ultimately, Congress enacted legislation substantially modifying Section 1220(d) of FARA. As a result, DEP revoked its prior suspension order and issued a second suspension order. The new order suspended the Permit indefinitely while DEP decided whether to approve a bird hazard mitigation plan submitted by Leatherwood.

Thereafter, the EHB consolidated the first appeal by Local Government Officials from the issuance of the Permit with the second appeal by Leatherwood from the *607 suspension of the Permit. The EHB postponed a hearing on the merits of the appeals pending consideration of a revised bird hazard mitigation plan. In January 2001, although DEP had yet to render a decision on the mitigation plan, the EHB began to conduct hearings on the first appeal.

Administrative Law Judge Michelle A. Coleman presided over 28 days of hearings on the merits and conducted an extensive site view. Thereafter, the EHB issued a thorough and thoughtful opinion setting forth detailed findings summarized below.

II.

The proposed Landfill consists of approximately 650 acres located in a sparsely populated area in the northeast corner of Pinecreek Township, Jefferson County. The eastern perimeter of the Landfill disposal area would lie approximately 12,600 feet from the western end of the Airport’s sole runway, and the entire disposal area would range between 12,500 and 15,500 feet from the western end of the runway. The Landfill would accept waste generated in Armstrong County, Pennsylvania and in the New York City metropolitan area.

Pursuant to federal regulations, owners or operators of new or existing municipal waste landfills within 10,000 feet of any airport runway end that is used by turbo jet aircraft “must demonstrate that the [landfill] units are designed and operated so that the [landfill] unit does not pose a bird hazard to aircraft.” 40 C.F.R. § 258.10(a) (1995). “Bird hazard” means “an increase in the likelihood of bird/aircraft collisions that may cause damage to the aircraft or injury to its occupants.” 40 C.F.R. § 258.10(d)(2) (1995).

Federal Aviation Administration (FAA) Order 5200.5A provides guidance concerning establishment of waste disposal facilities in the vicinity of airports. Pursuant to FAA Order 5200.5A, a waste disposal facility is considered incompatible with safe flight operations if it is located “within a 5 mile radius of a runway end,” and the facility “attracts or sustains hazardous bird movements from feeding, water or roosting areas into or across the runways and/or approach and departure patterns of aircraft.”

In 1991, Leatherwood notified the FAA of its intent to construct the Landfill within 12,500 to 15,500 feet of the Airport’s runway. In response, the FAA conducted an evaluation of the proposed site and communicated its negative findings to Leatherwood (FAA Review Letter).

Pursuant to SWMA regulations then existing, Leatherwood was required to include an environmental assessment with a detailed analysis of the potential impacts of the proposed facility on the environment and public health and safety. 25 Pa.Code 271.127(a) (1995). DEP, after consultation with appropriate governmental agencies and potentially affected persons, was required to evaluate the environmental assessment to determine whether a threat to the environment or public health and safety was present. 25 Pa.Code § 271.127(b) (1995). If DEP or Leatherwood determined the Landfill could cause harm, Leatherwood was required to provide a written explanation of how it planned to mitigate the harm, through alternatives to the design or siting of the facility or other appropriate measures. 25 Pa.Code § 271.127(c) (1995).

Leatherwood’s 1994 application included an environmental assessment, but did not identify the bird hazard as a potential harm. The assessment also failed to provide any analysis of the likelihood of a bird/aircraft collision. In addition, the application did not identify attraction of birds as a potential nuisance, and the nuisance *608 control plan submitted with the Application did not address birds in any way. Further, the application did not contain any analysis of the Landfill’s potential to attract bird movements into or across the approach and departure patterns of aircraft using the Airport. Also, the application did not contain any analysis of the likelihood of birds striking aircraft that use the Airport.

During its review of the Application, DEP personnel determined the potential for bird/aircraft collisions could significantly increase with activity at the proposed Landfill. Consequently, DEP determined the Landfill posed a threat to public safety. DEP based its determination on the negative FAA Review Letter, testimony by officials from the Pennsylvania Department of Transportation (PennDOT) Bureau of Aviation and USAir executives, oral and written correspondence from the FAA and PennDOT Bureau of Aviation.

Regulations in effect at the time placed the burden on the applicant to provide an adequate, site — specific environmental assessment. Prior to issuing the Permit, however, DEP did not require Leather-wood to provide any analysis quantifying the bird hazard. In addition, DEP did not engage an expert on birds and landfill operations to analyze the perceived harm posed by the bird hazard. Further, although DEP identified the bird hazard as a significant threat, it did not require Leatherwood to submit a bird hazard mitigation plan.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

West Rockhill Twp v. DEP; Apl of: Adelphia Gateway
Supreme Court of Pennsylvania, 2025
West Rockhill Twp v. DEP, Aplt.
Supreme Court of Pennsylvania, 2025
Cole, C. v. DEP; Apl of: Adelphia Gateway
Supreme Court of Pennsylvania, 2025
Cole, C. v. DEP, Aplt.
Supreme Court of Pennsylvania, 2025
Gibraltar Rock, Inc. v. PA DEP
Commonwealth Court of Pennsylvania, 2024
Reading School District v. I-Lead Charter School
206 A.3d 27 (Commonwealth Court of Pennsylvania, 2019)
Lester v. Department of Environmental Protection
153 A.3d 445 (Commonwealth Court of Pennsylvania, 2017)
Berks County v. Department of Environmental Protection
894 A.2d 183 (Commonwealth Court of Pennsylvania, 2006)
Delaware Riverkeeper v. Department of Environmental Protection
879 A.2d 351 (Commonwealth Court of Pennsylvania, 2005)
Pennsylvania Trout v. Department of Environmental Protection
863 A.2d 93 (Commonwealth Court of Pennsylvania, 2004)
Baehler v. Department of Environmental Protection
863 A.2d 57 (Commonwealth Court of Pennsylvania, 2004)
Eagle Environmental, L.P. v. Department of Environmental Protection
833 A.2d 805 (Commonwealth Court of Pennsylvania, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
819 A.2d 604, 2003 Pa. Commw. LEXIS 156, Counsel Stack Legal Research, https://law.counselstack.com/opinion/leatherwood-inc-v-commonwealth-department-of-environmental-protection-pacommwct-2003.