Concerned Residents of Yough, Inc. v. Deparment of Environmental Resources

639 A.2d 1265, 162 Pa. Commw. 669, 1994 Pa. Commw. LEXIS 136
CourtCommonwealth Court of Pennsylvania
DecidedMarch 28, 1994
StatusPublished
Cited by5 cases

This text of 639 A.2d 1265 (Concerned Residents of Yough, Inc. v. Deparment of Environmental Resources) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Concerned Residents of Yough, Inc. v. Deparment of Environmental Resources, 639 A.2d 1265, 162 Pa. Commw. 669, 1994 Pa. Commw. LEXIS 136 (Pa. Ct. App. 1994).

Opinion

McGINLEY, Judge.

Concerned Residents of the Yough (CRY) and Westmoreland County (County) appeal from a determination of the Environmental Hearing Board (EHB) holding that section 503 of the Solid Waste Management Act (SWMA), Act of July 7, 1980, P.L. 97, as amended 35 P.S. §§ 6018.101-6018.1003, did not bar the Department of Environmental Resources (DER) from issuing a solid waste disposal permit to Mill Service, Inc. (Mill Service) for construction of a residual waste impoundment at its waste storage and treatment facility in Yukon, Pennsylvania (Yukon facility), and that the DER did not abuse its discretion in issuing this permit, or other related permits.1

Mill Service is engaged in the business of treatment and storage of residual industrial waste, initially at a disposal facility in Bulger, Pennsylvania (Bulger facility), and since 1964, at the Yukon facility. The wastes, consisting primarily of pickle liquor sludge from the iron and steel industry, are stored [1268]*1268in reservoirs known as impoundments. After the enactment of the Federal Resource Conservation and Recovery Act, 42 U.S.C. §§ 6901-6992k, and Pennsylvania’s subsequent adoption of SWMA, Mill Service qualified as an interim service facility for the storage and treatment of hazardous waste. In 1983, Mill Service applied to DER for a hazardous waste disposal permit under SWMA. However, in 1984, DER determined that wastes had leached from Mill Service’s impoundments, particularly Impoundment No. 5, and contaminated groundwater from the Pittsburgh Coal Aquifer and the Red-stone Coal Aquifer.2

On April 19, 1985, while DER and Mill Service were negotiating a settlement, Mill Service submitted an application to construct and operate a sixth impoundment as a residual waste disposal facility. Effective May 24, 1985, Mill Service and the DER entered into a consent order which recognized Mill Service’s violations of certain provisions of the SWMA and the Clean Streams Law, Act of June 22,1937, P.L.1987, os amended, 35 P.S. §§ 691.1-691.1001, and provided a schedule for abating the contamination. The order stated that the DER had determined that on March 7, 1983, and thereafter, dike seepage from Impoundment No. 5 had discharged into the surface and/or groundwater on at least four occasions resulting in contamination. The order further stated that analysis of the dike wall revealed that waste could migrate, or leach, through the wall, although the system was considered presently stable. Consent Order at 5; R.R. at 292a. The order directed Mill Service to: withdraw its application for a hazardous waste disposal permit for Impoundment No. 5; stop depositing new wastes into Impoundment No. 5 by June 30, 1985; follow an approved closure plan for Impoundment No. 5; post a bond to guarantee proper closure of Impoundment No. 5; operate and maintain a leachate collection and treatment system for thirty years after the closure of Impoundment No. 5; monitor groundwater in the Redstone Coal Aquifer and the Pittsburgh Limestone Aquifer and maintain contaminant concentrations at background levels set forth in an appendix to the order; operate an abatement plan to remediate contamination in the Pittsburgh Coal Aquifer; and contribute $200,000 toward the installation of a public water line for the use of private citizens. The consent order also provided that execution of the order and an order of the same date relating to the Bulger facility placed Mill Service in compliance with Section 503 of SWMA so that DER need not deny issuance of the permits, licenses or permit amendments to which Mill Service was otherwise entitled. Consent Order, May 24, 1985, (Consent Order) at 22-23; Reproduced Record (R.R.) at 309a-310a. Although individual members of the Yukon community raised objections to the consent order the order was not appealed.

On August 6, 1986, after a review of Mill Service’s compliance history, DER issued Solid Waste Disposal Permit No. 301071 to Mill Service for the construction and operation of a surface impoundment to be known as Impoundment No. 6. CRY and the County separately appealed the issuance of this permit to the EHB. They also challenged the issuance of the following permits issued the same date in connection with the solid waste disposal permit: Water Obstructions and Encroachment Permit No. E65-164, Dam Safety Permit No. D65-153, and Earth Disturbance Permit No. (65) 65-84-8-2. The appeals of CRY and the County were consolidated at Docket No. 86-513-MJ on August 31, 1990.

Before the EHB both CRY and the County argued that pursuant to the language of Section 503 of SWMA, the DER was under a mandatory duty to deny the permit for Im-poundment No. 6 since hazardous waste leachate from Impoundment No. 5 continued to be discharged into the groundwater without a permit after the execution of the consent order and at the time of the issuance of the permit. The County further alleged that the permit should have been denied because the violations which led to the consent order demonstrated that Mill Service was unable to [1269]*1269comply with environmental regulations. CRY additionally raised concerns about air pollution and contended that the issuance of the permit violated Article 1, Section 27 of the Pennsylvania Constitution because the environmental harm to be reasonably expected from the construction and operation of Impoundment No. 6 clearly outweighs any economic benefit. CRY and the County both contend that the amount of the bond and public liability insurance set by DER are grossly inadequate.

On August 6, 1990, Mill Service filed a motion in limine to preclude CRY from offering evidence regarding events which had taken place after the date the permits were issued, to preclude evidence regarding violations which were resolved in the 1985 consent order and to preclude evidence regarding the siting of the Yukon facility. This motion was granted on September 17, 1990.

The EHB conducted a hearing from September 26, 1990, to October 3, 1990. On August 10, 1992, CRY filed a motion to reopen the testimony, seeking an order which would permit them to introduce evidence of ongoing leakage from the Yukon impound-ments after the date the permits were issued. The EHB denied the motion.

On February 1,1993, the EHB issued an adjudication holding that neither Section 503(e) nor 503(d) of SWMA barred DER from issuing the permits to Mill Service. The EHB reasoned that the 1985 consent order between the parties, which directed that compliance with the order was sufficient for issuance of the permits, had been approved by this Court and was not subject to collateral attack. It is from the EHB’s February 1,1993, order that CRY and the County appeal.3

CRY and the County now contend that the EHB erred in holding that compliance with Section 503 of SWMA did not preclude DER from issuing the permits to Mill Service. In addition, CRY presents the following issues for our disposition: whether the EHB erred in failing to require DER to condition the permit and require Mill Service to monitor air quality; whether the EHB erred by determining that DER did not abuse its discretion when it approved the liner system used in construction of Impoundment No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Robinson Township v. Commonwealth
83 A.3d 901 (Supreme Court of Pennsylvania, 2013)
Pennsylvania Trout v. Department of Environmental Protection
863 A.2d 93 (Commonwealth Court of Pennsylvania, 2004)
Leatherwood, Inc. v. Commonwealth, Department of Environmental Protection
819 A.2d 604 (Commonwealth Court of Pennsylvania, 2003)
Ainjar Trust v. Department of Environmental Protection
806 A.2d 482 (Commonwealth Court of Pennsylvania, 2002)
Gemstar Corp. v. Department of Environmental Protection
726 A.2d 1120 (Commonwealth Court of Pennsylvania, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
639 A.2d 1265, 162 Pa. Commw. 669, 1994 Pa. Commw. LEXIS 136, Counsel Stack Legal Research, https://law.counselstack.com/opinion/concerned-residents-of-yough-inc-v-deparment-of-environmental-resources-pacommwct-1994.