Al Hamilton Contracting Co. v. Department of Environmental Protection

680 A.2d 1209, 1996 Pa. Commw. LEXIS 309
CourtCommonwealth Court of Pennsylvania
DecidedJuly 18, 1996
StatusPublished
Cited by6 cases

This text of 680 A.2d 1209 (Al Hamilton Contracting Co. v. Department of Environmental Protection) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Al Hamilton Contracting Co. v. Department of Environmental Protection, 680 A.2d 1209, 1996 Pa. Commw. LEXIS 309 (Pa. Ct. App. 1996).

Opinion

COLINS, President Judge.

Petitioner, A1 Hamilton Contracting Company (Hamilton), petitions for review of an order of the Environmental Hearing Board (EHB) that affirmed the Department of Environmental Protection’s (DEP)1 denial of a request for bond release. We affirm.

The facts of this case are as follows. Hamilton is the owner and operator of a surface coal mine and processing operation located in Bradford Township, Clearfield County, Pennsylvania, known as the Little Beth site (Little Beth). Pursuant to regulations, DEP required Hamilton to carry bonds to guarantee the general environmental restoration of Little Beth. See generally 25 Pa. Code §§ 86.141-86.190 (detailing DEP’s provisions on bonding and insurance requirements). Thus, Hamilton obtained Surface Mining Permit (SMP) No. 17723164 prior to commencing operations at Little Beth and posted the requisite bond. The SMP bond was earmarked for the cost of reclaiming the entire area permitted to be mined and for any future expense incurred in treating or replacing contaminated discharges from the site. Additionally, the SMP bond could offset any unpaid civil fines levied against Hamilton. Of the SMP bond initially posted, a total of $139,430 remained at the time of this appeal.

Because of changes in federal surface mining regulations in 1989, Hamilton was required to obtain a separate permit and post a separate bond for its coal processing operations conducted on the Little Beth site. This bond, the Mining Activities Permit (MAP) bond was unlike the SMP because it covered the cost of reclaiming areas damaged by coal processing operations, not mining activities.2 Thus, MAP No. 17911603 was issued to Hamilton, it covered 47.8 acres. A bond of $146,-361 was posted in connection with the MAP. The 47.8 acres covered most, but not all, of the Little Beth SMP area.

Thereafter, Hamilton filed a bond release application with DEP seeking the release of $77,020 in reclamation bonds posted on 38.6 acres of the SMP area. This application was denied by DEP on May 26, 1994 for the following reasons: the existence of acid mine drainage discharges on, or emanating from, the permit area that were being treated by Hamilton pursuant to an order by DEP; inadequate groundwater monitoring information to demonstrate that the permit area was not hydrogeologically connected to other discharges of acid mine drainage on or adjacent to the permit area; and the pollution of surface and subsurface water and the probability of future pollution. Hamilton appealed DEP’s determination to the EHB, which affirmed. Appeal to this Court followed.

The issue in this case involves the characterization of the two bonds. It is Hamilton’s position that the SMP and MAP bonds overlap, and therefore, the SMP bond should be released to the extent of the overlap.3 DEP argues that the bonds do not overlap. Moreover, DEP argues that if it agreed to Hamilton’s bond release request, there would be insufficient funds to guarantee restoration of the area.

When reviewing decisions of the EHB, our scope of review is limited to determining whether constitutional rights were violated, an error of law was committed by the Board, or necessary findings of fact of the Board are supported by substantial evidence. Department of Environmental Resources v. Ogden, 93 Pa.Cmwlth. 153, 501 A.2d 311 (1985). Substantial evidence is such relevant [1212]*1212evidence as a reasonable mind might accept as adequate to support a conclusion. Kerrigan v. Department of Environmental Resources, 163 Pa.Cmwlth. 565, 641 A.2d 1265 (1994). To prevail before this Court, Hamilton must prove that the EHB action was erroneous. See Pennsylvania Game Commission v. Department of Environmental Resources, 97 Pa.Cmwlth. 78, 509 A.2d 877, 884 (1986).

Hamilton argues that the EHB erred in affirming DEP’s denial of the bond release because this denial results in an inequitable double bonding of Little Beth. Hamilton posits that since the circumstances of its operation are unique,4 insofar as it performs coal processing and surface mining operations on the same tract of land, there need be only one bond to cover both the activities. Thus, Hamilton argues that the MAP bond should serve as a replacement to a portion of the SMP bond and that the $77,020 that represents the replacement, or the overlap of the two bonds, should be released to it.

Hamilton’s contention concerning double bonding can not prevail because the record contains substantial evidence to support the Board’s finding that DEP intended the bonds to remain separate and distinct instruments, serving separate and distinct functions. William Plassio, the District Mining Manager for DEP’s McMurray District office, developed the process for permitting previously unpermitted coal processing plants. He testified that his process envisioned neither the MAP bond serving as a replacement for the SMP bond nor the eom-mingling of liability between the SMP and MAP bonds with respect to areas in which both bonds were needed. Furthermore, he stated that different criteria are used in setting the amount of money needed for each bond irrespective of the other. Essentially, the bonds are to remain two distinct instruments serving similar, yet distinguishable, purposes.5

There being substantial evidence to support the conclusion that the MAP bond did not replace the SMP bond, we next address Hamilton’s argument that the Board erred in not concluding that DEP abused its discretion. Hamilton argues that DEP abused its discretion by faffing to adhere to its own Program Guidance Manual (PGM).6 In support of this argument, Hamilton urges this Court’s consideration of Department of Environmental Resources v. Rushton Mining Co., 139 Pa.Cmwlth. 648, 591 A.2d 1168 (1991), wherein we set out the “binding norm test” as a means of determining whether a statement of policy reaches the level of a regulation under Section 553(b) of the Ad-' ministrative Procedure Act, 5 U.S.C. § 553(b). See also Pacific Gas & Electric Co. v. Federal Power Commission, 506 F.2d 33 (D.C.Cir.1974); Pennsylvania Human Relations Commission v. Norristown Area School District, 473 Pa. 334, 374 A.2d 671 (1977). If a statement of policy is a binding norm, “the agency is bound by the statement until the agency repeals it, and if the statement is binding on the agency, it is a regulation.” Rushton, 591 A.2d at 1173.

[1213]*1213We agree with Hamilton that DEP is bound by the PGM and that it should be utilized in the proper circumstances.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pittsburgh Palisades Park, LLC v. Pennsylvania State Horse Racing Commission
844 A.2d 62 (Commonwealth Court of Pennsylvania, 2004)
F.R. & S., Inc. v. Department of Environmental Protection
761 A.2d 634 (Commonwealth Court of Pennsylvania, 2000)
Westinghouse Electric Corp. v. Pennsylvania Department of Environmental Protection
705 A.2d 1349 (Commonwealth Court of Pennsylvania, 1998)
Soil Remediation Systems, Inc. v. Department of Environmental Protection
703 A.2d 1081 (Commonwealth Court of Pennsylvania, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
680 A.2d 1209, 1996 Pa. Commw. LEXIS 309, Counsel Stack Legal Research, https://law.counselstack.com/opinion/al-hamilton-contracting-co-v-department-of-environmental-protection-pacommwct-1996.