EQT Prod. Co. v. Dep't of Envtl. Prot.

193 A.3d 1137
CourtCommonwealth Court of Pennsylvania
DecidedSeptember 10, 2018
Docket844 C.D. 2017
StatusPublished
Cited by4 cases

This text of 193 A.3d 1137 (EQT Prod. Co. v. Dep't of Envtl. Prot.) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
EQT Prod. Co. v. Dep't of Envtl. Prot., 193 A.3d 1137 (Pa. Ct. App. 2018).

Opinion

OPINION BY JUDGE BROBSON

By Adjudication and Order (Adjudication) issued May 26, 2017, the Commonwealth of Pennsylvania Environmental Hearing Board (Board) assessed Petitioner EQT Production Company (EQT) a civil penalty of $1,137,295.76 for violations of The Clean Streams Law 1 and a related regulation. The violations stemmed from the release of wastewater 2 through the damaged liner of an impoundment, also known as the "S Pit," in Tioga County, Pennsylvania, which EQT used as part of fracking operations for an unconventional gas well site known as "Pad S." The wastewater infiltrated the ground beneath the impoundment and ultimately polluted groundwater, seeps and springs, and a stream in the vicinity. None of this is in dispute.

On appeal, EQT challenges the amount of the civil penalty. 3 The Clean Streams Law provides for a civil penalty of up to $10,000 per day, per violation:

(a) In addition to proceeding under any other remedy available at law or in equity for a violation of a provision of this act, rule, regulation, order of the department, or a condition of any permit issued pursuant to this act, the department, after hearing, may assess a civil penalty upon a person or municipality for such violation. Such a penalty may be assessed whether or not the violation was wilful. The civil penalty so assessed shall not exceed ten thousand dollars ($10,000) per day for each violation. In determining the amount of the civil penalty the department shall consider the wilfullness [sic] of the violation, damage or injury to the waters of the Commonwealth or their uses, cost of restoration, and other relevant factors.

Section 605(a) of The Clean Streams Law, 35 P.S. § 691.605(a). For the reasons set forth below, we affirm the Board's civil penalty assessment.

I. BACKGROUND

DEP filed its complaint for civil penalties against EQT with the Board on October 7, 2014, alleging that EQT violated The Clean Streams Law through the unpermitted release of wastewater from the impoundment. DEP sought a civil penalty in excess of $4.5 million. Following completion of discovery and the filing of prehearing motions, the Board held a hearing on the merits of DEP's complaint over a period of ten days from July 25 to August 5, 2016. The resulting Adjudication is lengthy and detailed, with 270 separately-numbered findings of fact, nearly 50 pages of discussion/analysis, and 24 separately-numbered conclusions of law. 4

In calculating the penalty, the Board noted that Section 605(a) of The Clean Streams Law requires that it consider the willfulness of the "violation, damage or injury to the waters of the Commonwealth or their uses, cost of restoration, and other relevant factors." (Adjudication at 70.) Included among other relevant factors that the Board has considered are the cost savings that the violator reaped by engaging in the unlawful activity, the size of the facility in question, the volume of the discharge, deterrence, and the costs incurred by DEP. ( Id. ) The Board then noted several factors relative to the pollution from the impoundment. First, the Board noted that the "release did not adversely affect any public or private drinking water supplies." ( Id. at 70-71.) Moreover, the Board observed that the record was inadequate to support a finding that the "release had an actual adverse effect on aquatic life." ( Id. at 71.) The Board also noted that while the "release caused some adverse impacts to vegetation" in the vicinity of the site, it did not factor that damage into its calculation. ( Id. at 72.) It also did not consider any damage to soil. ( Id. ) The Board also refused to assess any penalties for other violations at the Pad S site, focusing its inquiry solely on the damage caused by the failure of the liner in the impoundment. ( Id. )

Turning first to the issue of cost savings, the Board noted that, subject to the statutory maximum amount, a civil penalty should be no less than the amount of cost savings that the violator enjoyed by engaging in the unlawful activity. Noting limited evidence in the record on the question, however, the Board ultimately concluded that the amount of the penalty that it was imposing "is likely in excess of EQT's cost savings." ( Id. at 73.) The Board then held that DEP was entitled to recoup its documented costs of $112,295.76, which the Board would include in EQT's civil penalty. ( Id. )

The Board then considered the extent of damage to the waters of the Commonwealth, one of the criteria expressly set forth in Section 605(a) of The Clean Streams Law. It again noted its finding that the release from the impoundment did not harm public or private water supplies. It also noted as a mitigating factor that the constituents of the wastewater ( e.g. , barium, lithium, strontium, chloride) occur naturally in the waters of the Commonwealth, though not at the levels released from the impoundment. Nonetheless, the Board noted that the high concentrations "have for the most part declined over time." ( Id. at 73.) The Board also noted that the release from the impoundment caused limited contamination to Rock Run, a Class A Wild Trout and High Quality stream located within approximately 1,500 feet of the impoundment. ( Id. at 73 and Findings of Fact (FF) ## 11, 12.) The Board, however, continued:

[C]leanup was still ongoing at the time of our hearing four years after the leak was discovered, which shows that harm caused by multiple contaminants was persistent and prolonged. EQT degraded a High Quality, Class A Wild Trout stream, as well as a tributary, the underground water, and the spring and seeps in the watershed that feed the stream. No unpermitted degradation of such a valuable natural resource is tolerable. The release extended a considerable distance, creating a known contamination plume on the order of 2,000 feet across. [DEP] witnesses testified that it caused the largest aerial extent of contamination in the history of the program and affected Exceptional Value wetlands. Thirty-five million gallons of contaminated water were collected at the time of the hearing. [DEP's] characterization of the damage as severe is supported by the record.

( Id. at 73-74 (emphasis in original).)

The Board noted further that the damage to the waters of the Commonwealth were largely caused by releases from the impoundment that occurred prior to the end of June 2012, which corresponds to the period of time by which EQT had drained the impoundment and patched the holes in the liner: "We have reduced the amount of the daily penalty in part to reflect the fact that new releases after that time would have continued to shrink such that, by September 27, [2012,] they would have been quite limited." ( Id. at 74.) According to the Board's findings of fact, September 27, 2012, is the date by which EQT had fully removed the damaged liner from the impoundment, excavated contaminated soil, and installed a temporary liner. ( Id. FF ## 216-21.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
193 A.3d 1137, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eqt-prod-co-v-dept-of-envtl-prot-pacommwct-2018.