Wayco Sand and Gravel v. DEP & P. Karnick

CourtCommonwealth Court of Pennsylvania
DecidedJanuary 6, 2020
Docket713 C.D. 2018
StatusUnpublished

This text of Wayco Sand and Gravel v. DEP & P. Karnick (Wayco Sand and Gravel v. DEP & P. Karnick) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wayco Sand and Gravel v. DEP & P. Karnick, (Pa. Ct. App. 2020).

Opinion

IN THE COMMONWEALTH COURT OF PENNSYLVANIA

Wayco Sand and Gravel, : : Petitioner : : v. : No. 713 C.D. 2018 : Submitted: March 22, 2019 Department of Environmental : Protection and Peter Karnick, : : Respondents :

BEFORE: HONORABLE RENÉE COHN JUBELIRER, Judge HONORABLE ROBERT SIMPSON, Judge1 HONORABLE MICHAEL H. WOJCIK, Judge

OPINION NOT REPORTED

MEMORANDUM OPINION BY JUDGE WOJCIK FILED: January 6, 2020

Wayco Sand and Gravel (Wayco) petitions for review of the order of the Environmental Hearing Board (EHB) sustaining Peter Karnick’s (Landowner) appeal from the Department of Environmental Protection’s (DEP) approval of the Stage I and II bond release to Wayco for the permitted area of Landowner’s property. We affirm. Wayco is in the business of asphalt paving and conducts surface mining of sand and gravel. In July 1994, Wayco was issued a noncoal surface mining permit to conduct operations on a 7.6-acre portion of Landowner’s property

1 This matter was assigned to this panel before September 1, 2019, when Judge Simpson assumed the status of senior judge and was decided before Judge Simpson's service on the Court ended on December 31, 2019. in Waymart, Pennsylvania, identified as Parcel 13 on Module 15 (the Site). See Reproduced Record (R.R.) at 117, 120, 848-62. Mining support activities occurred on the Site that included the processing of sand and gravel, but no mining or extraction of minerals occurred there and there were no pits or highwalls on the Site. The Site was previously mined for sand and gravel and was reclaimed before Wayco and Landowner entered into a 10-year lease for Wayco to use it for processing minerals that had been extracted from other sites. As part of the processing operations, Wayco constructed several ponds or impoundments on the Site, including two large silt or sedimentation ponds or basins (silt ponds). See R.R. at 252-54, 890. There are drainage problems associated with the continued presence of the silt ponds on the Site affecting drainage patterns and preventing adequate drainage. See id. at 252-54. Wayco’s attempts to improve the draining problems associated with its decision to leave the silt ponds on the Site have not eliminated the drainage problems. See id. at 261. Section 17.1 of Module 17, relating to Post-mining Use and Reclamation, states that “the present land use is forestland with a portion as pastureland,” that the “[a]ffected areas will be restored to forestland,” and that the “[Approximate Original Contour (AOC)2] will be restored during reclamation.”

2 Section 3 of the Noncoal Surface Mining Conservation and Reclamation Act (Act), Act of December 19, 1984, P.L. 1093, as amended, 52 P.S. §3303, defines AOC as “[c]ontouring as defined in this act” which, in turn, is defined as:

Reclamation of the land affected to [AOC] so that it closely resembles the general surface configuration of the land prior to mining and blends into and complements the drainage pattern of the surrounding terrain with no highwall, spoil piles or depressions to accumulate water and with adequate provisions for drainage. (Footnote continued on next page…) 2 R.R. at 905. Section 17.2 states, “The [S]ite will be restored to AOC by regrading. Positive drainage will be produced and forestland restored. Reclamation will increase the amount of forestland on the permit area.” Id. On November 26, 2014, DEP informed Landowner that Wayco had applied for a Stage I and II bond release of liability on the permit and that an inspection would be scheduled “to evaluate the adequacy of the reclamation work performed.” R.R. at 919.3 On July 1, 2016, DEP sent Landowner a letter stating

(continued…)

See also Section 77.1 of DEP’s regulations, 25 Pa. Code §77.1 (same). Additionally, Section 77.1 of DEP’s regulations defines “reclamation” as “[a]ctions taken to reclaim the area affected by surface mining activities as required by this chapter.” Id.

3 Section 77.242(a) of DEP’s regulations sets forth the procedure for seeking a Stage I and II bond release stating, in relevant part:

(a) Release of bond. The permittee may file an application with [DEP] for release of all or part of the bond liability applicable to a permit or designated phase of a permit area after reclamation, restoration and abatement work in a reclamation stage, as defined in §77.243 (relating to criteria and schedule for release of bond), has been completed on the permit area or designated phase of a permit area, subject to the following conditions:

(1) Applications may be filed only at times or seasons that allow [DEP] to properly evaluate the reclamation operations reported to have been completed.

(2) Within 60 days after filing the application for release, the permittee shall submit proof of publication of the advertisement [of the filing of the application in a newspaper of general circulation in the locality of the permit area as] required by subsection (b).

25 Pa. Code §77.242(a).

(Footnote continued on next page…) 3 (continued…)

Section 77.243(b)(1), (2) and (c) sets forth the standards governing the bond release: (b) For the purposes of this section the following apply:

(1) Reclamation Stage I shall be deemed to have been completed when:

(i) The permittee completes backfilling, regrading and drainage control in accordance with the approved reclamation plan.

(ii) Topsoil has been replaced and revegetation has been established in accordance with the approved reclamation plan and the standards for the success of revegetation are met.

(iii) The lands have been stabilized to prevent accelerated erosion and sedimentation under Chapter 102 (relating to erosion control).

(iv) The permittee has successfully completed mining and reclamation operations in accordance with the approved reclamation plan, so that the land is capable of supporting post-mining land use approved under §77.653 (relating to post-mining land use).

(v) The permittee has achieved compliance with the requirements of the environmental acts, this chapter and the conditions of the permits.

(2) Reclamation Stage II shall be deemed to be complete when the applicable liability period under §77.204 (relating to period of liability) has expired.

(c) [DEP] will not release a bond amount deposited . . . if the release would reduce the total remaining amount of bond to an amount which would be insufficient for [DEP] to complete reclamation and to take measures that may be necessary to prevent adverse effects upon the environment or public health, safety or (Footnote continued on next page…) 4 that following a field inspection “to evaluate the adequacy of the reclamation work performed and the success standards of the vegetation that has been planted,” DEP intended to release the bond posted on the site based on its determination that “the reclamation work performed and revegetation success of the [S]ite meets the requirements contained in the mine permit and [DEP’s] rules and regulations[.]” Id. at 921. On July 21, 2016, DEP released Wayco’s bond. Id. at 923. On August 10, 2016, Landowner appealed DEP’s release of Wayco’s bond alleging, inter alia, that the Site “was not reclaimed to where [h]e could use it” because the “silt ponds are 5 to 8 [feet] deep with swamp grass and willows” and that the “dams on the silt ponds are keeping [the] ponds from drying out.” R.R. at 1. Landowner also asserted that DEP had not classified the Site as “wetlands,” and that it is now overgrown “with swamp grass [and] weeds and it’s to[o] rough to farm.” Id. In sum, Landowner stated, “All I want is [the] land

welfare under the environmental acts, the [A]ct, this chapter, the terms and conditions of the permits and order of [DEP].

25 Pa. Code §77.243(b)(1) and (2), (c).

In turn, Section 77.204(a) states:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lock v. City of Philadelphia
895 A.2d 660 (Commonwealth Court of Pennsylvania, 2006)
Commonwealth v. Glover
401 A.2d 779 (Superior Court of Pennsylvania, 1979)
Commonwealth v. Berry
172 A.3d 1 (Superior Court of Pennsylvania, 2017)
EQT Prod. Co. v. Dep't of Envtl. Prot.
193 A.3d 1137 (Commonwealth Court of Pennsylvania, 2018)
Wilbar Realty, Inc. v. Department of Environmental Resources
663 A.2d 857 (Commonwealth Court of Pennsylvania, 1995)
Pennsylvania Game Commission v. Bowman
474 A.2d 383 (Commonwealth Court of Pennsylvania, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
Wayco Sand and Gravel v. DEP & P. Karnick, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wayco-sand-and-gravel-v-dep-p-karnick-pacommwct-2020.