Western Washington Corp. v. Ferrellgas, Inc.

7 P.3d 861, 102 Wash. App. 488, 2000 Wash. App. LEXIS 1638
CourtCourt of Appeals of Washington
DecidedSeptember 8, 2000
DocketNos. 23334-7-II; 23338-0-II
StatusPublished
Cited by42 cases

This text of 7 P.3d 861 (Western Washington Corp. v. Ferrellgas, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Washington Corp. v. Ferrellgas, Inc., 7 P.3d 861, 102 Wash. App. 488, 2000 Wash. App. LEXIS 1638 (Wash. Ct. App. 2000).

Opinion

Armstrong, C.J.

— The Western Washington Corporation of Seventh-Day Adventists (the Church) sued its heating contractor and its propane supplier for fire damage to its partially constructed building. The suit was brought on behalf of the Church’s property insurer, who claimed subrogation rights against the allegedly negligent heating contractor, Art & Sons, Inc., and the propane supplier, Ferrellgas, Inc. Art & Sons and Ferrellgas each moved for summary judgment, arguing that the insurer had no subrogation rights (1) because Art & Sons and Ferrellgas are co-insureds under the insurance policy, and (2) because the Church waived subrogation rights by contract. The Church also moved for partial summary judgment, seeking dismissal of these defenses. The trial court granted summary judgment for Art & Sons, concluding that its trade contract with the Church incorporated by reference a subrogation waiver. The Church appeals.

The trial court also granted the Church’s motion for [491]*491summary judgment against Ferrellgas. The court concluded that Ferrellgas was not a third party beneficiary of the Church’s agreement with its architect, which Ferrellgas contends incorporates by reference a waiver of subrogation in favor of contractors. The trial court also concluded that Ferrellgas was not a co-insured under the Church’s policy. Ferrellgas appeals. We affirm.

FACTS

The Church sued both Art & Sons and Ferrellgas for negligence and breach of contract. The suit was brought on behalf of Adventist Risk Management, which claims a subrogation interest in any recovery. Adventist Risk Management paid $1,847,567.27 to the Church for damages caused by the fire.

In 1992, the Church contracted with architect Russ Hasse to design the church. The contract is ALA Document B141, entitled “Standard Form of Agreement Between Owner and Architect” (the Owner/Architect Agreement). Under the Owner/Architect Agreement, Hasse was required to prepare construction documents — drawings and specifications setting forth the requirements for construction of the project. And, he was required to administer the contract as set forth in “AIA Document A201, General Conditions of the Contract for Construction.”

The Owner/Architect Agreement also provides that “[t]erms in this Agreement shall have the same meaning as those in AIA Document A201, General Conditions of the Contract for Construction.” AIA Document A201 includes ‘Waivers of Subrogation,” under which the owner, all contractors, and subcontractors agree to waive their rights of subrogation against each other.

As required by the Owner/Architect Agreement, Hasse prepared a project manual and specifications (the Project Manual). The Project Manual included a section entitled “Division 1 - General Requirements.” Paragraph 1.2 of this section provides: “General Conditions of the Contract for [492]*492the Construction of Buildings (AIA Document A201) is a part of this specification.”

In June 1994, the Church entered into a “Project Management/Superintendent Agreement” with Tex Ladish, a registered general building contractor. Under the agreement, Ladish was required to maintain and organize the job-site, coordinate the subcontractors, order materials, manage the construction schedule, and inspect subcontractors’ work. In addition, he was required to select subcontractors with the building committee and prepare and administer contracts between the Church and the subcontractors. Ladish said he may have received a copy of the Project Manual but claims that he did not use it. The Church concedes that Ladish had a copy of the Project Manual.

On September 8, 1994, Art & Sons entered into a “Trade Contract” with Ladish to install a furnace and the associated fans, vents, and ductwork. Under the Trade Contract, Art & Sons was “to perform the Work... in accordance with the Project Contract Documents.” Article 2, entitled SCOPE OF WORK, further provides: “Trade Contractor agrees ... to perform and complete such Work in accordance with Contract Documents . . . .” Art & Sons was also required to procure $1,000,000 Comprehensive General Liability insurance, naming the construction superintendent, owner, and architect as additional insureds.

On the same day that Art & Sons’ contract was executed, Ladish sent them “Plan Set 14, Spec [sic] Set 14, and Revised Mechanical Plans.” The Church admits that Ladish gave Art & Sons the project drawings and mechanical specifications. The following paragraph is included at the beginning of nine separate subsections in the mechanical specifications:

PART I GENERAL

1.01 RELATED DOCUMENTS: The Drawings, Conditions of Contract, and Division I of Specification Sections apply to this Section.

(Emphasis added.)

[493]*493Division I of the specifications expressly incorporates AIA Document A201, which includes the agreement by the owner, contractor, and subcontractors to waive their subrogation rights against each other. But Division I of the specifications was not attached to the Trade Contract or the specifications.

Ferrellgas was both a supplier of gas and a contractor. The mechanical specifications for the exterior gas system provide: “Serving utility shall be responsible for providing and installing the storage tank. This contractor shall be responsible for piping from the tank connection to the building.” But Ferrellgas did not have a trade contract with the Church. Instead, its agreement is found in two “Equipment Rent and Gas Sale Agreement[s]” and two invoices, all of which were drafted by Ferrellgas.

The first agreement is for a 500-gallon tank, a construction heater, and miscellaneous equipment. Ladish signed the agreement. Although the agreement states that there are additional terms on the back of the document, the back of the document is not included in the exhibit. An invoice indicates that the 500-gallon tank and equipment were temporary.

The second agreement, on a form identical to the first, is for three 1,000-gallon tanks. Neither the Church nor Ladish signed this document. The additional terms are attached to this agreement and state in part, “Consumer will. . . pay for all loss or damage to, LP gas or equipment owned by [Ferrellgas], except for damage to the leased equipment resulting from ordinary wear and use.”

The trial court granted Art & Sons’ motion for summary judgment, concluding that the trade contract incorporated the Project Manual, and the Project Manual incorporated ALA Document A201. The Church’s summary judgment motion against Art & Sons was dismissed. The court denied Ferrellgas’ motion for summary judgment and granted the Church’s motion for summary judgment against Ferrellgas, thereby striking Ferrellgas’ affirmative defenses.

[494]*494ANALYSIS

A. Standard of Review

When reviewing an order of summary judgment, we engage in the same inquiry as the trial court. Wilson v. Steinbach, 98 Wn.2d 434, 437, 656 R2d 1030 (1982). Summary judgment is appropriate only if the pleadings, affidavits, depositions, and admissions on file demonstrate the absence of any genuine issues of material fact, and that the moving party is entitled to judgment as a matter of law. CR 56(c). The court should grant the motion only if, from all the evidence, reasonable persons could reach but one conclusion. Wilson, 98 Wn.2d at 437.

B.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Zurich American Insurance Co. v. Infrastructure Engineering, Inc.
2024 IL 130242 (Illinois Supreme Court, 2024)
Trina Lyons, V. Dshs
Court of Appeals of Washington, 2024
Goceri v. Amazon.Com, Inc.
N.D. California, 2024
Baionne Coleman, V. Impact Public Schools
Court of Appeals of Washington, 2024
Michael Roupp, V. Lucius Gregory Meredith
Court of Appeals of Washington, 2022
Zaire Webb v. Washington State University
Court of Appeals of Washington, 2020
Harley Blanton v. Domino's Pizza Franchising LLC
962 F.3d 842 (Sixth Circuit, 2020)
John Hastings v. Unikrn, Inc.
Court of Appeals of Washington, 2020
Edifice Construction Company v. Sak & Patch, Inc.
Court of Appeals of Washington, 2020
Steven Burnett v. Pagliacci Pizza
442 P.3d 1267 (Court of Appeals of Washington, 2019)
Pitell v. King Cnty. Pub. Hosp. Dist. No. 2
423 P.3d 900 (Court of Appeals of Washington, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
7 P.3d 861, 102 Wash. App. 488, 2000 Wash. App. LEXIS 1638, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-washington-corp-v-ferrellgas-inc-washctapp-2000.