Zurich American Insurance Co. v. Infrastructure Engineering, Inc.

2024 IL 130242, 248 N.E.3d 1072
CourtIllinois Supreme Court
DecidedSeptember 19, 2024
Docket130242
StatusPublished
Cited by43 cases

This text of 2024 IL 130242 (Zurich American Insurance Co. v. Infrastructure Engineering, Inc.) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zurich American Insurance Co. v. Infrastructure Engineering, Inc., 2024 IL 130242, 248 N.E.3d 1072 (Ill. 2024).

Opinion

2024 IL 130242

IN THE SUPREME COURT OF THE STATE OF ILLINOIS

(Docket No. 130242)

ZURICH AMERICAN INSURANCE COMPANY, Appellee, v. INFRASTRUCTURE ENGINEERING, INC., Appellant.

Opinion filed September 19, 2024.

JUSTICE OVERSTREET delivered the judgment of the court, with opinion.

Chief Justice Theis and Justices Neville, Holder White, Cunningham, Rochford, and O’Brien concurred in the judgment and opinion.

OPINION

¶1 Plaintiff, Zurich American Insurance Company (Zurich), issued a builder’s risk insurance policy to insure the construction of an academic building for Community College District No. 508, doing business as City Colleges of Chicago (City Colleges). Defendant, Infrastructure Engineering, Inc. (IEI), a subcontractor on the construction project, was hired to design a system for collecting rainwater. While the building was under construction, a rainstorm caused the basement of the building to flood, causing significant damage.

¶2 Zurich paid a claim for the resulting damages by submitting payment to CMO, a joint venture and general contractor on the project, pursuant to the builder’s risk policy. Zurich, claiming the status of subrogee of City Colleges, then sued IEI for breach of contract, alleging IEI’s rainwater redesign caused the damage to the building. IEI moved for summary judgment, arguing that Zurich was not entitled to subrogation for City Colleges because it issued payment under the policy to CMO, not City Colleges, and CMO, as general contractor, repaired the physical damages. The Cook County circuit court agreed and entered summary judgment in IEI’s favor. Zurich appealed, arguing that the builder’s risk policy entitled it to step into City Colleges’ shoes pursuant to the policy’s subrogation provisions. The appellate court agreed, reversed the circuit court’s judgment, and remanded the cause for further proceedings. 2023 IL App (1st) 230147.

¶3 We granted IEI’s petition for leave to appeal, and for the following reasons, we affirm the appellate court’s judgment and reverse the circuit court’s judgment.

¶4 BACKGROUND

¶5 City Colleges owns and operates Malcolm X College. In planning the construction of the approximately 500,000-square-foot academic building and parking garage for Malcolm X College, City Colleges executed an agreement with CMO as general contractor and an agreement with Moody Nolan, Inc. (Moody Nolan), as architect for the project. The project included the development of the academic building with one or more basement levels to house, among other things, mechanical and electrical equipment.

¶6 On April 4, 2013, City Colleges entered into the written contract with Moody Nolan wherein Moody Nolan agreed to provide architectural and engineering services for the project. The contract contemplated that Moody Nolan may subcontract engineering consultants to perform some of the design work, subject to certain conditions. The contract defined “Subcontractor” as any “entity with whom [Moody Nolan] contracts to provide any part of the Services *** including subcontractors and subconsultants of any tier, whether or not in privity with”

-2- Moody Nolan. The Moody Nolan contract stated, in part, “In addition, each subcontract for the performance of the Services must provide that [City Colleges] is a third-party beneficiary to the subcontract, and may enforce any of the subcontract terms including[ ] those pertaining to standard of performance, indemnity and insurance.” City Colleges’ contract with Moody Nolan did not include a waiver of subrogation provision, wherein, for example, City Colleges waived claims against Moody Nolan or its subcontractors for damages covered by property insurance for the building’s construction.

¶7 Moody Nolan entered into a written contract with IEI on April 17, 2013, and this written agreement incorporated City Colleges’ agreement with Moody Nolan, referring to it as the “Prime Agreement.” Moody Nolan subcontracted to IEI the civil engineering work for the project, including the design and specification of the stormwater management systems. The IEI subcontract stated, in part, “Where a provision of the Prime Agreement is inconsistent with a provision of this Agreement, the Prime Agreement shall govern.” 1 The IEI subcontract required IEI to maintain general liability, automobile liability, workers’ compensation, and professional liability insurance.

¶8 On January 8, 2014, City Colleges and CMO entered into an agreement, which listed Moody Nolan as architect of record for the construction of the new academic building. In the agreement, CMO agreed to serve as the general contractor for the construction of the building, providing all necessary labor, material, and equipment to complete the project. This agreement required CMO to warrant that the work conformed to the requirements of the contract documents and was free from defects.

¶9 The contract between CMO and City Colleges required CMO to purchase and maintain a builder’s risk property insurance policy during the period of construction. 2 Specifically, the contract provided:

1 Because the Prime Agreement between City Colleges and Moody Nolan expressly required City Colleges to be a third-party beneficiary of any subcontracts Moody Nolan entered into with its subcontractors, and the Moody Nolan-IEI subcontract provided that the Prime Agreement governed, the appellate court found that City Colleges was a third-party beneficiary of the Moody Nolan-IEI subcontract. 2023 IL App (1st) 230147, ¶ 54. IEI does not challenge this finding in this court. 2 A builder’s risk policy is first-party property insurance that provides coverage for a building under construction before it becomes insurable as a completed structure. 5 Jeffrey E. Thomas, New

-3- “[CMO] shall purchase and maintain *** property insurance written on a builder’s risk ‘all-risk’ or equivalent policy form in the amount of the initial Contract Sum, plus value of subsequent Contract Modifications and cost materials supplied or installed by others, comprising total value for the entire Project at the site on a replacement cost basis without optional deductibles. Such property insurance shall be maintained, unless otherwise provided in the Contract Documents or otherwise agreed in writing by all persons and entities who are beneficiaries of such insurance, until final payment has been made *** or until no person or entity other than [City Colleges] has an insurable interest in the property required *** to be covered, whichever is later. This insurance shall include interests of the Owner, the Contractor, Subcontractors[,] and Sub- subcontractors in the Project.”

¶ 10 In the January 8, 2014, agreement, City Colleges agreed to pay premiums for that portion of insurance required by the contract. The agreement further specified that City Colleges and CMO “waive all rights against *** each other and any of their subcontractors, sub-subcontractors, agents and employees, each of the other, for damages caused by fire or other causes of loss to the extent covered by” the builder’s risk insurance policy. 3

¶ 11 In 2014, CMO purchased the builder’s risk policy from Zurich to insure the construction of the academic building for the policy period of January 20, 2014, to December 31, 2015. CMO was listed as the “Named Insured” in the policy, and City Colleges, as owner, was listed as an “Additional Named Insured.” Specifically, the policy provided that “Additional Named Insured(s)” included

“All owners, all contractors and subcontractors of every tier, and tenants at the project location, except [CMO], as required by any contract, subcontract or oral agreement for the INSURED PROJECT [located at West Jackson Boulevard

Appleman on Insurance Law Library Edition § 50.01 (2024).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2024 IL 130242, 248 N.E.3d 1072, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zurich-american-insurance-co-v-infrastructure-engineering-inc-ill-2024.