Behr v. Hook

787 A.2d 499, 173 Vt. 122, 2001 Vt. LEXIS 286
CourtSupreme Court of Vermont
DecidedSeptember 28, 2001
Docket00-223
StatusPublished
Cited by20 cases

This text of 787 A.2d 499 (Behr v. Hook) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Behr v. Hook, 787 A.2d 499, 173 Vt. 122, 2001 Vt. LEXIS 286 (Vt. 2001).

Opinion

*124 Skoglund, J.

Plaintiffs Peter and Marjorie Behr, whose newly constructed home was destroyed by fire shortly before they were to move into it, appeal the superior court’s summary judgment ruling upholding a waiver-of-subrogation provision contained in the construction contract entered into between the Behrs and their general contractor. Under the court’s ruling, the Behrs’ insurer — the real party in interest in this subrogation action — may not recoup from defendant subcontractors, who are alleged to have caused the fire, the $1.4 million the insurer paid the Behrs for the fire loss. We reject plaintiffs’ arguments that (1) given their allegations of gross negligence, public policy considerations precluded the superior court from enforcing the waiver-of-subrogation provision; (2) apart from considerations of public policy, the provision should not apply because the general contractor failed to obtain waivers from the subcontractors, as required by the contract; and (3) a portion of the damages were outside the scope of the provision, even if it was applicable. Accordingly, we affirm the superior court’s grant of summary judgment in favor of defendants.

In March 1995, the Behrs contracted with Jaynes & Berge, Inc. for the construction of their new home. They signed a standard contract published by the American Institute of Architects (AJA). The contract required the Behrs to purchase and maintain property insurance in the amount of the initial contract plus any later modifications for work done at the site. The contract explicitly required the policy to insure against the perils of fire, among other things. The contract also included a waiver-of-subrogation provision that required the Behrs and the general contractor to waive all rights against each other and any of their subcontractors for damages caused by fire to the extent covered by insurance obtained pursuant to the contract. Further, the provision required that the insurance policies obtained pursuant to the contract provide waivers of subrogation, as set forth in the contract, by endorsement or otherwise. 1

*125 Construction on the home proceeded through the summer and fall of 1995. Then, in the early morning hours of December 8, 1995, the Behrs’ recently completed home was destroyed by fire. The state police fire marshal determined that a propane heater owned by one subcontractor and left unattended by another subcontractor was the most probable source of the ignition that caused the fire. The Behrs’ insurer paid the Behrs $1.4 million for the loss and initiated a subrogation action, in the Behrs’ name, against the subcontractor who owned the heater, Dead River Company of Maine d/b/a Leonard’s Gas & Electric Service (hereinafter Dead River), and the painting subcontractor who left the heater unattended, Norman Hook d/b/a Norm’s Painting. Plaintiffs alleged that the painting subcontractor acted in a grossly negligent manner by leaving the heater unattended propped near a freshly painted porch to accelerate the drying process on a cold night. Plaintiffs also alleged both ordinary and gross negligence against Dead River, claiming that the heating subcontractor failed to instruct others how to use the heater safely around combustible material, failed to place proper warnings on the heater, and failed to provide an appropriate guard or other safety device on the heater to prevent ignition of combustible materials.

Both defendants filed motions for summary judgment based upon the waiver-of-subrogation provision contained in the construction contract. After hearing oral argument, the superior court granted the motions. Relying on Fairchild Square Co. v. Green Mountain Bagel Bakery, Inc., 163 Vt. 433, 658 A.2d 31 (1995), the court concluded that the intent of the contractual language was unambiguous, and that public policy considerations did not preclude the waiver of subrogation contained in the contract. On appeal from a *126 decision granting summary judgment, we apply the same standard applied by the trial court — we will affirm the judgment if there is no genuine issue as to any material fact and the moving party is entitled to judgment as a matter of law. See Hamelin v. Simpson Paper Co., 167 Vt. 17, 19, 702 A.2d 86, 88 (1997).

I.

Plaintiffs’ primary argument on appeal is that public policy considerations preclude applying a waiver-of-subrogation provision when gross, as opposed to ordinary, negligence is alleged. In making this argument, plaintiffs concede that parties in Vermont may contractually exculpate themselves from their negligent conduct in certain circumstances, but contend that public policy should not allow a party to contractually waive responsibility for reckless conduct that imperils the public. We conclude that, given the circumstances of this case, the instant waiver-of-subrogation provision does not violate public policy.

While acknowledging that exculpatory clauses are traditionally-disfavored and subject to exacting judicial scrutiny, Fairchild Square, 163 Vt. at 437, 658 A.2d at 33, we have recognized that such clauses should be upheld when they are freely and fairly made between parties in an equal bargaining position and do not interfere with any social interest. Dalury v. S-K-I, Ltd., 164 Vt. 329, 332, 670 A.2d 795, 797 (1995) (citing Restatement (Second) of Torts § 496B comment b (1965)). Among the relevant considerations in determining the appropriateness of applying a particular exculpatory clause are (1) whether the contract concerns a business suitable for public regulation; (2) whether the party seeking exculpation is performing a service of great importance to the public; (3) whether that party holds itself out as willing to perform the service for any member of the public; (4) whether, as a result of the essential nature of the service, that party has a decisive bargaining position; (5) whether that party confronts the public with a standardized adhesion contract of exculpation; (6) whether the contract was fairly entered into; and (7) whether the parties’ intent is expressed in clear and unambiguous language. Dalury, 164 Vt. at 332-33, 670 A.2d at 797. Because the context of the contract is critical, Fairchild Square, 163 Vt. at 437, 658 A.2d at 33, the determination of whether an exculpatory clause violates public policy depends ultimately upon “‘the totality of the circumstances . . . against the backdrop of *127 current societal expectations.’ ” Dalury, 164 Vt. at 333-34, 670 A.2d at 798; see New Light Co. v. Wells Fargo Alarm Servs., 525 N.W.2d 25, 30 (Neb.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Zurich American Insurance Co. v. Infrastructure Engineering, Inc.
2024 IL 130242 (Illinois Supreme Court, 2024)
Allstate Insurance Co. v. ADT, LLC
194 F. Supp. 3d 1331 (N.D. Georgia, 2016)
Hemingway v. Construction By Design Corporation
2015 UT App 10 (Court of Appeals of Utah, 2015)
North American Specialty Insurance v. Payton Construction Corp.
953 N.E.2d 233 (Massachusetts Appeals Court, 2011)
Puro v. NEIL ENTERPRISES, INC.
2009 VT 95 (Supreme Court of Vermont, 2009)
LEXINGTON INSURANCE COMPANY v. Entrex Communication Services, Inc.
749 N.W.2d 124 (Nebraska Supreme Court, 2008)
Reliance National Indemnity v. Knowles Industrial Services, Corp.
2005 ME 29 (Supreme Judicial Court of Maine, 2005)
Best Friends Pet Care, Inc. v. Design Learned, Inc.
823 A.2d 329 (Connecticut Appellate Court, 2003)
Buote v. Verizon New England
249 F. Supp. 2d 422 (D. Vermont, 2003)
Best Friends v. Designed Learned, No. X06-Cv-00-0169755 S (Jul. 22, 2002)
2002 Conn. Super. Ct. 9056 (Connecticut Superior Court, 2002)
Best Friends P.C. v. Design Learned, No. X06-Cv-00-0169755 S (Jul. 22, 2002)
2002 Conn. Super. Ct. 9132 (Connecticut Superior Court, 2002)
Colonial Properties Realty Ltd. Partnership v. Lowder Construction Co.
567 S.E.2d 389 (Court of Appeals of Georgia, 2002)
Travelers Indem. Co. of Conn. v. LOSCO GROUP
204 F. Supp. 2d 639 (S.D. New York, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
787 A.2d 499, 173 Vt. 122, 2001 Vt. LEXIS 286, Counsel Stack Legal Research, https://law.counselstack.com/opinion/behr-v-hook-vt-2001.