Walter-Thosti-Boswau Ag v. Michael P.W. Stone, Secretary of the Army

6 F.3d 786, 1993 U.S. App. LEXIS 38036, 1993 WL 342589
CourtCourt of Appeals for the Federal Circuit
DecidedSeptember 3, 1993
Docket92-1398
StatusPublished

This text of 6 F.3d 786 (Walter-Thosti-Boswau Ag v. Michael P.W. Stone, Secretary of the Army) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walter-Thosti-Boswau Ag v. Michael P.W. Stone, Secretary of the Army, 6 F.3d 786, 1993 U.S. App. LEXIS 38036, 1993 WL 342589 (Fed. Cir. 1993).

Opinion

6 F.3d 786
NOTICE: Federal Circuit Local Rule 47.6(b) states that opinions and orders which are designated as not citable as precedent shall not be employed or cited as precedent. This does not preclude assertion of issues of claim preclusion, issue preclusion, judicial estoppel, law of the case or the like based on a decision of the Court rendered in a nonprecedential opinion or order.

WALTER-THOSTI-BOSWAU AG, Appellant,
v.
Michael P.W. STONE, Secretary of the Army, Appellee.

No. 92-1398.

United States Court of Appeals, Federal Circuit.

Sept. 3, 1993.

Before ARCHER, Circuit Judge, COWEN, Senior Circuit Judge, and MICHEL, Circuit Judge.

ARCHER, Circuit Judge.

Walter-Thosti-Boswau AG (WTB) appeals from the decision by the Armed Services Board of Contract Appeals (board), Walter-Thosti-Boswau AG v. Secretary of the Army, ASBCA No. 37973, 92-2 B.C.A. (CCH) p 24,841 (1992), in which the board upheld the contracting officer's (CO) decision denying WTB's claim for an equitable adjustment. We affirm.

I.

A. The United States Army Corps of Engineers (Army) and WTB entered into a firm, fixed-price, lump-sum contract on September 19, 1987 for the renovation of military housing in Erlangen, Germany. Upon completion of the contract, WTB filed with the contracting officer a claim for an equitable adjustment in the amount of DM 469,050 (approximately $317,269 in United States currency). WTB's claim for an equitable adjustment was based on the fact that the Army required WTB to install impregnated (moisture-proof) gypsum board panels on the ceilings of all rooms in the renovated apartments. WTB maintains, under a correct construction of the terms of the contract, it was required to install the ceiling panels only in "wet rooms," i.e., bathrooms. The contracting officer denied the claim and on appeal his decision was upheld by the board.

The contract between the Army and WTB was executed on Standard Form 1442 and is divided into sections as follows:

Composition of Solicitation/Award:

1. Part I Schedule ...

Part II Instructions, Conditions and Notices ...

Part III Special Contract Requirements ...

Part IV Contract Clauses ...

2. Specifications and Drawings ...

Section 2 contains a "Preface to Specifications" describing the work to be done under the contract. Paragraph 3.1.5 headed "Complete Bathroom Renovation" provides under a subheading "Ceilings":

Ceilings: Impregnated moisture-proof gypsumboard panels, painted with enamel paint.

Paragraph 3.1.6 entitled "Renovation of Damaged Plaster and Finish Areas" provides:

Walls and Ceilings: In living, dining and bedroom areas, as well as corridor areas, all wall and ceiling plaster incl. reed mats will be removed. Walls to be provided with machine-applied gypsum plaster MG-PIVa, ceilings with gypsum board panels.

Section 2 also includes the "Master Specifications" covering particular categories of work. It provides in Item 03.02.0503:

Ceiling lining with impregnated gypsumboard panels for wet rooms, board width 625 mm, board thickness 12.5 mm incl. suspension system of galvanized C-sections, suspension height approx. 150 mm to 250 mm. Joints shall be filled, reinforced, and spackled.

Included among the drawings is Drawing No. A5 entitled "Interior Finished Schedule Standard Building VA." Although labelled a drawing, Drawing No. A5 is actually a table delineating the specific materials required for the interior finish for each type of room in the housing units. Drawing No. A5 shows that ceiling linings are required in bathrooms, dining rooms, living rooms, bedrooms, halls, stairs, corridors and toilets.

In addition to the contract documents, the Army furnished the contractor with a schedule entitled "Cost and Quantities Breakdown." This document was only informational as expressly noted on the face of the solicitation document, Standard Form 1442, which stated: "NOTE: Cost and Quantities Breakdown ... furnished for information only." On the first page of this schedule paragraph 1 gives the following notice to contractors:

All items of work described in the specifications and shown on the drawings are included in this "bid schedule". There are no quantities shown in this "bid schedule". It is the intent that each contractor will estimate his own quantities and unit prices for all listed work items and record his total lump sum bid prices in the accompanying "Cost Summary" Part No. I.

The board found that "[t]his document was not returned to the Government with the offers." While the schedule contains a listing of various items of work, each with numerical designations corresponding to subsections in the "Master Specifications," the only reference to ceiling panels is Item 03.02.0503, entitled "Ceiling Lining Impregnated." The corresponding item in the "Master Specifications" required impregnated gypsum board panels for wet rooms.

The contract in Part II, "Instructions, Conditions and Notices," contains a provision incorporating Federal Acquisition Regulations (FAR) Sec. 52.215-14, entitled "Explanation to Prospective Offerors" which sets forth the manner in which a prospective bidder can seek an explanation or interpretation of the solicitation document before bidding.

Any prospective offeror desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing soon enough to allow a reply to reach all prospective offerors before the submission of their offers. Oral explanations or instructions given before the award of the contract will not be binding. Any information given to a prospective offeror concerning a solicitation will be furnished promptly to all other prospective offerors as an amendment of the solicitation, if that information is necessary in submitting offers or if the lack of it would be prejudicial to any other prospective offerors.

Part II of the contract also incorporates FAR Sec. 52.215-33, which provides for an order of preference among the contract documents, as follows:

Any inconsistency in this solicitation or contract shall be resolved by giving precedence in the following order: (a) the Schedule (excluding the specifications); (b) representations and other instructions; (c) contract clauses; (d) other documents, exhibits and attachments; and (e) the specifications.

Part IV of the contract, entitled "Contract Clauses," contains FAR Sec. 52.236-21, entitled "Specifications and Drawings For Construction." Subsection (a) of this clause indicates how discrepancies in the specifications and drawings are to be resolved by providing:

The Contractor shall keep on the work site a copy of the drawings and specifications and shall at all times give the Contracting Officer access thereto. Anything mentioned in the specifications and not shown on the drawings, or shown on the drawings and not mentioned in the specifications, shall be of like effect as if shown or mentioned in both. In case of difference between drawings and specifications, the specifications shall govern.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
6 F.3d 786, 1993 U.S. App. LEXIS 38036, 1993 WL 342589, Counsel Stack Legal Research, https://law.counselstack.com/opinion/walter-thosti-boswau-ag-v-michael-pw-stone-secreta-cafc-1993.