Van-Tex, Inc., Industrial Indemnity, Inc. v. Samuel R. Pierce, Jr., Secretary, Department of Housing and Urban Development

703 F.2d 891, 1983 U.S. App. LEXIS 28567
CourtCourt of Appeals for the Fifth Circuit
DecidedApril 25, 1983
Docket82-1002
StatusPublished
Cited by9 cases

This text of 703 F.2d 891 (Van-Tex, Inc., Industrial Indemnity, Inc. v. Samuel R. Pierce, Jr., Secretary, Department of Housing and Urban Development) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Van-Tex, Inc., Industrial Indemnity, Inc. v. Samuel R. Pierce, Jr., Secretary, Department of Housing and Urban Development, 703 F.2d 891, 1983 U.S. App. LEXIS 28567 (5th Cir. 1983).

Opinion

PATRICK E. HIGGINBOTHAM, Circuit Judge:

We decide today three cases dealing with the rights to construction holdbacks on projects financed by HUD-insured mortgages. In this case, Industrial Indemnity, the surety of a contractor on a § 221(d)(4) (12 U.S.C. § 17157(d)(4)) project, brought suit against HUD to recover holdbacks after the mortgagee had foreclosed and assigned the project to HUD. On cross-motions for summary judgment relying upon a stipulation of facts referencing testimony and exhibits, the district court entered judgment for Industrial Indemnity on theories of third-party beneficiary and unjust enrichment. We reverse.

Facts and Procedural History

In 1971, HUD insured advances by Home Savings Assn, of Dallas County to Casa Claire Apartments, the owner-sponsor of a 160-unit project to be built in Mesquite, Texas. At the “initial closing” twenty-two documents were executed. These included a building loan agreement on a HUD-prescribed form, which provided as follows:

The Borrower shall make monthly applications on FHA Form No. 2403 for advances of mortgage proceeds from the Lender. Applications for advances with respect to construction items shall be for *893 amounts equal to (i) the total value of classes of the work acceptably completed; plus (ii) the value of materials and equipment not incorporated in the work, but delivered to and suitably stored at the site; less (iii) 10 percent (holdback) and less prior advances....
Upon completion of the improvements, ... the Borrower shall furnish to the Lender and the [Federal Housing] Commissioner satisfactory evidence that all work requiring inspection by municipal or other governmental authorities having jurisdiction has been duly inspected and approved by such authorities and by the rating or inspection organization, bureau, association or office having jurisdiction; and that all requisite certificates of occupancy and other approvals have been issued. The balance due the Borrower hereunder shall be payable at such time after completion as the commissioner authorizes the release of the holdback. However, the Lender may withhold final payment until after the expiration of any period which mechanics and materialmen may have for filing liens.

The value of the HUD-insured mortgage was $2,143,000.

Van-Tex, Inc., was designated the general contractor. Because B.L. Nelson was both a 5 percent general partner in Casa Claire Apartments and the 91 percent stockholder in an entity that owned 80 percent of Van-Tex, “an identity of interest” was created between the owner-sponsor and the contractor. As a result, HUD required the construction contract to be on a cost-plus basis with the contractor’s costs to be certified. See 24 C.F.R. §§ 221.548(c)(1), 221.551(a). In identity of interest cases, however, HUD also permits the owner-sponsor and the contractor to waive the Builder’s and Sponsor’s Profit and Risk allowance, thereby minimizing the up-front money needed. For this reason many § 221(d)(4) participants deliberately choose to have an identity of interest. Casa Claire Apartments and Van-Tex did so here.

At the initial closing Casa Claire Apartments and Van-Tex entered into the cost-plus construction contract on yet another HUD-prescribed form. That contract contained a holdback provision in large part mirroring the provision in the building loan agreement:

Subject to the approval of the Lender and the Commissioner, the Contractor shall be entitled to payment thereon in an amount equal to (1) the total value of classes of the work acceptably completed; plus (2) the value of materials and equipment not incorporated in the work, but delivered to and suitably stored at the site; less (3) 10 percent holdback and less prior payments....
The balance due the Contractor hereunder shall be payable upon the expiration of 30 days after the work hereunder is fully completed, provided the following have occurred:
(1) All work hereunder requiring inspection by municipal or other governmental authorities having jurisdiction has been inspected and approved by such authorities. ..
(2) All certificates of occupancy, or other approvals, with respect to all units of the project have been issued by State or local governmental authorities having jurisdiction; and
(3) Permissions to occupy (FHA Form No. 2485) for all units of the project have been issued by the Commissioner.

After the initial closing Casa Claire Apartments assigned its assets and liabilities to Casa Claire Apartments, Ltd., a limited partnership in which B.L. Nelson remained a 5 percent general partner. The mortgage was assigned to Metropolitan Savings Bank of Brooklyn, New York, although Home Savings Assn, remained the servicing agent.

Construction began in 1971 and continued into the following year. Home periodically advanced construction funds to Van-Tex less the 10 percent retainage. By April 25, 1972, a HUD inspector certified that construction was 99.7 percent complete. The last disbursement of mortgage proceeds occurred on June 27, 1972. HUD determined the date of substantial completion to be August 29.

*894 Meanwhile, however, the owner-sponsor had failed to make monthly interest payments. On August 17, Home sent HUD a notice of default indicating that Casa Claire had failed to meet payments for May, June, and July. Additional notices of default followed. Finally, by letter of December 1, Home as servicing agent for Metropolitan informed HUD that it was exercising its option to foreclose on the apartment project. Two months later Metropolitan took possession of the project and began to operate it. Later in 1973 it deeded the property to HUD, and received $1,884,-465.80 plus interest as mortgage insurance. HUD eventually sold the project for $1,200,-000.

This appeal is concerned with the construction holdbacks. When Van-Tex finished construction, they amounted to $186,-590.14. Because of Casa Claire’s default, the holdback was never paid out. HUD refused to insure the disbursement, so Metropolitan and Home refused to disburse this amount from the mortgage proceeds.

This vintage lawsuit, now entering its tenth year, was brought by Industrial Indemnity as surety of Van-Tex. Industrial Indemnity claimed it was entitled to recover the retainage from HUD as a third-party beneficiary of the building loan agreement, HUD having inherited the mortgagee’s duties. Industrial Indemnity also claimed it was entitled to recover on the basis of unjust enrichment in that Van-Tex did all it was supposed to do, while HUD got a housing project without paying full costs of construction. Because some of the construction costs were disallowed by HUD, the parties have stipulated that if any money is owed to Industrial Indemnity by HUD, that amount is $148,849.

The district court first ruled that it had no subject-matter jurisdiction because HUD was immune from suit. We reversed and remanded. Industrial Indemnity, Inc. v. Landrieu,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
703 F.2d 891, 1983 U.S. App. LEXIS 28567, Counsel Stack Legal Research, https://law.counselstack.com/opinion/van-tex-inc-industrial-indemnity-inc-v-samuel-r-pierce-jr-ca5-1983.