STATE OF LOUISIANA COURT OF APPEAL, THIRD CIRCUIT
23-229
UNICORP, LLC
VERSUS
BRADD, LLC
**********
APPEAL FROM THE FOURTEENTH JUDICIAL DISTRICT COURT PARISH OF CALCASIEU, NO. 2021-1293 HONORABLE ROBERT L. WYATT, DISTRICT JUDGE
ELIZABETH A. PICKETT JUDGE
Court composed of Elizabeth A. Pickett, Shannon J. Gremillion, and Charles G. Fitzgerald, Judges.
REVERSED AND REMANDED.
Jeffrey K Prattini Prattini Law Firm, L.L.P. 300 Board of Trade Place New Orleans, LA 70130 (504) 754-6600 COUNSEL FOR PLAINTIFF-APPELLEE: Unicorp, LLC Cody C. Bailey (Admitted Pro Hac Vice) Brunini, Grantham, Grower & Hewes, PLLC Post Office Drawer 119 Jackson, Mississippi 39205 Telephone: (601) 948-3101 COUNSEL FOR PLAINTIFF-APPELLEE: Unicorp, LLC
Darren A. Patin Hailey, McNamara 3445 N. Causeway Blvd, Suite 800 Metairie, LA 70002 (504) 836-6500 COUNSEL FOR DEFENDANT-APPELLANT: BRaDD, LLC
Timothy O’Dowd O’Dowd Law Firm, LLC 924 Hodges Street Lake Charles, LA 70601 (337) 310-2304 COUNSEL FOR DEFENDANT-APPELLANT: BRaDD, LLC
Merrick “Rick” J. Norman, Jr. Taylor, Porter, Brooks, & Phillips, LLP 145 East Street Lake Charles, LA 70601 (337) 436-7781 COUNSEL FOR DEFENDANT-APPELLANT: BRaDD, LLC
John T. Andrishok Taylor, Porter, Brooks & Phillips, LLP 450 Laurel Street, 8th Floor Baton Rouge, LA 70801 (225) 381-0285 COUNSEL FOR DEFENDANT-APPELLANT: BRaDD, LLC PICKETT, Judge.
The owner of an apartment complex appeals the trial court’s judgment
granting summary judgment in favor of the contractor that constructed the complex
and ordering the owner to pay the contractor funds retained by the owner’s lender
in accordance with the parties’ contracts. For the following reasons, the trial
court’s judgment is reversed.
FACTS
On December 20, 2017, BRaDD, LLC contracted with Unicorp, LLC to
build the Erdace Apartments in Lake Charles. BRaDD funded construction of the
project with a loan by Greystone Servicing Corporation, Inc. (Greystone) that is
insured by the Federal Housing Administration (FHA), which is overseen by the
U.S. Department of Housing and Urban Development (HUD). BRaDD and
Unicorp signed two contracts with each other that bear on the issues presented
herein: a HUD Construction Contract (the Construction Contract) and AIA®
Document A201–2007 General Conditions of the Contract for Construction (the
General Conditions).1
The Construction Contract included a Retainage Reduction Rider that
provides for “the holdback of ten percent (10%) as set out in Item (4) of Article 5,
paragraph A of the Construction Contract.”2 The ten percent holdback was retained
1 “AIA®” is an acronym for “The American Institute of Architects.” 2 Article 5(A) of the Construction Contract states:
A. Each month after the commencement of Work hereunder, Contractor shall make a monthly request on HUD-92448 for payment by Owner for Work done during the preceding month. . . . Subject to the approval of Lender and HUD, Contractor shall be entitled to payment thereon in an amount equal to (1) the total value of classes of the Work acceptably completed; plus (2) the value of materials and equipment not incorporated in the Work, but delivered to and suitably stored at the site; plus (3) the value of components stored off -site in compliance with Program Obligations; less (4) ten (10) percent holdback [as this percentage may be reduced in accordance with the provisions of the Retainage Reduction Rider as provided in the Retainage Reduction Rider. In March 2020, Unicorp filed a
motion for partial summary judgment seeking to recover immediately retained
funds totaling $3,214,711. Unicorp sought to have BRaDD release the retained
funds pursuant to the terms of Section 9.8.5 of the General Conditions. BRaDD
resisted Unicorp’s demand, arguing that Article 5 of the Construction Contract
governs the release of the retained funds and that Unicorp failed to comply with
the requirements of that provision.
After conducting two hearings on the motion, the trial court granted
Unicorp’s motion and signed a judgment against BRaDD awarding Unicorp
$3,214,711, together with legal interest thereon from March 28, 2022. The trial
court designated the judgment as a final judgment, subject to immediate appeal as
provided in La.Civ.Code art. 1915(B)(1). BRaDD appealed the judgment, asserting
that the trial court erred in granting judgment in favor of Unicorp. On appeal,
BRaDD urges that the judgment violates provisions of the Construction Contract.
STANDARD OF REVIEW
“The determination of whether the words of a contract are clear and explicit
or ambiguous is a question of law.” Admin-Media, LLC v. AC of Lafayette, L.L.C.,
19-691, p. 6 (La.App. 3 Cir. 3/11/20), 297 So.3d 44, 49. Accordingly, appellate
review in a case of contract interpretation is de novo with the appellate court
determining whether the trial court interpreted the contract correctly or incorrectly.
Johnson v. Allstate Prop. & Cas. Ins. Co., 21-552 (La.App. 3 Cir. 4/27/22), 338
So.3d 109. “Contracts have the effect of law for the parties and may be dissolved
only through the consent of the parties or on grounds provided by law. Contracts
must be performed in good faith.” La.Civ.Code art. 1983. “Interpretation of a
attached hereto, if applicable](or as reduced by HUD in writing) and less (5) prior payments. 2 contract is the determination of the common intent of the parties.” La.Civ.Code art.
2045. “When the words of a contract are clear and explicit and lead to no absurd
consequences, no further interpretation may be made in search of the parties’
intent.” La.Civ.Code art. 2046.
DISCUSSION
Unicorp argues that the General Conditions govern the issues presented by
its motion for summary judgment, while BRaDD contends that the Construction
Contract governs these issues. Specifically, Unicorp argues that Section 9.8.5 of
the General Conditions obligated BRaDD to pay immediately the withheld
retainage when the contracted work was substantially complete, as defined by that
provision. Section 9.8.5 states:
The Certificate of Substantial Completion shall be submitted to the Owner and Contractor for their written acceptance of responsibilities assigned to them in such Certificate. Upon such acceptance and consent of surety, if any, the Owner shall make payment of retainage applying to such Work or designated portion thereof. Such payment shall be adjusted for Work that is incomplete or not in accordance with the requirements of the Contract Documents.
Unicorp and BRaDD accepted the responsibilities assigned to each of them
by a Certificate of Substantial Completion dated June 3, 2020. Additionally,
Unicorp served a List of Material Facts not in Dispute on BRaDD which included
the following:
BRaDD agreed to and accepted the Certificates of Substantial Completion, and the surety consented to the release of all retainage. No punch list items were identified at substantial completion. However, BRaDD has not paid any part of the Retainage to Unicorp.
BRaDD admitted that it accepted the Certificates of Substantial Completion
and that the surety on Unicorp’s bond consented to the release of retainage but
Free access — add to your briefcase to read the full text and ask questions with AI
STATE OF LOUISIANA COURT OF APPEAL, THIRD CIRCUIT
23-229
UNICORP, LLC
VERSUS
BRADD, LLC
**********
APPEAL FROM THE FOURTEENTH JUDICIAL DISTRICT COURT PARISH OF CALCASIEU, NO. 2021-1293 HONORABLE ROBERT L. WYATT, DISTRICT JUDGE
ELIZABETH A. PICKETT JUDGE
Court composed of Elizabeth A. Pickett, Shannon J. Gremillion, and Charles G. Fitzgerald, Judges.
REVERSED AND REMANDED.
Jeffrey K Prattini Prattini Law Firm, L.L.P. 300 Board of Trade Place New Orleans, LA 70130 (504) 754-6600 COUNSEL FOR PLAINTIFF-APPELLEE: Unicorp, LLC Cody C. Bailey (Admitted Pro Hac Vice) Brunini, Grantham, Grower & Hewes, PLLC Post Office Drawer 119 Jackson, Mississippi 39205 Telephone: (601) 948-3101 COUNSEL FOR PLAINTIFF-APPELLEE: Unicorp, LLC
Darren A. Patin Hailey, McNamara 3445 N. Causeway Blvd, Suite 800 Metairie, LA 70002 (504) 836-6500 COUNSEL FOR DEFENDANT-APPELLANT: BRaDD, LLC
Timothy O’Dowd O’Dowd Law Firm, LLC 924 Hodges Street Lake Charles, LA 70601 (337) 310-2304 COUNSEL FOR DEFENDANT-APPELLANT: BRaDD, LLC
Merrick “Rick” J. Norman, Jr. Taylor, Porter, Brooks, & Phillips, LLP 145 East Street Lake Charles, LA 70601 (337) 436-7781 COUNSEL FOR DEFENDANT-APPELLANT: BRaDD, LLC
John T. Andrishok Taylor, Porter, Brooks & Phillips, LLP 450 Laurel Street, 8th Floor Baton Rouge, LA 70801 (225) 381-0285 COUNSEL FOR DEFENDANT-APPELLANT: BRaDD, LLC PICKETT, Judge.
The owner of an apartment complex appeals the trial court’s judgment
granting summary judgment in favor of the contractor that constructed the complex
and ordering the owner to pay the contractor funds retained by the owner’s lender
in accordance with the parties’ contracts. For the following reasons, the trial
court’s judgment is reversed.
FACTS
On December 20, 2017, BRaDD, LLC contracted with Unicorp, LLC to
build the Erdace Apartments in Lake Charles. BRaDD funded construction of the
project with a loan by Greystone Servicing Corporation, Inc. (Greystone) that is
insured by the Federal Housing Administration (FHA), which is overseen by the
U.S. Department of Housing and Urban Development (HUD). BRaDD and
Unicorp signed two contracts with each other that bear on the issues presented
herein: a HUD Construction Contract (the Construction Contract) and AIA®
Document A201–2007 General Conditions of the Contract for Construction (the
General Conditions).1
The Construction Contract included a Retainage Reduction Rider that
provides for “the holdback of ten percent (10%) as set out in Item (4) of Article 5,
paragraph A of the Construction Contract.”2 The ten percent holdback was retained
1 “AIA®” is an acronym for “The American Institute of Architects.” 2 Article 5(A) of the Construction Contract states:
A. Each month after the commencement of Work hereunder, Contractor shall make a monthly request on HUD-92448 for payment by Owner for Work done during the preceding month. . . . Subject to the approval of Lender and HUD, Contractor shall be entitled to payment thereon in an amount equal to (1) the total value of classes of the Work acceptably completed; plus (2) the value of materials and equipment not incorporated in the Work, but delivered to and suitably stored at the site; plus (3) the value of components stored off -site in compliance with Program Obligations; less (4) ten (10) percent holdback [as this percentage may be reduced in accordance with the provisions of the Retainage Reduction Rider as provided in the Retainage Reduction Rider. In March 2020, Unicorp filed a
motion for partial summary judgment seeking to recover immediately retained
funds totaling $3,214,711. Unicorp sought to have BRaDD release the retained
funds pursuant to the terms of Section 9.8.5 of the General Conditions. BRaDD
resisted Unicorp’s demand, arguing that Article 5 of the Construction Contract
governs the release of the retained funds and that Unicorp failed to comply with
the requirements of that provision.
After conducting two hearings on the motion, the trial court granted
Unicorp’s motion and signed a judgment against BRaDD awarding Unicorp
$3,214,711, together with legal interest thereon from March 28, 2022. The trial
court designated the judgment as a final judgment, subject to immediate appeal as
provided in La.Civ.Code art. 1915(B)(1). BRaDD appealed the judgment, asserting
that the trial court erred in granting judgment in favor of Unicorp. On appeal,
BRaDD urges that the judgment violates provisions of the Construction Contract.
STANDARD OF REVIEW
“The determination of whether the words of a contract are clear and explicit
or ambiguous is a question of law.” Admin-Media, LLC v. AC of Lafayette, L.L.C.,
19-691, p. 6 (La.App. 3 Cir. 3/11/20), 297 So.3d 44, 49. Accordingly, appellate
review in a case of contract interpretation is de novo with the appellate court
determining whether the trial court interpreted the contract correctly or incorrectly.
Johnson v. Allstate Prop. & Cas. Ins. Co., 21-552 (La.App. 3 Cir. 4/27/22), 338
So.3d 109. “Contracts have the effect of law for the parties and may be dissolved
only through the consent of the parties or on grounds provided by law. Contracts
must be performed in good faith.” La.Civ.Code art. 1983. “Interpretation of a
attached hereto, if applicable](or as reduced by HUD in writing) and less (5) prior payments. 2 contract is the determination of the common intent of the parties.” La.Civ.Code art.
2045. “When the words of a contract are clear and explicit and lead to no absurd
consequences, no further interpretation may be made in search of the parties’
intent.” La.Civ.Code art. 2046.
DISCUSSION
Unicorp argues that the General Conditions govern the issues presented by
its motion for summary judgment, while BRaDD contends that the Construction
Contract governs these issues. Specifically, Unicorp argues that Section 9.8.5 of
the General Conditions obligated BRaDD to pay immediately the withheld
retainage when the contracted work was substantially complete, as defined by that
provision. Section 9.8.5 states:
The Certificate of Substantial Completion shall be submitted to the Owner and Contractor for their written acceptance of responsibilities assigned to them in such Certificate. Upon such acceptance and consent of surety, if any, the Owner shall make payment of retainage applying to such Work or designated portion thereof. Such payment shall be adjusted for Work that is incomplete or not in accordance with the requirements of the Contract Documents.
Unicorp and BRaDD accepted the responsibilities assigned to each of them
by a Certificate of Substantial Completion dated June 3, 2020. Additionally,
Unicorp served a List of Material Facts not in Dispute on BRaDD which included
the following:
BRaDD agreed to and accepted the Certificates of Substantial Completion, and the surety consented to the release of all retainage. No punch list items were identified at substantial completion. However, BRaDD has not paid any part of the Retainage to Unicorp.
BRaDD admitted that it accepted the Certificates of Substantial Completion
and that the surety on Unicorp’s bond consented to the release of retainage but
denied the remainder of the asserted material fact, stating “punch list items were
identified at substantial completion and thereafter, and which items remain to be 3 completed.” In line with this denial, BRaDD contends that Unicorp is not entitled
to the retainage at this time because Article 5 of the Construction Contract conflicts
with Section 9.8.5 of the General Conditions and, therefore, Article 5 governs the
release of the retainage.
Articles 1 and 2 of the Construction Contract provide that the parties’
contract consists of the Construction Contract and additional documents identified
in Article 2(A)(2), which include the General Conditions. Article 2(A)(2)
(emphasis added) further provides that “If any of the provisions of this Agreement
conflict with the terms contained in the General Conditions, the provisions in this
Agreement shall control.”
Article 5 of the Construction Contract is entitled “Requisition and Payment
Procedures” and provides the procedures for Unicorp to obtain payments for its
work. Article 5(A) provides for monthly requests for work that the contractor
performed “during the preceding month,” while section (B) provides “final
payment” for “all unpaid obligations contracted in connection with the Work
performed under this Contract,” and lastly, section (C) provides for payment of
“the balance due to Contractor.” BRaDD asserts that the “balance due” includes
the retainage and that Unicorp can only collect payment of the “balance due” after
the following conditions set forth in Article 5(C) have been satisfied:
The balance due to Contractor hereunder shall be payable upon the expiration of thirty (30) days after the Work hereunder is fully completed, provided the following have occurred: (1) all Work hereunder requiring inspection by Governmental Authorities having jurisdiction has been inspected and approved by such authorities and by the rating or inspection organization, bureau, association or office having jurisdiction; (2) all certificates of occupancy, or other approvals, with respect to the Project have been issued by Governmental Authorities; (3) Permission(s) to Occupy (HUD-92485) for all units of the Project have been issued by HUD; (4) where applicable, HUD shall have approved Contractor’s Certificate of Actual Cost; (5) as-built Drawings and Specifications, the as-built survey and all warranties shall have been delivered to Owner; and (6) 4 all executed final advance documents required by HUD have been submitted.
Unicorp counters that Article 5(C) pertains to final payment only, not
payment of the retainage. This argument overlooks the construction of Article 5
and treats paragraphs (B) and (C) thereof as a single provision. Article 5(C)
addresses “balance due,” not “final payment.” In other words, Unicorp equates the
term “final payment” to “balance due.” Unicorp further asserts that because Article
5(C) does not contain the term “retainage,” it does not pertain to the retainage
withheld pursuant to the Retainer Reduction Rider as set forth in Article 5(A).
Unicorp then points out that Section 9.8.5 of the General Conditions is the only
provision of the Contract Documents that addresses the release of the “retainage”
and concludes that there is no conflict between the Construction Contract and
Section 9.8.5 of the General Conditions because it specifically uses the term
“retainage.”
Unicorp’s argument overlooks the difference between Article 5’s use of the
terms “final payment” and “balance due.” Article 5(B) governs Unicorp’s request
to receive “final payment,” while Article 5(C) governs the “balance due.” Contrary
to Unicorp’s argument, “balance due” in Article 5(C) has been held to be “retained
amounts,” and, as such, it is not “final payment.” In Trans-Bay Engineers &
Builders, Inc. v. Hills, 551 F.2d 370, 374 (D.C. Cir.1976), as here, “The
Construction Contract authorized the payment of monthly draws incremental
payments based upon completed construction, but minus a 10% retention or
‘holdback’.” The court concluded that these “retained amounts” are “holdback”
that “‘shall be payable’ to the contractor . . . after construction has been completed
provided certain preconditions were met.” Id. at 375, citing Article 3(C) of the
Construction Contract at issue therein, which is identical to Article 5(C) of the
5 Construction Contract at issue here. See also, Van-Tex, Inc. v. Pierce, 703 F.2d 891
(5th Cir. 1983).
The court’s determination in Trans-Bay, 551 F.2d 370, gives meaning to all
three terms of payment identified in Article 5(A), (B), and (C), whereas Unicorp’s
interpretation of the terms “final payment” and “balance due” effectively
eliminates one of those terms. For these reasons, we conclude that the terms of
Section 9.8.5 of the General Conditions conflict with the terms of Article 5 of the
Contract and, therefore, Article 5 of the Contract controls the release of the
retainage.
BRaDD established that Section 5 of the Construction Contract governs the
release of the retainage. Having based its claim to obtain partial release of the
retainage solely on Section 9.8.5 of the General Conditions, Unicorp did not prove
that it satisfied the requirements of Section 5 of the Construction Contract.
Accordingly, BRaDD has established that a genuine issue of material fact exists as
to whether Unicorp is entitled to recover $3,214,711 for retainage at this time.
DISPOSITION
For these reasons, the judgment of the trial court granting partial summary
judgment in favor of Unicorp, LLC and against BRaDD, LLC in the amount of
$3,214,711, together with legal interest thereon from March 28, 2022, is reversed.
All costs associated with this appeal are assessed to Unicorp, LLC.