Bennett Construction Co. Inc. v. Allen Gardens, Inc.

433 F. Supp. 825, 1977 U.S. Dist. LEXIS 15439
CourtDistrict Court, W.D. Missouri
DecidedJune 14, 1977
Docket73CV515-W-4
StatusPublished
Cited by34 cases

This text of 433 F. Supp. 825 (Bennett Construction Co. Inc. v. Allen Gardens, Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bennett Construction Co. Inc. v. Allen Gardens, Inc., 433 F. Supp. 825, 1977 U.S. Dist. LEXIS 15439 (W.D. Mo. 1977).

Opinion

MEMORANDUM AND ORDER

ELMO B. HUNTER, District Judge.

By this action plaintiff Bennett Construction Company (Bennett) seeks to recover unpaid contract installments and retainages and unpaid expenses for extra labor and *828 materials expended in the construction of a low income housing project known as Allen Gardens. When first filed, this suit named as defendants the Secretary of the Department of Housing and Urban Development (HUD), mortgage insurer and present mortgagee of the Allen Gardens project; Allen Gardens, Inc., a not-for-profit Missouri corporation and owner of the Allen Gardens project; Charles F. Curry & Company (Curry), a private corporate lender and original mortgagee of the Allen Gardens project; Mr. M. C. Kenn, original trustee under the deed of trust on the Allen Gardens properties; and Mr. William H. Johnson, architect of the Allen Gardens project. As finally submitted, however, this action is limited solely to claims against defendant HUD and all other defendants have been dismissed by plaintiff.

As the only two remaining-litigants, Bennett and HUD have submitted this case upon an agreed pretrial order which incorporates a designation of the legal issues remaining for the Court’s determination and a complete stipulation of the facts, including the sum due plaintiff should it prevail on the issue of liability. Because the facts have been stipulated in the form of more than two hundred separate paragraphs, the Court will not endeavor to set those facts out in full but will only reference to those factual matters which are significant in the context of the ultimate decision in this case.

BACKGROUND OF THE LITIGATION

In July, 1969, the Allen Chapel AME Church, an unincorporated association located in Kansas City, Missouri, submitted through Curry an application for mortgage insurance on a proposed low income multifamily housing project to be constructed in Kansas City. That application sought a commitment from the Federal Housing Administration, an organizational unit within HUD, to fully insure a loan equivalent to 100% of the estimated development costs of the project under the provisions of § 236 of the National Housing Act, 12 U.S.C. § 1715z-l. The provisions of that section as implemented by HUD are intended to spur the construction or rehabilitation of rental and cooperative housing for lower income families by means of federally insured private mortgage financing and federally funded interest reduction payments for the life of the insured mortgage.

In December, 1969, after application review, project appraisal and income analyses, site approval, and other internal agency procedures, HUD accepted the proposed Allen Gardens project as an insurable risk and invited the Allen Chapel Church to submit an application for conditional commitment for mortgage insurance on the project. That application was submitted and on May 21, 1970, HUD committed to insure a loan from Curry for 100% of the estimated development cost of the Allen Gardens project to a maximum of $1,317,000. The commitment was made with full knowledge that the project sponsor, Allen Chapel Church, had no financial assets or other resources to contribute toward the development of the project other than borrowed funds and future rental income which might be received from project tenants. On July 1, 1970, a not-for-profit corporation, Allen Gardens, Inc., was incorporated to function as the nominal owner and mortgagor of the Allen Gardens project. All necessary incorporation fees were paid from loan proceeds insured by HUD.

Following the insolvency of the construction company originally approved by HUD as general contractor on the project, Curry contacted plaintiff Bennett Construction Company. Plaintiff was assured by a Curry representative that as general contractor on the Allen Gardens project it would be paid, that the project was legitimate with a solvent sponsor which had sufficient funds available to it to pay construction costs, and that HUD was behind the project and committed to insure it. Bennett was not informed that Allen Gardens, Inc. had no funds of its own to invest in the project; however, Bennett neither conducted an in *829 dependent inquiry into the financial status of the sponsor nor required it to produce a financial statement. On approximately August 8, 1970, plaintiff submitted to HUD the required contractor’s cost breakdown which reflected a total estimated cost of construction of $1,043,322. That cost, which was acceptable to and approved by HUD, was subsequently established as the maximum figure payable to Bennett under the terms of the construction contract.

On September 18, 1970, initial closing of the project was held. At that time, plaintiff and Allen Gardens, Inc. entered into a cost plus construction contract by which Allen Gardens, Inc. agreed to pay Bennett as general contractor the cost of construction plus a fixed fee to a maximum of $1,043,322 upon full completion of the project, a term defined by the contract. Also as part of the initial closing, Allen Gardens, Inc. entered into a building loan agreement with Curry whereby Curry contracted to make a loan for the construction of the project in the sum of $1,317,000. In consideration of that loan, Allen Gardens, Inc. executed a deed of trust note payable to Curry in an amount equal to the loan and a deed of trust conveying the Allen Gardens properties to M. C. Kenn in trust for Curry. As required by HUD as a condition to its insurance commitment, the building loan agreement and the construction contract were executed on HUD standard forms. The mortgage documents were likewise prepared by HUD. 1

Bennett began actual construction of the Allen Gardens project on October 16, 1970. Approximately one year later the first tenants moved into the project and on April 30, 1972, the Project Inspection Report (FHA Form 2449) was executed indicating substantial completion of the project. Bennett continued work on the project pursuant to the construction contract’s warranty on latent defects until April 19, 1973, and at HUD’s request until July 2, 1973. On that date an agency inspector advised Bennett that its construction responsibility had been completed. Federal Housing Administration officials certified on August 31, 1973, that the project was fully and satisfactorily completed. During the entire period of construction, Bennett acted totally in good faith and was always willing to proceed with and complete the project.

Subsequent to the date of substantial completion but prior to final completion of the project, Allen Gardens, Inc., defaulted on its obligations under the mortgage agreement with Curry. By the terms of the loan agreement, Allen Gardens, Inc., was to commence monthly payments of the loan principal on July 1, 1972. None of those principal payments, all of which were to be paid from funds other than loan proceeds, has ever been made. On March 1, 1973, Curry advised HUD that it intended to file a formal notice of default in the “very near future”. That notice was formally filed with HUD on April 12, 1973. Bennett however, was never advised of the mortgagor’s default commencing July 12th until after construction work had been completed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hayduk v. United Parcel Service, Inc.
930 F. Supp. 584 (S.D. Florida, 1996)
Ryan v. Dow Chemical Co.
781 F. Supp. 934 (E.D. New York, 1992)
Embree Construction Group, Inc. v. Rafcor, Inc.
411 S.E.2d 916 (Supreme Court of North Carolina, 1992)
Iota Management Corp. v. Boulevard Investment Co.
731 S.W.2d 399 (Missouri Court of Appeals, 1987)
United States v. Conservation Chemical Co.
653 F. Supp. 152 (W.D. Missouri, 1986)
Metz v. McKinley
583 F. Supp. 683 (S.D. Georgia, 1984)
Robinson v. US, Through Small Business Admin.
551 F. Supp. 1120 (M.D. Louisiana, 1982)
Monal Construction Co. v. Brookside Ltd. Partnership
539 F. Supp. 478 (W.D. Pennsylvania, 1982)
Armor Elevator Co., Inc. v. Phoenix Urban Corp.
493 F. Supp. 876 (D. Massachusetts, 1980)
Gee v. Eberle
420 A.2d 1050 (Superior Court of Pennsylvania, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
433 F. Supp. 825, 1977 U.S. Dist. LEXIS 15439, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bennett-construction-co-inc-v-allen-gardens-inc-mowd-1977.