Commercial Standard Insurance v. Bryce Street Apartments, Ltd.

703 F.2d 904
CourtCourt of Appeals for the Fifth Circuit
DecidedApril 25, 1983
DocketNo. 81-1578
StatusPublished
Cited by1 cases

This text of 703 F.2d 904 (Commercial Standard Insurance v. Bryce Street Apartments, Ltd.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commercial Standard Insurance v. Bryce Street Apartments, Ltd., 703 F.2d 904 (5th Cir. 1983).

Opinion

PATRICK E. HIGGINBOTHAM, Circuit Judge:

This is the third and final case we decide today concerning rights to construction holdbacks on projects financed by HUD-insured mortgages. Commercial Standard [906]*906Insurance Co., a surety, brought suit against HUD and several other parties to recover amounts it had paid in satisfaction of subcontractors’ claims. It urged that it was entitled to recover the sum of unadvanced mortgage proceeds from HUD both because the subcontractors were third-party beneficiaries and on grounds of unjust enrichment. After a bench trial, the district court entered a judgment against HUD on a third-party beneficiary rationale awarding Commercial Standard the retainage, less any amount it recovered under a separate indemnity agreement. We affirm.

Facts and Procedural History

This appeal, unlike the preceding two, is concerned with a § 236 (12 U.S.C. § 1715z-1) low-income housing project. In May 1972, HUD executed a commitment to insure mortgage advances in a low-income housing project in Fort Worth, Texas. Ryan Mortgage Co. was the mortgagee on this $386,500 mortgage; Bryce Street Apartments, Ltd., a for-profit limited partnership, was the mortgagor.

The initial closing took place in June, at which time Ryan and Bryce Street signed the building loan agreement. At the same time Bryce Street and Lindsey Construction Co. entered into a cost-plus construction contract. Lindsey Construction Co., a sole proprietorship, was owned by the general partner in Bryce Street. Thus the familiar “identity of interest” existed.

Both the building loan agreement and the cost-plus construction contract were on the usual HUD-prescribed forms. The former contained the standard provision relating to holdbacks:

The Borrower shall make monthly applications on FHA Form No. 2403 for advances of mortgage proceeds from the Lender. Applications for advances with respect to construction items shall be for amounts equal to (i) the total value of classes of the work acceptably completed; plus (ii) the value of materials and equipment not incorporated in the work, but delivered to and suitably stored at the site; less (iii) 10 percent (holdback) and less prior advances....
... The balance due the Borrower hereunder shall be payable at such time after completion as the commissioner authorizes the release of the holdback. However, the Lender may withhold final payment until after the expiration of any period which mechanics and materialmen may have for filing liens.

So did the latter:

The balance due the Contractor hereunder shall be payable upon the expiration of 30 days after the work hereunder is fully completed, provided the following have occurred:
(1) All work hereunder requiring inspection by municipal or other governmental authorities having jurisdiction has been inspected and approved by such authorities ...
(2) All certificates of occupancy, or other approvals, with respect to all units of the project have been issued by State or local governmental authorities having jurisdiction; and
(3) Permissions to occupy (FHA Form No. 2485) for all units of the project have been issued by the Commissioner.

Commercial Standard furnished a payment and performance bond in connection with the construction contract. Work on the project commenced soon thereafter. Pursuant to the terms of the building loan agreement, Ryan withheld 10 percent retainage as construction proceeded. By April 1973, Lindsey Construction Co. had completed all physical construction. On November 3, 1973, after application had been made for the final advance, Bryce Street defaulted on its obligations. Ryan requested HUD to authorize release of the final advance and to insure that amount; HUD refused. Ryan subsequently foreclosed on the property and deeded it to HUD in return for the mortgage insurance. HUD eventually sold the project for $256,000.

Following the completion of construction, various unpaid subcontractors filed liens against the property. Commercial Standard compromised their claims, then brought the present action as subrogee [907]*907against Lindsey Construction, Bryce Street, Ryan Mortgage, the Secretary of HUD, and the guarantors on an indemnity agreement. After a bench trial, in which most of the fact issues were stipulated, the district court held that Commercial Standard was entitled to recover the retainage from HUD, less any amount it recovered from other parties under a separate indemnity agreement. The district court’s damage award was based on the conclusion that Commercial Standard was the subrogee of third-party beneficiaries of the building loan agreement, and had a valid third-party beneficiary claim against HUD. HUD appeals the district court’s judgment, asserting several reasons why recovery should not have been granted. We will deal with them in turn, beginning with those that were presented to the court below.

Trans-Bay Once More

In Trans-Bay Engineers & Builders, Inc. v. Hills, 551 F.2d 370 (D.C.Cir.1976), as we have noted in Van-Tex, Inc. v. Pierce, 703 F.2d 891, the D.C. Circuit held that a retainage-less contractor on a defaulting § 236 project had two avenues of recovery from HUD — third-party beneficiary and unjust enrichment. These two theories of recovery have been sustained in other cases. See, e.g., Spring Construction Co. v. Harris, 562 F.2d 933 (4th Cir.1977). In this appeal HUD does not dispute the general principle that a § 236 contractor or, as here, a § 236 subcontractor may be a third-party beneficiary of the building loan agreement. Indeed HUD in its brief says, “We have no difficulty with this as a general statement.” Therefore we shall assume for the purposes of this case third-party beneficiary status, and leave the issue to be decided by another panel on another day.

HUD’s Liability on the Building Loan Agreement

HUD argues, however, that even if the subcontractors could recover from the original mortgagee, they have no claims against HUD. The agency, it contends, never assumed the obligations of the building loan agreement. HUD emphasizes that in this case, unlike in Trans-Bay and Spring Construction, the mortgagee foreclosed on the property before the assignment to HUD took place. Thus, HUD only assumed property rights and claims, not lending obligations.

We are not convinced. The act of foreclosure cannot extinguish third-party beneficiary claims against the mortgagee. When HUD was assigned the mortgagee’s property rights and its claims against the mortgagor, it also assumed the mortgagee’s liabilities under the building loan agreement. The building loan agreement itself expressly states, “As used in this instrument, the term ‘Lender’ shall be deemed to include any person to whom the Note and Mortgage referred to above shall be assigned with the knowledge and consent of the Commissioner.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
703 F.2d 904, Counsel Stack Legal Research, https://law.counselstack.com/opinion/commercial-standard-insurance-v-bryce-street-apartments-ltd-ca5-1983.