Spring Construction Co. v. Harris

562 F.2d 933
CourtCourt of Appeals for the Fourth Circuit
DecidedSeptember 29, 1977
DocketNo. 76-2399
StatusPublished
Cited by15 cases

This text of 562 F.2d 933 (Spring Construction Co. v. Harris) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Spring Construction Co. v. Harris, 562 F.2d 933 (4th Cir. 1977).

Opinion

K. K. HALL, Circuit Judge:

Plaintiff, Spring Construction Company, Inc., brought suit against the Secretary of the Department of Housing and Urban Development (HUD), Parker-Riddick Village, Inc., and Cogic Homes, Inc., seeking damages for breach of contract and equitable relief. After a trial by the court, the district court denied plaintiff any relief and entered judgment for the defendant. Plaintiff appealed. Parker-Riddick Village, Inc., and Cogic Homes, Inc., are not parties in this appeal.

We reverse the judgment of the district court and remand with instructions.

I.

FACTS

This suit arose from plaintiff’s participation as a contractor in a federally-insured housing project. The relevant parties involved in the undertaking were:

1. Spring Construction Company (Spring) — plaintiff/ appellant.

2. Department of Housing and Urban Development (HUD) — defendant/appellee.

3. Cogic Homes, Inc. (COGIC)— owner/mortgagor.

4. Parker-Riddick Village, Inc. (ParkerRiddick) — owner/mortgagor.

[935]*9355. VNB Mortgage Corporation (VNB)— mortgagee.

The owners, both nonprofit, nonasset corporations, negotiated successfully with HUD and VNB to acquire money for the construction of two low-income housing developments. Pursuant to the appropriate provisions of the National Housing Act, 12 U.S.C. §§ 1701 et seq., the owners received 100% financing, and plaintiff was named the prime contractor.

One of the many requirements which must be met before a housing project can receive HUD approval is that provision must be made for sewer connections. Without placing blame on any party, it is apparent that the initial closing occurred on June 9, 1971, without proper arrangements having been made for sewer connections. The facts are disputed as to when HUD knew, or should have known, of this complication, but it is stipulated that HUD was informed of the sewer problem by plaintiff on or about September 1, 1971. A meeting was held on January 12, 1972, at which a solution to the problem was sought, but no resolution of the difficulty resulted.

Despite HUD’s knowledge of the sewer problem, it continued insuring mortgage advances from VNB to the owners, and, furthermore, HUD officials instructed plaintiff to continue work on the project while a solution to the problem was sought. Defendant Hills’ Supplemental Answers to Interrogatories of Plaintiff.1 Finally, on October 12, 1975, HUD informed the mortagee, VNB, that HUD would no longer insure mortgage advances; VNB refused further advances, and the project was shut down. The reasons given for HUD’s withdrawal of the mortgage insurance all centered around the sewer dilemma.

The construction contract entered into by plaintiff and the owners of the project provided for monthly payments to the plaintiff with a 10% holdback, or retainage, from the amounts so paid. Concurrently, the building loan agreements between the owners and the mortgagee provided for a similar 10% holdback which was not to be paid to the mortgagors until approved by HUD.

At the time of the shutdown, the projects were 81.5% completed. Plaintiff had incurred substantial amounts in holdbacks by this time, in addition to other sums plaintiff claims for unpaid requisitions, additional work and material, lost profits and interest. We express no opinion at this time concerning the legitimacy of the individual claims. The projects were never completed by the parties herein, and after VNB assigned its rights and obligations under the various agreements to HUD, the projects were sold at a $2,100,000 loss.

II.

CONTRACTUAL REMEDIES

Plaintiff clearly has no cause of action against HUD based on the construction contracts between it and the two owners, because HUD was not a party to those agreements. Instead, plaintiff asserts that it is a creditor third party beneficiary of the building loan agreements between the two owners and the mortgagee. Under this theory, plaintiff would assume the legal positions of the mortgagors, possessing the same rights and obligations as the mortgagors. The obligation of HUD to pay the retainages to the plaintiff is premised on the fact that HUD assumed the obligations of the mortgagee upon the assignment of the building loan agreements from VNB to HUD, after the project collapsed.

A. Creditor Third Party Beneficiary.

During oral argument, defendant conceded that had plaintiff completed or been wrongfully prevented by HUD from completing the projects, the plaintiff would be a creditor third party beneficiary under [936]*936the building loan agreements.2 Although we intimate no opinion on whether completion or wrongful prevention of completion by HUD is a necessary prerequisite to third party beneficiary status in this case, our holding that defendant waived any defense of nonperformance it may have possessed eliminates the necessity of considering the aforesaid as possible bars to plaintiff’s third party beneficiary status. See part 11(C) infra.

B. HUD’s Duty to Pay Retainages.

Defendant’s own regulations provide that:

The mortgagee shall be obligated, as a part of the mortgage transaction, to disburse the principal amount of the mortgage, to, or for the account of the mortgagor or to his creditors for his account and with his consent.

24 C.F.R. § 221.512. The implications of this section accompanied with the assignment of the building loan agreement to HUD were aptly stated by the district court in Bennett, supra:

Inasmuch as HUD assumed the obligations of “lender” or “mortgagee” upon [the mortgagee’s] assignment and pursuant to paragraph 18 of the building loan agreement,1 it is equally obligated by regulation to dispurse (sic) proceeds to the mortgagor or the mortgagor’s creditors.

Bennett, supra at 832-33.

In this case, the relevant statutory provisions and contractual clauses are almost identical to those in Bennett. Because we agree with the district court’s reasoning therein, we hold that plaintiff is entitled to damages as a creditor third party beneficiary of the building loan agreement, unless defendant raises an effective bar to plaintiff’s recovery.

C. Defense of Nonperformance: Failure to Complete the Contract.

Defendant raises several contentions in opposition to plaintiff’s recovery under the third party beneficiary theory. The thrust of all these contentions is that even if HUD is primarily obligated to pay the retainages to plaintiff under the third party beneficiary theory, plaintiff’s failure to complete the contract is a bar to recovery. The mortgagee was not required to pay the 10% holdback to the mortgagor under the building loan agreement until “such time after completion as the commissioner authorizes the release of the holdback.” Building Loan Agreement 1 (4)(b). Inasmuch as under the third party beneficiary theory, the plaintiff assumes both the rights and obligations

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arthur J. Fulcher, Jr. v. United States
632 F.2d 278 (Fourth Circuit, 1980)
Armor Elevator Co., Inc. v. Phoenix Urban Corp.
493 F. Supp. 876 (D. Massachusetts, 1980)
Capitol Indemnity Corp. v. Freedom House Development Corp.
487 F. Supp. 839 (D. Massachusetts, 1980)
Spring Construction Co. v. Harris
614 F.2d 374 (Fourth Circuit, 1980)
United States v. Mill Ass'n, Inc.
480 F. Supp. 3 (E.D. New York, 1979)
Spring Construction Company, Inc. v. Harris
562 F.2d 933 (Fourth Circuit, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
562 F.2d 933, Counsel Stack Legal Research, https://law.counselstack.com/opinion/spring-construction-co-v-harris-ca4-1977.