USA for the use and Benefit of Spirtas Worldwide, LLC v. SGLC Consulting LLC

CourtDistrict Court, S.D. Illinois
DecidedJune 13, 2022
Docket3:21-cv-00182
StatusUnknown

This text of USA for the use and Benefit of Spirtas Worldwide, LLC v. SGLC Consulting LLC (USA for the use and Benefit of Spirtas Worldwide, LLC v. SGLC Consulting LLC) is published on Counsel Stack Legal Research, covering District Court, S.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
USA for the use and Benefit of Spirtas Worldwide, LLC v. SGLC Consulting LLC, (S.D. Ill. 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE SOUTHERN DISTRICT OF ILLINOIS

USA FOR THE USE AND BENEFIT OF ) SPIRTAS WORLDWIDE, LLC, ) ) Plaintiff, ) ) Case No. 3:21-CV-00182-MAB vs. ) ) SGLC CONSULTING LLC, ET AL., ) ) Defendants.

MEMORANDUM AND ORDER

BEATTY, Magistrate Judge: BACKGROUND Plaintiff, The United States for the Use and Benefit of Spirtas Worldwide, LLC, (“Plaintiff”) filed this lawsuit on February 16, 2021 pursuant to 40 U.S.C. § 3131, et seq., (“The Miller Act”), for uncompensated subcontracting work Plaintiff alleges was conducted pursuant to a Trade Partners Agreement (“TPA”) (Docs. 1, 43, 60). Prior to filing his lawsuit, Plaintiff contends that Defendant SGLC (“SGLC”) entered into a contract with the Department of the Interior, U.S. Fish and Wildlife Service, for a demolition project and cleanup of a particular area located at the Crab Orchard National Wildlife Refuge (“Crab Orchard”) in Marion, Illinois (Doc. 60, pp. 1-2). Pursuant to the Miller Act, Defendant Westchester Fire Insurance Company (“Westchester”) provided payment and performance bonds for this project (Id. at p. 2). Plaintiff signed a TPA with SGLC on or around September 1, 2020 (Id.). While the parties disagree as to the applicability of certain terms of this agreement, the agreement generally outlined that Plaintiff would perform as a subcontractor on projects for SGLC. Id. Approximately two months later on November 4, 2020, SGLC ordered Plaintiff off of

the project. Plaintiff complied and stopped working, but, to date, SGLC has not paid Plaintiff for the work performed during those two months. Id. Approximately three months later, Plaintiff filed this lawsuit, attempting to recoup the cost of materials and labor for the projects Plaintiff completed for SGLC. When Plaintiff first filed the lawsuit, there were a total of four claims: 1) a Miller Act claim; 2) implied subcontract; 3) quantum meruit; and 4) fraud (Doc. 1).

Plaintiff filed a motion to amend its complaint on March 30, 2021, seeking to correct the name of one of the Defendants (Doc. 36). As the Defendants had not filed their responsive pleadings to Plaintiff’s complaint, the Court granted Plaintiff’s motion and the first amended complaint was filed on April 8, 2021 (Docs. 42, 43). After seeking a few extensions of time, SGLC filed a motion to compel arbitration (Doc. 47). The same day,

Defendant Grant Cunningham (“Cunningham”) filed his motion to dismiss (Doc. 48). The following day, on April 22, 2021, Westchester filed a motion to stay the proceedings or, in the alternative, motion for extension of time to file a response to Plaintiff’s amended complaint (Doc. 50). Westchester explained that, to avoid bifurcated proceedings, it would prefer to file its responsive pleading to Plaintiff’s complaint once the motion to

compel arbitration was decided. As Plaintiff did not object to this motion, the Court granted it on July 7, 2021, and stayed Westchester’s responsive pleading (Doc. 55). On August 26, 2021, Plaintiff filed its second motion to amend/correct the complaint, seeking to file an amended complaint eliminating Counts I and II of Plaintiff’s April 8, 2021 complaint. Plaintiff argued that filing this complaint would moot the motion to compel arbitration, saving the Court the trouble of issuing a decision on that motion

(Doc. 56, pp. 1-2). SGLC and Cunningham opposed the motion, filing their joint response on September 1, 2021 (Doc. 58). The Court granted Plaintiff’s motion and allowed Plaintiff one more opportunity to amend the complaint, which it did on November 29, 2021 (Doc. 59). Additionally, the Court denied, without prejudice and with leave to refile, SGLC and Cunningham’s motions (Docs. 47; 49). The operative complaint is similar to Plaintiff’s first amended complaint in that

Plaintiff brings a Miller Act claim against SGLC and then a second claim under the Illinois Consumer Fraud and Deceptive Practices Act (815 ILL. COMP. STAT. § 505/2) against Cunningham (Doc. 60, pp. 1; 8-10). In filing this complaint, Plaintiff dropped its two other claims: implied subcontract and quantum meruit claims (Doc. 43, pp. 8-10). SGLC, Cunningham, and Westchester filed their renewed motions to dismiss and to stay on

December 17 and 20, 2021, respectively (Docs. 61, 62, 63). These motions, and the responsive briefings, are presently before the Court. DISCUSSION Plaintiff brings two claims against Defendants in this matter. The first is a Miller Act claim against SGLC. The second is an Illinois fraud claim against SGLC’s President,

Co-Defendant Grant Cunningham. Westchester is added as a Defendant in Plaintiff’s Miller Act claim, as they issued the bonds to both SGLC and Plaintiff for the construction work at the Crab Orchard site. Before the Court are two main pending motions. The first is SGLC’s motion to dismiss Count I, or in the alternative, motion to compel arbitration as to Count I and stay the proceedings (Doc. 61). The second is Cunningham’s renewed motion to dismiss Count II of Plaintiff’s amended complaint. While the Court will

address these motions separately for the majority of this Order, there are certain arguments that Plaintiff makes in responses to both motions that may be referenced. I. SGLC’s Motion to Dismiss Count I for Improper Venue Plaintiff brings this case in federal court first and foremost under the Miller Act. Count I of Plaintiff’s complaint, which is against SGLC, is Plaintiff’s Miller Act claim. The Miller Act, 40 U.S.C. § 3131 et seq., seeks to protect subcontractors against nonpayment

for work performed on federal government construction projects by requiring the prime contractor to provide a payment bond on which the subcontractor can then make a claim for payment. A&C Constr. & Installation, Co. WLL v. Zurich Am. Ins. Co., 963 F.3d 705, 706 (7th Cir. 2020). Courts within the Seventh Circuit have held that a contract of some sort is necessary for a Miller Act claim. “On its face, the Miller Act provides a right of action

only for those who have a contract to furnish labor or material to the contractor or subcontractor; it does not provide a right of action for those who have a guaranty agreement with the contractor or subcontractor.” U.S., Dep't of the Navy v. Norden Enterprises, LLC, No. 01-C-8968, 2004 WL 42318, at *5 (N.D. Ill. Jan. 6, 2004) (quoting U.S. ex rel. Gold Bond Bldg. Prods. v. Blake Constr. Co., Inc., 820 F.2d 139, 142 (5th Cir.1987)).

Furthermore, courts have repeatedly held that Miller Act claims are arbitrable. Gatlin Plumbing & Heating, Inc. v. Welty Bldg. Co., No. 212-CV-114-TLS, 2013 WL 704736, at *7 (N.D. Ind. Feb. 26, 2013); U. S. for Use & Benefit of Frank A. Trucco & Sons Co. v. Bregman Const. Corp., 256 F.2d 851 (7th Cir. 1958). SGLC argues that dismissal of the Miller Act claim is appropriate for two main reasons (Doc. 61). The first is that an agreement to arbitrate exists between the parties,

contained in the parties’ TPA; therefore, Plaintiff’s claim must be dismissed so that the parties can seek arbitration pursuant to the language of the TPA. SGLC further argues that Plaintiff cannot avoid the arbitration clause in the TPA by only filing certain claims, like a claim under the Miller Act, because ultimately, the TPA governs the parties’ interactions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Prima Paint Corp. v. Flood & Conklin Mfg. Co.
388 U.S. 395 (Supreme Court, 1967)
Dean Witter Reynolds Inc. v. Byrd
470 U.S. 213 (Supreme Court, 1985)
Circuit City Stores, Inc. v. Adams
532 U.S. 105 (Supreme Court, 2001)
Howsam v. Dean Witter Reynolds, Inc.
537 U.S. 79 (Supreme Court, 2002)
Raghunathan v. Holder
604 F.3d 371 (Seventh Circuit, 2010)
Buckeye Check Cashing, Inc. v. Cardegna
546 U.S. 440 (Supreme Court, 2006)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Alfred Janiga v. Questar Capital Co
615 F.3d 735 (Seventh Circuit, 2010)
Reynolds v. CB Sports Bar, Inc.
623 F.3d 1143 (Seventh Circuit, 2010)
Faulkenberg v. CB Tax Franchise Systems, LP
637 F.3d 801 (Seventh Circuit, 2011)
Tapia v. United States
131 S. Ct. 2382 (Supreme Court, 2011)
Schulze and Burch Biscuit Company v. Tree Top, Inc.
831 F.2d 709 (Seventh Circuit, 1987)
Christopher L. Gore v. Alltel Commu
666 F.3d 1027 (Seventh Circuit, 2012)
Athey Products Corporation v. Harris Bank Roselle
89 F.3d 430 (Seventh Circuit, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
USA for the use and Benefit of Spirtas Worldwide, LLC v. SGLC Consulting LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/usa-for-the-use-and-benefit-of-spirtas-worldwide-llc-v-sglc-consulting-ilsd-2022.