United States v. Motor Vessel Gopher State

614 F.2d 1186, 1982 A.M.C. 1518
Court of Appeals for the Eighth Circuit·Decided February 12, 1980·No. Nos. 79-1401, 79-1436·Published·Cited by 19 cases

Opinion

ROSS, Circuit Judge.

This is an admiralty ease brought by the United States for the cost of repairs to a lock on the Mississippi River resulting from a collision of a vessel with two miter gates within the lock.

On June 30, 1975, the Motor Vessel Gopher State and her tow, owned and operated by Midwest Towing, Inc. (Midwest), collided with and damaged two upper miter gates of Mississippi River Lock 25, located at Winfield, Missouri. Damage to such a structure results in liability without fault under the Rivers and Harbors Act of 1899, 33 U.S.C. § 408. The parties stipulated that $2,420 would be adequate to repair Gate No. 2, which suffered minor damage. Repairs to Gate No. 4, severely damaged, were estimated by the Army Corps of Engineers to be $99,959.61; actual costs claimed after the repairs were made amounted to $156,-527.65. The district court awarded the United States $100,000 as the reasonable cost of repairing Gate No. 4; $2,420 as stipulated by the parties for damages to Gate No. 2; $1,000 as a penalty pursuant to 33 U.S.C. § 411 for hitting the gates; and prejudgment interest pursuant to Section 407.020 R.S.Mo.1969, at a rate of six percent. We affirm, but remand for a redetermination of the prejudgment interest.

On appeal, the United States contends that the district court erred: (1) in finding the actual costs of repair to be unreasonable to the extent that they exceeded the United States’ estimated costs as to Miter Gate No. 4; and (2) in granting prejudgment interest mechanically at the six percent Missouri statutory rate rather than at a truly compensatory rate. Midwest cross-appeals challenging the award of prejudgment interest in any amount.

In an admiralty case, the findings of fact of a district court, sitting without a jury, may not be set aside unless clearly erroneous. United Barge Co. v. Notre Dame Fleeting & Towing Service, Inc., 568 F.2d 599, 602 (8th Cir. 1978); Midland Enterprises v. Notre Dame Fleeting & Towing Service, Inc., 538 F.2d 1356, 1357 (8th Cir. 1976). Factual findings are clearly erroneous only when unsupported by substantial evidence or based on an erroneous conception of the applicable law, Southern Illinois Stone Co. v. Universal Engineering Corp., 592 F.2d 446, 451 (8th Cir. 1979), or when “the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed.” McAllister v. United States, 348 U.S. 19, 20, 75 S.Ct. 6, 8, 99 L.Ed. 20 (1954), (quoting United States v. United States Gypsum Co., 333 U.S. 364, 395, 68 S.Ct. 525, 541-542, 92 L.Ed. 746 (1948)).

The district court held that the government failed to prove the reasonableness of the amount claimed above its original estimate for the repairs.1 Although we disagree with the use of the estimate in ascertaining the award of damages, we cannot say that the district court’s determination of the facts is clearly erroneous or is based on an erroneous conception of the [1188]*1188applicable law. Substantial evidence supports those findings, which were based on the following evidence.

Pursuant to regulation and custom, the United States Corps of Army Engineers prepared a formal, detailed, and itemized estimate of the projected costs of repairing the damaged gates. That estimate was prepared by a civil engineer employed by the Corps of Engineers and was approved by the head of the Lock and Dam Section, the Chiefs of the Finance and Accounting Branch and Program and Development Offices, and the Corps’ District Engineer. The estimate, based on the experience of the Corps of Engineers in repairing similar damage, reflected a cost of $91,668.00 as the cost of repair, plus an overhead charge of $8,291.61, for a total of $99,959.61 in estimated damages. A final bill of $157,402.15 was submitted to Midwest. Although the estimate correctly ascertained the amount of material and equipment needed to complete the project, it was highly inaccurate in determining labor and overhead charges.2

As the district court found, a comparison of the estimates with the final invoice reflects a gross disparity between the amount estimated and the amount claimed for both labor and overhead charges. Offsite labor hours were originally estimated at 3600 labor hours; the final invoice charged Mid-west with 5409 hours of labor, which is an increase of 50 percent over the amount estimated. Accordingly, the cost of offsite labor was adjusted upward from $42,408.00 to $80,224.21. Overhead actually billed amounted to $53,421.32, a sum $45,129.71 or 544 percent greater than the amount reflected in the original estimate. This increase, ridiculous on its face, undoubtedly influenced the trial court in arriving at the proper figure to be allowed.

The government did not solicit bids from any private contractors to determine the amount they would have charged to repair the damaged gates, although it was authorized to do so and in fact had done so on past occasions. Evidence adduced at trial established that the miter gates could possibly have been repaired by private contractors for $100,000, provided they were removed from the lock by the Corps of Engineers. Further, a survey conducted on behalf of Midwest by a marine surveyor, Merrill Marine Services, Inc., mirrored the Corps’ original computation of the estimates of costs of repair.

Based on this evidence, the district court found that the United States failed to meet its burden of proving that the sum of $157,-000.00 constituted a fair and reasonable charge for the repairs to the damaged gates. Testimony was introduced to establish that miter repair job costs were sometimes greater than anticipated. However, the district court credited the testimony of two independent marine surveyors who stated that the labor charges were unreasonably high. Those surveyors were highly qualified and experienced in estimating such costs. In fact, one of the two independent marine surveyors testifying had previously been employed by the Corps of Engineers as an expert in a case involving similar lock damage.

In an effort to meet its burden of proving that the amount of labor charged was necessary to complete the job, the government called the Acting Chief of the Plant Branch of the St. Louis Corps of Engineers who testified that all labor charges could be accounted for as actually incurred by the Corps. However, the government failed to call as a witness the Corps’ Chief of the Service Base Section, the individual in charge of supervising the labor devoted to the Gopher State job. Moreover, it offered no explanation as to why he was not called to testify to justify the increased labor costs.

Free access — add to your briefcase to read the full text and ask questions with AI

United States v. Motor Vessel Gopher State, 614 F.2d 1186, 1982 A.M.C. 1518 (8th Cir. 1980).

614 F.2d 1186 (United States v. Motor Vessel Gopher State) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ivory v. Esper
W.D. Arkansas, 2020
White v. Martin
290 F. Supp. 2d 986 (D. Minnesota, 2003)
Gamma-10 Plastics, Inc. v. American President Lines, Ltd.
839 F. Supp. 1359 (D. Minnesota, 1993)
No. 92-1333
988 F.2d 860 (Eighth Circuit, 1993)
United States v. American Commercial Barge Line Co.
988 F.2d 860 (Eighth Circuit, 1993)
Stroh Container Co. v. Delphi Industries, Inc.
783 F.2d 743 (Eighth Circuit, 1986)
United States v. Peavey Barge Line
748 F.2d 395 (Seventh Circuit, 1984)
No. 84-1251
748 F.2d 395 (Seventh Circuit, 1984)
Ohio River Co. v. Peavey Co.
731 F.2d 547 (Eighth Circuit, 1984)
L & L MARINE SERV. v. Korf Transport Corp.
514 F. Supp. 378 (E.D. Missouri, 1981)
Slater v. Texaco, Inc.
506 F. Supp. 1099 (D. Delaware, 1981)
United States v. Motor Vessel Gopher State
614 F.2d 1186 (Eighth Circuit, 1980)