No. 84-1251

748 F.2d 395
CourtCourt of Appeals for the Seventh Circuit
DecidedNovember 8, 1984
Docket395
StatusPublished

This text of 748 F.2d 395 (No. 84-1251) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
No. 84-1251, 748 F.2d 395 (7th Cir. 1984).

Opinion

748 F.2d 395

UNITED STATES of America, Plaintiff-Appellee,
v.
PEAVEY BARGE LINE, in personam, and the M/V GREMCO, Barge PV
5985, Barge PV 5996, Barge PV 5978, Barge ABS 1448, Barge
UMC 2464, Barge PV 5903, Barge PV 2926, Barge PV 2923, and
Barge PV 5997, their appurtenances, etc., in rem,
Defendants-Appellants.

No. 84-1251.

United States Court of Appeals,
Seventh Circuit.

Argued Sept. 13, 1984.
Decided Nov. 8, 1984.

Daryl F. Sohn, Goldstein & Price, St. Louis, Mo., for defendants-appellants.

L. Lee Smith, Asst. U.S. Atty., Peoria, Ill., for plaintiff-appellee.

Before FLAUM, Circuit Judge, SWYGERT and FAIRCHILD, Senior Circuit Judges.

FLAUM, Circuit Judge.

This is an appeal of an admiralty case by the defendants following a bench trial which was limited to the issue of damages. The district court awarded the United States $425,373.24 for damages to a lock, dam, and bridge on the Mississippi River plus prejudgment interest at a rate of 11% from the date of the accident. For the reasons stated below, we affirm the decision of the district court.

I.

On July 15, 1978, the defendant Motor Vessel Gremco, operated by the Peavey Barge Line, was towing nine loaded barges near Rock Island, Illinois when one of the barges struck the guide wall of Lock and Dam No. 15, which are owned by the United States. This collision caused the remaining barges to become detached and collide with the lock's miter gates, the Rock Island Arsenal Bridge, and the roller gates of the dam. The Rock Island District of the United States Corps of Engineers began temporary repairs to the miter gates on July 31, 1978, and completed these repairs on April 27, 1979. The United States employed a private contractor for the guide wall repairs, which were completed on June 6, 1980. Repairs to the Rock Island Arsenal Bridge were completed in mid to late 1979 by a private contractor as part of a previously planned major bridge rehabilitation and renovation. At the trial in September 1983, the dam's roller gates had not yet been repaired, but the Corps of Engineers submitted an estimate of repair costs which went unchallenged by the defendant.

The United States filed suit against the defendant on June 30, 1981, claiming that it should recover for the damages it sustained to the lock and dam based on a theory of absolute liability under 33 U.S.C. Sec. 408 (1982)1 and to the bridge based on a negligence theory. Following a confession of liability by the defendant, the district court entered summary judgment for the United States on the issue of liability on December 28, 1982, and ordered a $1,000 pecuniary penalty against each of the defendant's barges pursuant to 33 U.S.C. Secs. 411 and 412. After a two-day trial at which the sole issue was the reasonableness of the damages claimed by the United States, the district court awarded the United States $425,373.242 plus prejudgment interest at a rate of 11% per annum from the date of the collision to the date of the judgment.

On appeal, the defendant claims that the district court's award of damages for such items as use of plant and equipment, use of shop and yards, motor vehicle usage, and labor on the guide wall was erroneous because these items lacked any evidentiary support. The defendant also challenges the award of overhead as being unrelated to the repair work caused by the collision and as being computed on items that constitute overhead themselves. Finally, the defendant disputes the grant of prejudgment interest from the date of the collision, if interest is granted at all, rather than from the date that the United States expended money to make the repairs. These issues will be addressed in turn below.

II.

A. Disputed Elements of Damages

In an admiralty case, as in a civil action under Rule 52(a) of the Federal Rules of Civil Procedure, the findings of fact of the district court may not be set aside unless clearly erroneous. McAllister v. United States, 348 U.S. 19, 20, 75 S.Ct. 6, 7-8, 99 L.Ed. 20 (1954); Feeder Line Towing Service, Inc. v. Toledo, Peoria & W. R.R. Co., 539 F.2d 1107, 1110 (7th Cir.1976). According to the Supreme Court, a finding is "clearly erroneous" when although there is evidence to support it, the appellate court on the entire evidence is left with the definite and firm conviction that a mistake has been committed. United States v. United States Gypsum Co., 333 U.S. 364, 395, 68 S.Ct. 525, 541, 92 L.Ed. 746 (1948). When reviewing for clear error in the district court's findings, the appellate court must be especially circumspect if there has been conflicting evidence on controverted issues of fact. Indiana State Employees Ass'n v. Negley, 501 F.2d 1239, 1241 (7th Cir.1974).

In this case, the defendant disputes the district court's award of $52,327.00 for use of plant and equipment on the miter gate repair project, $2,262.39 for use of shop and yards, $1,644.00 for motor vehicle usage, and $4,825.59 for the Army Corps of Engineers' labor on the guide wall repairs.3 The defendant claims that the Corps merely offered testimony identifying each item rather than proving that the charge was necessary and reasonable.4 The district court found that the charges for use of plant and equipment, use of shop and yards, and motor vehicle usage were items which bore a "reasonable relationship to the Corps' experience in equipment breakage and obsolescence." United States v. Peavey Barge Line, 590 F.Supp. 319 at 323-324 (C.D.Ill.1984) ("Memorandum Opinion"). The district court noted that certain amounts for items claimed by the United States could be determined by applying a fixed percentage to specific costs. Id. However, the court noted that the plaintiff has to prove that there exists a reasonable basis to apply that item to a particular repair claim. Id. Applying this test, the court disallowed the United States' claim of $38.41 for handling charges, $1,101.62 for per diem and transportation, $24.90 for reproduction services, and $922.56 for tool, furniture, and equipment replacement.5 Id.

The district court also found that the $4,825.59 for Corps labor related to the guide wall repairs was an appropriate charge. Id. at 324-325. The court held that this charge was supported by testimony that the figure was derived from time cards for the period that Corps laborers worked on the repairs. Id. The testimony revealed that services of such technical people as engineers were charged to the job as labor if they devoted more than an hour to the repairs. Id. at 325 n. 9.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. United States Gypsum Co.
333 U.S. 364 (Supreme Court, 1948)
McAllister v. United States
348 U.S. 19 (Supreme Court, 1954)
United States v. THE M/V MARTIN
198 F. Supp. 171 (S.D. Illinois, 1961)
L & L MARINE SERV. v. Korf Transport Corp.
514 F. Supp. 378 (E.D. Missouri, 1981)
United States v. Motor Vessel Gopher State
472 F. Supp. 556 (E.D. Missouri, 1979)
United States v. Peavey Barge Line
590 F. Supp. 319 (C.D. Illinois, 1984)
Department of Water & Power v. United States
131 F. Supp. 329 (S.D. California, 1955)
Bultema Dock & Dredge Co. v. Thompson
252 F. Supp. 881 (W.D. Michigan, 1966)
Indiana State Employees Ass'n v. Negley
501 F.2d 1239 (Seventh Circuit, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
748 F.2d 395, Counsel Stack Legal Research, https://law.counselstack.com/opinion/no-84-1251-ca7-1984.