748 F.2d 395
UNITED STATES of America, Plaintiff-Appellee,
v.
PEAVEY BARGE LINE, in personam, and the M/V GREMCO, Barge PV
5985, Barge PV 5996, Barge PV 5978, Barge ABS 1448, Barge
UMC 2464, Barge PV 5903, Barge PV 2926, Barge PV 2923, and
Barge PV 5997, their appurtenances, etc., in rem,
Defendants-Appellants.
No. 84-1251.
United States Court of Appeals,
Seventh Circuit.
Argued Sept. 13, 1984.
Decided Nov. 8, 1984.
Daryl F. Sohn, Goldstein & Price, St. Louis, Mo., for defendants-appellants.
L. Lee Smith, Asst. U.S. Atty., Peoria, Ill., for plaintiff-appellee.
Before FLAUM, Circuit Judge, SWYGERT and FAIRCHILD, Senior Circuit Judges.
FLAUM, Circuit Judge.
This is an appeal of an admiralty case by the defendants following a bench trial which was limited to the issue of damages. The district court awarded the United States $425,373.24 for damages to a lock, dam, and bridge on the Mississippi River plus prejudgment interest at a rate of 11% from the date of the accident. For the reasons stated below, we affirm the decision of the district court.
I.
On July 15, 1978, the defendant Motor Vessel Gremco, operated by the Peavey Barge Line, was towing nine loaded barges near Rock Island, Illinois when one of the barges struck the guide wall of Lock and Dam No. 15, which are owned by the United States. This collision caused the remaining barges to become detached and collide with the lock's miter gates, the Rock Island Arsenal Bridge, and the roller gates of the dam. The Rock Island District of the United States Corps of Engineers began temporary repairs to the miter gates on July 31, 1978, and completed these repairs on April 27, 1979. The United States employed a private contractor for the guide wall repairs, which were completed on June 6, 1980. Repairs to the Rock Island Arsenal Bridge were completed in mid to late 1979 by a private contractor as part of a previously planned major bridge rehabilitation and renovation. At the trial in September 1983, the dam's roller gates had not yet been repaired, but the Corps of Engineers submitted an estimate of repair costs which went unchallenged by the defendant.
The United States filed suit against the defendant on June 30, 1981, claiming that it should recover for the damages it sustained to the lock and dam based on a theory of absolute liability under 33 U.S.C. Sec. 408 (1982) and to the bridge based on a negligence theory. Following a confession of liability by the defendant, the district court entered summary judgment for the United States on the issue of liability on December 28, 1982, and ordered a $1,000 pecuniary penalty against each of the defendant's barges pursuant to 33 U.S.C. Secs. 411 and 412. After a two-day trial at which the sole issue was the reasonableness of the damages claimed by the United States, the district court awarded the United States $425,373.24 plus prejudgment interest at a rate of 11% per annum from the date of the collision to the date of the judgment.
On appeal, the defendant claims that the district court's award of damages for such items as use of plant and equipment, use of shop and yards, motor vehicle usage, and labor on the guide wall was erroneous because these items lacked any evidentiary support. The defendant also challenges the award of overhead as being unrelated to the repair work caused by the collision and as being computed on items that constitute overhead themselves. Finally, the defendant disputes the grant of prejudgment interest from the date of the collision, if interest is granted at all, rather than from the date that the United States expended money to make the repairs. These issues will be addressed in turn below.
II.
A. Disputed Elements of Damages
In an admiralty case, as in a civil action under Rule 52(a) of the Federal Rules of Civil Procedure, the findings of fact of the district court may not be set aside unless clearly erroneous. McAllister v. United States, 348 U.S. 19, 20, 75 S.Ct. 6, 7-8, 99 L.Ed. 20 (1954); Feeder Line Towing Service, Inc. v. Toledo, Peoria & W. R.R. Co., 539 F.2d 1107, 1110 (7th Cir.1976). According to the Supreme Court, a finding is "clearly erroneous" when although there is evidence to support it, the appellate court on the entire evidence is left with the definite and firm conviction that a mistake has been committed. United States v. United States Gypsum Co., 333 U.S. 364, 395, 68 S.Ct. 525, 541, 92 L.Ed. 746 (1948). When reviewing for clear error in the district court's findings, the appellate court must be especially circumspect if there has been conflicting evidence on controverted issues of fact. Indiana State Employees Ass'n v. Negley, 501 F.2d 1239, 1241 (7th Cir.1974).
In this case, the defendant disputes the district court's award of $52,327.00 for use of plant and equipment on the miter gate repair project, $2,262.39 for use of shop and yards, $1,644.00 for motor vehicle usage, and $4,825.59 for the Army Corps of Engineers' labor on the guide wall repairs. The defendant claims that the Corps merely offered testimony identifying each item rather than proving that the charge was necessary and reasonable. The district court found that the charges for use of plant and equipment, use of shop and yards, and motor vehicle usage were items which bore a "reasonable relationship to the Corps' experience in equipment breakage and obsolescence." United States v. Peavey Barge Line, 590 F.Supp. 319 at 323-324 (C.D.Ill.1984) ("Memorandum Opinion"). The district court noted that certain amounts for items claimed by the United States could be determined by applying a fixed percentage to specific costs. Id. However, the court noted that the plaintiff has to prove that there exists a reasonable basis to apply that item to a particular repair claim. Id. Applying this test, the court disallowed the United States' claim of $38.41 for handling charges, $1,101.62 for per diem and transportation, $24.90 for reproduction services, and $922.56 for tool, furniture, and equipment replacement. Id.
The district court also found that the $4,825.59 for Corps labor related to the guide wall repairs was an appropriate charge. Id. at 324-325. The court held that this charge was supported by testimony that the figure was derived from time cards for the period that Corps laborers worked on the repairs. Id. The testimony revealed that services of such technical people as engineers were charged to the job as labor if they devoted more than an hour to the repairs. Id. at 325 n. 9.
Free access — add to your briefcase to read the full text and ask questions with AI
748 F.2d 395
UNITED STATES of America, Plaintiff-Appellee,
v.
PEAVEY BARGE LINE, in personam, and the M/V GREMCO, Barge PV
5985, Barge PV 5996, Barge PV 5978, Barge ABS 1448, Barge
UMC 2464, Barge PV 5903, Barge PV 2926, Barge PV 2923, and
Barge PV 5997, their appurtenances, etc., in rem,
Defendants-Appellants.
No. 84-1251.
United States Court of Appeals,
Seventh Circuit.
Argued Sept. 13, 1984.
Decided Nov. 8, 1984.
Daryl F. Sohn, Goldstein & Price, St. Louis, Mo., for defendants-appellants.
L. Lee Smith, Asst. U.S. Atty., Peoria, Ill., for plaintiff-appellee.
Before FLAUM, Circuit Judge, SWYGERT and FAIRCHILD, Senior Circuit Judges.
FLAUM, Circuit Judge.
This is an appeal of an admiralty case by the defendants following a bench trial which was limited to the issue of damages. The district court awarded the United States $425,373.24 for damages to a lock, dam, and bridge on the Mississippi River plus prejudgment interest at a rate of 11% from the date of the accident. For the reasons stated below, we affirm the decision of the district court.
I.
On July 15, 1978, the defendant Motor Vessel Gremco, operated by the Peavey Barge Line, was towing nine loaded barges near Rock Island, Illinois when one of the barges struck the guide wall of Lock and Dam No. 15, which are owned by the United States. This collision caused the remaining barges to become detached and collide with the lock's miter gates, the Rock Island Arsenal Bridge, and the roller gates of the dam. The Rock Island District of the United States Corps of Engineers began temporary repairs to the miter gates on July 31, 1978, and completed these repairs on April 27, 1979. The United States employed a private contractor for the guide wall repairs, which were completed on June 6, 1980. Repairs to the Rock Island Arsenal Bridge were completed in mid to late 1979 by a private contractor as part of a previously planned major bridge rehabilitation and renovation. At the trial in September 1983, the dam's roller gates had not yet been repaired, but the Corps of Engineers submitted an estimate of repair costs which went unchallenged by the defendant.
The United States filed suit against the defendant on June 30, 1981, claiming that it should recover for the damages it sustained to the lock and dam based on a theory of absolute liability under 33 U.S.C. Sec. 408 (1982) and to the bridge based on a negligence theory. Following a confession of liability by the defendant, the district court entered summary judgment for the United States on the issue of liability on December 28, 1982, and ordered a $1,000 pecuniary penalty against each of the defendant's barges pursuant to 33 U.S.C. Secs. 411 and 412. After a two-day trial at which the sole issue was the reasonableness of the damages claimed by the United States, the district court awarded the United States $425,373.24 plus prejudgment interest at a rate of 11% per annum from the date of the collision to the date of the judgment.
On appeal, the defendant claims that the district court's award of damages for such items as use of plant and equipment, use of shop and yards, motor vehicle usage, and labor on the guide wall was erroneous because these items lacked any evidentiary support. The defendant also challenges the award of overhead as being unrelated to the repair work caused by the collision and as being computed on items that constitute overhead themselves. Finally, the defendant disputes the grant of prejudgment interest from the date of the collision, if interest is granted at all, rather than from the date that the United States expended money to make the repairs. These issues will be addressed in turn below.
II.
A. Disputed Elements of Damages
In an admiralty case, as in a civil action under Rule 52(a) of the Federal Rules of Civil Procedure, the findings of fact of the district court may not be set aside unless clearly erroneous. McAllister v. United States, 348 U.S. 19, 20, 75 S.Ct. 6, 7-8, 99 L.Ed. 20 (1954); Feeder Line Towing Service, Inc. v. Toledo, Peoria & W. R.R. Co., 539 F.2d 1107, 1110 (7th Cir.1976). According to the Supreme Court, a finding is "clearly erroneous" when although there is evidence to support it, the appellate court on the entire evidence is left with the definite and firm conviction that a mistake has been committed. United States v. United States Gypsum Co., 333 U.S. 364, 395, 68 S.Ct. 525, 541, 92 L.Ed. 746 (1948). When reviewing for clear error in the district court's findings, the appellate court must be especially circumspect if there has been conflicting evidence on controverted issues of fact. Indiana State Employees Ass'n v. Negley, 501 F.2d 1239, 1241 (7th Cir.1974).
In this case, the defendant disputes the district court's award of $52,327.00 for use of plant and equipment on the miter gate repair project, $2,262.39 for use of shop and yards, $1,644.00 for motor vehicle usage, and $4,825.59 for the Army Corps of Engineers' labor on the guide wall repairs. The defendant claims that the Corps merely offered testimony identifying each item rather than proving that the charge was necessary and reasonable. The district court found that the charges for use of plant and equipment, use of shop and yards, and motor vehicle usage were items which bore a "reasonable relationship to the Corps' experience in equipment breakage and obsolescence." United States v. Peavey Barge Line, 590 F.Supp. 319 at 323-324 (C.D.Ill.1984) ("Memorandum Opinion"). The district court noted that certain amounts for items claimed by the United States could be determined by applying a fixed percentage to specific costs. Id. However, the court noted that the plaintiff has to prove that there exists a reasonable basis to apply that item to a particular repair claim. Id. Applying this test, the court disallowed the United States' claim of $38.41 for handling charges, $1,101.62 for per diem and transportation, $24.90 for reproduction services, and $922.56 for tool, furniture, and equipment replacement. Id.
The district court also found that the $4,825.59 for Corps labor related to the guide wall repairs was an appropriate charge. Id. at 324-325. The court held that this charge was supported by testimony that the figure was derived from time cards for the period that Corps laborers worked on the repairs. Id. The testimony revealed that services of such technical people as engineers were charged to the job as labor if they devoted more than an hour to the repairs. Id. at 325 n. 9. As with the miter gate repairs, the court refused to allow reimbursement for certain costs related to the guide wall repairs that were not supported by the evidence such as $68.16 for tool, furniture, and equipment replacement, $682.23 for reproduction services, and $422.63 for other facility charges. Id. at 325.
The extended and accurate analysis of the facts by the district court reveals that its ultimate holding was the product of a careful study of the evidence. Indiana State Employees Ass'n v. Negley, 501 F.2d at 1242. We hold that the district court's findings on these items of damages were not clearly erroneous.
B. Overhead
Overhead expenses include those expenses that are necessary to keep a company or organization functioning as a going concern and that cannot be easily identified with any individual product or repair project. See United Electrical, Radio and Mach. Workers v. Oliver Corp., 205 F.2d 376, 387 (8th Cir.1953). By its very definition, overhead serves to reimburse a party for its general operating expenses, which are composed of costs that are not directly allocable to a particular project. Furthermore, reasonable overhead charges can be included in the cost of repairs even if the injured party makes the repairs itself since such charges would be billed by any outside firm selected to complete the repairs. Freeport Sulphur Co. v. The S/S Hermosa, 526 F.2d 300, 304 (5th Cir.1976); Bultema Dock and Dredge Co. v. Steamship David P. Thompson, 252 F.Supp. 881, 885-86 (W.D.Mich.1966).
In admiralty cases, the courts have held that the grant or denial of damages rests within the discretion of the judge, who can base his decision upon principles of equity and justice. See, e.g., United States v. Motor Vessel Gopher State, 472 F.Supp. 556, 559 (E.D.Mo.1979), aff'd, 614 F.2d 1186 (8th Cir.1980). In Motor Vessel, the district court held that overhead charges should be reasonable in amount and factually related to the actual repair work performed. Id. at 559. The court noted that the overhead charges in that case were not based upon actual expenditures on items related to the accident, but were determined by the staff of the St. Louis Corps applying regulations promulgated by the Army Corps. Id. at 558.
In the present case, the district court noted that the claim for district overhead on various repair jobs was wholly consistent with business practice and was adequately shown to be realistically based upon the Corps' experience in its overall operations. Memorandum Opinion at 323-324. At trial, both an accountant in the Corps' Civil Works division and the head Finance and Accounting Officer for the Rock Island District Corps testified as to the method for determining district overhead rates. Tr. I at 120-21, 143-47. The head officer, Mr. Gillum, and an independent certified public accountant, Mr. Haney, testified that the overhead rate is developed by estimating the annual overhead costs and dividing that estimate by the overhead allocation base, which is the estimated annual district costs exclusive of district overhead and outside contractors' fees. Tr. I at 143-44, 171-72. The overhead rate was applied as a flat percentage against total costs of the particular repair project exclusive of overhead and outside contractors' fees until fiscal year 1980, when the rate was applied only against direct labor costs. Id. These rates are adjusted periodically, so that the overhead charged to the district's projects accurately reflects the total overhead actually incurred. Tr. I at 144. Using this formula to calculate the district overhead charge and adding to that amount the indirect labor costs, the district court awarded $38,564.76 in overhead charges out of a total judgment of $425,373.24.
We uphold the district court's award of overhead costs in this case. This award was necessary in order to compensate fully the Army Corps for its general operating expenses. In addition to explaining how the overhead rate was calculated and adjusted periodically, an independent certified public accountant testified at trial that the method of allocating overhead was adequate and proper. Tr. I at 176-77. The accountant did not find that the method of allocating overhead in this case resulted in any disproportional distribution of costs. Tr. I at 180.
The testimony concerning the reasonableness of the overhead rate distinguishes this case from United States v. Thomas Petroleum Transit, Inc., No. 78-2292-B, slip op. at 5 (S.D.Ill.1980), where the court held that the record was devoid of any evidence offered by the United States to show that the overhead charges were reasonable. The court in Thomas stated that the fact that the government's counsel thought that the overhead on repairs in a lock and dam collision was reasonable was of no significance and that overhead does not automatically become reasonable because it is authorized in the Corps' regulations. Id. at 5-6. Although the court in Thomas found that no evidence had been presented to show that the overhead rate was reasonable, it noted that its holding was a very limited one and made no determination about the use of overhead charges in other repairs. Id. at 6. We find, as did the district court, that the overhead costs assessed against the defendant were reasonable.
C. Prejudgment Interest
As was stated above, a reviewing court will not set aside the judgment of a district court sitting without a jury in an admiralty case unless the lower court's findings are clearly erroneous. McAllister v. United States, 348 U.S. at 20, 75 S.Ct. at 7-8; Feeder Line Towing v. Toledo, 539 F.2d at 1110. In admiralty cases, the district court has discretion to award prejudgment interest in order to compensate the injured party in full. United States v. Motor Vessel Gopher State, 614 F.2d 1186, 1190 (8th Cir.1980). The courts have observed that prejudgment interest in a sole fault collision case has always been allowed by maritime law unless exceptional circumstances render such an award inequitable, Bankers Trust Co. v. Bethlehem Steel Corp., 658 F.2d 103, 108 (3d Cir.1981), cert. denied, 456 U.S. 961, 102 S.Ct. 2038, 72 L.Ed.2d 485 (1982); Gulf Oil Corp. v. Panama Canal Co., 481 F.2d 561, 570 (5th Cir.1973). Peculiar circumstances that might prompt the district court to deny prejudgment interest include cases where the party requesting the prejudgment interest has unreasonably delayed prosecuting its claim, has made a bad faith estimate of its damages which precludes settlement or has not sustained any actual damages. Bankers Trust v. Bethlehem Steel, 658 F.2d at 108.
Although a district court can only deny prejudgment interest in cases involving extraordinary circumstances, a district court possesses broader discretion in determining when prejudgment interest should commence and what rate of interest to apply. Independent Bulk Transp., Inc. v. The Vessel "Morania Abaco", 676 F.2d 23, 25 (2d Cir.1982). The Seventh Circuit has held that the general rule in admiralty is to award prejudgment interest from the date of the collision, thereby compensating the plaintiff in full. Bunge Corp. v. American Commercial Barge Line Co., 630 F.2d 1236, 1242 (7th Cir.1980); Elgin, Joliet and E. Ry. Co. v. American Commercial Line, Inc., 317 F.Supp. 175, 177 (N.D.Ill.1970); United States v. The M/V Martin, 198 F.Supp. 171, 174, 177 (S.D.Ill.1961), aff'd, 313 F.2d 851 (7th Cir.1963). The district court in the present case awarded prejudgment interest at the rate of 11% per annum from July 15, 1978, the date of the collision. Memorandum Opinion at 327.
We affirm the district court's award of prejudgment interest from the date of the collision. Prejudgment interest, as part of the loss itself, is awarded to a victim who has incurred out-of-pocket cash expenses and/or a loss of use of its property. Gulf Oil v. Panama Canal, 481 F.2d at 571. In cases involving collisions between two vessels, the courts have held that prejudgment interest should not be awarded before the injured party pays for the repairs if damages include both demurrage costs and repair costs. Stevens v. F/V Bonnie Doon, 731 F.2d 1433, 1437-38 (9th Cir.1984); Independent Bulk v. "Morania Abaco", 676 F.2d at 25-26. The courts have reasoned that prejudgment interest on unspent money would be inappropriate when the injured party has recovered for loss of use or demurrage. Id. In the present case, the United States did not recover damages for loss of use, so prejudgment interest should be awarded from the date of the collision. In addition, the United States began incurring out-of-pocket cash expenses for the repair work immediately after the collision. By mid-1979, one year after the collision, the United States had spent $318,000 for repairs on the bridge and miter gates. By June 1980, the United States had expended over $410,000 for repairs. Appellee's Brief at 17-18.
In awarding prejudgment interest of 11% from the date of the collision, the district court specifically found that there were no peculiar circumstances prompting the exercise of its discretion to deny prejudgment interest on the United States' claim. Memorandum Opinion at 327. The defendant on appeal has argued that the district court should not have awarded prejudgment interest because the United States did not send a bill to the defendant for lock gate repairs until February 11, 1981, and did not institute this suit until June 30, 1981, almost three years after the collision. The courts have held that prejudgment interest can be denied only when delays in the resolution of a case are directly attributable to the party claiming the prejudgment interest. Bankers Trust v. Bethlehem Steel, 658 F.2d at 109. Thus, delays which are due to the size, complexity or need for extensive discovery in a case cannot be charged to the party claiming the prejudgment interest especially when the district court has expressly found no party responsible for such delays. Id. The district court in the present case granted a motion to enlarge the time for discovery due to the volume of documents regarding the United States' accounting procedures and the inherent difficulty in coordinating and compiling the documentation. Record at 9, 11. Furthermore, courts have held that a period of delay of one and a half to two years between the collision and the filing of the complaint is not so dilatory as to justify a denial of prejudgment interest when settlement negotiations have been ongoing. Mid-American Transp. Co. v. Cargo Carriers, Inc., 480 F.2d 1071, 1074 (8th Cir.1973); L & L Marine Service, Inc. v. Korf Transp. Corp., 514 F.Supp. 378, 384 (E.D.Mo.1981).
The United States began its temporary repairs and preparations for permanent repairs immediately following the collision and worked continuously on the miter gates regardless of the weather. Tr. I at 24, 29, 46-47, 59, 67-68. Peavey Barge Line was aware from the marine surveyors that it sent to the collision site that there had been a collision involving one of its vessels and the barges and that the United States had sustained damages. Plaintiff's Reply to Peavey Barge Line's Response on Motion for Summary Judgment, Attachment B, Record at 27. Peavey Barge Line only confessed liability for the damage caused by its vessel and barges on November 29, 1982, after the United States filed a motion for summary judgment on the issue of liability. After granting the United States' motion for summary judgment on the issue of liability, the court imposed sanctions against the defendant for its failure to admit that as a result of the collision, one or more of the defendant's barges damaged the dam, lock, and bridge. Record at 33. In view of the fact that the United States promptly began the repairs necessitated by the damage caused by the defendant and in light of the district court's specific finding that no peculiar circumstances existed to deny an award of prejudgment interest, this court affirms the district court's order to award prejudgment interest from the date of the collision even though the suit was instituted almost three years following the collision.
In conclusion, the district court's award of $425,373.24 for damages to the lock, dam, and bridge and of prejudgment interest from the date of the collision is affirmed.