United States v. Keith Churn

800 F.3d 768, 2015 FED App. 0224P, 98 Fed. R. Serv. 595, 2015 U.S. App. LEXIS 16074, 2015 WL 5255162
CourtCourt of Appeals for the Sixth Circuit
DecidedSeptember 10, 2015
Docket14-5720
StatusPublished
Cited by70 cases

This text of 800 F.3d 768 (United States v. Keith Churn) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Keith Churn, 800 F.3d 768, 2015 FED App. 0224P, 98 Fed. R. Serv. 595, 2015 U.S. App. LEXIS 16074, 2015 WL 5255162 (6th Cir. 2015).

Opinion

OPINION

COLE, Chief Judge.

In December 2013, defendant Keith Churn was found guilty of seven counts of bank fraud stemming from two schemes in which he received bank loans ostensibly to construct houses, but performed little to no work. The district court sentenced him to 33 months in prison and ordered restitution of $237,950.50. On appeal, Churn argues his conviction should be reversed and that he should receive a new trial because the district court purportedly made various evidentiary errors. He also requests vacatur of a portion of his restitution order, claiming the amount exceeds a statutory maximum, and vacatur of his sentence. Because the district court did not commit any reversible evidentiary errors, entered an appropriate restitution order, and properly sentenced Churn, we affirm the judgment of the district court.

I. BACKGROUND

A. Churn Proposes Two Projects.

Defendant Keith Churn owned C & M Construction Management, a Tennessee construction company specializing in remodeling and rehabilitation, since the late 1990s. Around October 2006, Churn entered a business agreement with Dustin Rief, under which Rief would purchase real property at 2408 Clarksville Pike, Nashville, Tennessee, and Churn would install a modular — or prefabricated — house on the property. Churn would pay Rief rent during the six-to-eight months of construction and would purchase the property from him upon completion. For his efforts, Rief would receive $5,000 initially and an additional $5,000 after Churn’s purchase, for a total of $10,000.

Rief financed the purchase and construction of the Clarksville Pike property with a $187,800 construction loan from BancorpSouth Bank (“BSB”). Under the terms of the loan agreement, a portion of the loan would be distributed upfront to purchase the property, and the remaining funds would be distributed in stages to pay for construction. BSB disbursed $66,758.19 for the purchase, leaving $121,041.81 for construction.

The same year, Churn proposed a similar investment to Milton Thomas.. Thomas agreed to obtain financing to purchase 956 Green Street, Franklin, Tennessee, and Churn agreed to demolish the existing house and install a modular home. The *772 two would split any profits. To finance the project, Thomas received a $226,500 loan from BSB, $77,976.83 of which was distributed to fund the property purchase.

BSB distributed the portion of the loan for construction in “draws.” For each draw, the bank would transfer money from the loan to Rief s and Thomas’s checking accounts, which they could then use to pay contractors. Before approving a draw, the bank might send an inspector to the property, or it might review contractors’ receipts, to ensure that the claimed work was actually being performed.

There were four draws made for the Clarksville Pike property: $25,000 on October 31, 2006; $15,000 on December 18, 2006; $30,000 on January 10, 2007, and $4,500 on January 12, 2007. On December 5, 2006, Churn submitted an invoice for $17,733 to BSB for permit fees, disconnecting old utilities, grading, and preparing footings and foundations. Based on the invoice, BSB approved a $15,000 draw on December 18.

On December 22, 2006, Churn submitted a specification sheet and an invoice to BSB, which purportedly showed an order for a modular house from All American Homes of N.C., LLC (“AAH”). The invoice charged a down payment of $33,462, or approximately one-third of the total cost of the modular house. Two weeks later, Churn informed a BSB loan officer, Lisa Campsey, that the house would be set on February 8, 2007. Campsey later approved draws of $30,000 and $4,500. During this period, a site inspector for BSB submitted periodic reports to BSB indicating that demolition of the existing structure had occurred and the lot was cleared.

There were four draws on the loan for the Green Street property: $20,000 on December 15, 2006; $8,000 on January 10, 2007; $12,000 on January 18, 2007; $22,000 on January 23, 2007; and $668.91 on February 1, 2007. On January 17, 2007, Churn submitted a specification sheet and an invoice to BSB, which purportedly showed an order for a modular house from AAH. Like the invoice for the Clarksville Pike property, the invoice charged a down payment of approximately one-third of the total cost of the modular house, or $33,638. Based on the invoice, BSB approved draws of $12,000 and $22,000.

B. Questions Arise About the Projects.

At some point, Campsey grew suspicious about the progress of the projects. For the Clarksville Pike property, although some demolition had been done, Campsey learned that the tasks listed on the December 5, 2006, invoice were not actually completed, including “pulling” the construction permit. Nor was the modular house set on February 8 as Churn said it would be. Similarly, she visited the Green Street property, but found no completed work.

An inspector dispatched by BSB made similar observations. On his first visit to the Clarksville Pike property in October 2006, he noted that the existing structure had been torn down and cleared. But a few months later, on March 23, 2007, the inspector estimated that only 1.2 percent of the construction project had been completed. He later found that no additional work was performed from then through July 17. The inspector also assessed the Green Street property on March 16 and determined that only 1.2 percent of the construction project had been completed; when he returned on July 17, he found that no work had been done since his March 16 visit.

Questions about Churn’s invoices arose as well. The invoices he submitted to BSB to support draw requests purportedly re- *773 fleeted purchases for two “Hot Tamale”style modular houses. But AAH never received any orders or payments from Churn. AAH also did not prepare the invoices Churn submitted to BSB. While the submitted invoices reflected a one-third deposit on the total purchases, as well as costs associated with installing electrical and plumbing “tie-ins,” AAH never required more than a 10-percent deposit — the industry standard. Indeed, AAH was not even able or licensed to provide electrical or plumbing services.

On March 3, 2007, Campsey emailed Churn, stating that an AAH representative told her that it had not received funds from Churn and would not start construction on modular homes until it received the money. She stated that Churn’s representations to BSB that he had paid deposits on the houses using the loans “greatly conflicts” with information given by AAH. Since Churn had previously said that he would pay for the purchases through checks, Campsey requested copies of can-celled checks and further information about what charges Churn had paid, but she never received any. She also pointed out to Churn that there was no pad (a part of the foundation) laid on the Green Street property even though Churn told her that it was already installed.

Two days later, Churn told Campsey that she would “have the information that’s needed by the end of the business day.” Churn also said that BSB’s inspector should “go by [the] site at [the] end of this week” and that Churn “will also have in writing this week [a] guarantee from [the] manuf[acturer] that we will have product this month on the sites.” (Id.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
800 F.3d 768, 2015 FED App. 0224P, 98 Fed. R. Serv. 595, 2015 U.S. App. LEXIS 16074, 2015 WL 5255162, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-keith-churn-ca6-2015.