United States v. Honeywell International, Inc.

226 F. Supp. 3d 962, 2016 WL 7478959, 2016 U.S. Dist. LEXIS 180021
CourtDistrict Court, D. Alaska
DecidedDecember 29, 2016
DocketCase No. 3:07-cv-00215-SLG
StatusPublished

This text of 226 F. Supp. 3d 962 (United States v. Honeywell International, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Alaska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Honeywell International, Inc., 226 F. Supp. 3d 962, 2016 WL 7478959, 2016 U.S. Dist. LEXIS 180021 (D. Alaska 2016).

Opinion

[965]*965ORDER RE CROSS MOTIONS FOR SUMMARY JUDGMENT

Sharon L. Gleason, UNITED STATES DISTRICT JUDGE

Before the Court are Defendants’ Motion for Summary Judgment at Docket 220 and Relators’ Motion for Partial Summary Judgment at Docket 225. The motions have been fully briefed; 1 oral argument was held on October 17, 2016.2

This is the third time the Court has addressed dispositive motions in this case. The Ninth Circuit has twice, sent this case back to the district court following orders granting motions to dismiss based solely on the allegations pled by Relators.3 In contrast to the prior motions to dismiss, the motions before the Court at this juncture are motions for summary judgment; the Court’s disposition of these motions is based on its review of the extensive submissions of the parties regarding these motions, which consists of thousands of pages of documentary evidence and excerpts from over a dozen depositions.

BACKGROUND

In the late 1990s the Army sought to privatize the utilities at U.S. Army installations.4 Simultaneously, but as a separate initiative, the Army endeavored to increase the energy efficiency of its buildings and facilities.5 In 1986, Congress authorized government agencies to enter into Energy Savings Performance Contracts (“ESPC”), whereby the agency could use the savings from an efficiency upgrade to pay for that upgrade.6 Pursuant to this law, a private contractor would install and maintain Energy Cost Savings Measures (“ECSM”), finance their installation, and receive compensation from the government for years into the future based on verified savings from the measures it had installed.7 By statute, payments to a contractor in a given year cannot exceed “the amount that the agency would have paid for utilities without an [ESPC] ” during that year.8 Federal law also requires that the contract “provide for a guarantee of savings to the agency.”9 It is these types of contracts that underlie this case.

As part of the privatization initiative, beginning in 1999 the Fort Richardson Army base in Anchorage, Alaska (“FRA”) contemplated shutting down its central heating and power plant (“CHPP”) and instead buying its electricity from a commercial provider.10 At around the same time, FRA reached out to Honeywell, Inc. to explore options for improving its buildings’ energy efficiency.11 Honeywell had previously entered a contract with the U.S. Army making it the contractor for ESPCs for an extendable five year term.12 Under [966]*966that “umbrella” Indefinite-Delivery Indefinite-Quantity contract (“IDIQ”), Honeywell could propose ESPCs that the government could accept by issuing a “Task Order” under the IDIQ.13 In 2000, Honeywell proposed two ESPCs—referred to as Proposal #3 and Proposal #4—to improve FRA’s energy efficiency.14 It developed these proposals with the understanding that FRA planned to cease generating its own electricity and would instead buy its electricity from a third-party provider.15 Honeywell’s proposals included estimates of the costs of installation, the current costs of electricity and heating for the base, and the projected costs of electricity and heating after the efficiency measures had been installed and the CHPP shuttered. Honeywell prepared detailed calculations setting out how it arrived at its estimates, which it shared with both FRA personnel and Army Corps of Engineers staff in Huntsville, Alabama.16

As the proposals were developed, there were extensive discussions between Honeywell’s engineers and the engineers at Huntsville about the basis, and reasonableness of certain calculations. Over time, these issues were resolved in multilateral meetings and exchanges. Honeywell submitted several revised drafts containing certain amended calculations during the course of these discussions.17 Ultimately, the Army accepted Honeywell’s proposals for FRA in late 2000; Proposal #3 became formalized as Task Order 8 and Proposal #4 became formalized as Task Order 9.18

Over the next few years, questions arose as to whether FRA could pay the contract amounts because its actual savings were less than projected.19 Because the statute authorizing ESPCs limits payments to actual savings, Army lawyers were concerned that making the payments would violate the Anti-Deficiency Act.20 Honeywell and the government renegotiated and combined the two task orders in 2003.21 Honeywell received its first payments thereafter, pursuant to the renegotiated contract.22 After unsuccessfully pursuing internal channels,23 Relators initiated this action in 2007, alleging that in 2000 Honeywell fraudulently obtained Task Orders 8 and 9. According to Relators, this initial fraud also induced the government to en[967]*967ter the 2003 modification and thus, Rela-tors allege, the government’s payments pursuant to that modification were fraudulently induced in violation of the FCA.24

DISCUSSION

I. Jurisdiction

The Court has jurisdiction pursuant to 28 U.S.C. § 1331 because Plaintiffs’ claims arise under the False Claims Act, 31 U.S.C. § 3729 et seq.

II. Standard for Summary Judgment

Federal Rule of Civil Procedure 56(a) directs a court to “grant summary judgment if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” The burden of showing the absence of a genuine dispute of material fact initially lies with the moving party.25 If the moving party meets this burden, the non-moving party must present specific factual evidence demonstrating the existence of a genuine issue of fact.26 The non-moving party may not rely on mere allegations or denials. Rather, that party must demonstrate that enough evidence supports the alleged factual dispute to require a finder of fact to make a determination at trial between the parties’ differing versions of the truth.27

When considering a motion for summary judgment, a court views the facts in the light most favorable to the non-moving party and draws “all justifiable inferences” in the non-moving party’s favor.28 When faced with cross-motions for summary judgment, the court “reviewfs] each separately, giving the non-movant for each motion the benefit of all reasonable inferences.”29 To reach the level of a genuine dispute, the evidence must be such “that a reasonable jury could return a verdict for the non-moving party.”30

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rex Trailer Co. v. United States
350 U.S. 148 (Supreme Court, 1956)
First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Adickes v. S. H. Kress & Co.
398 U.S. 144 (Supreme Court, 1970)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
United States Ex Rel. Burlbaw v. Orenduff
548 F.3d 931 (Tenth Circuit, 2008)
In Re Oracle Corp. Securities Litigation
627 F.3d 376 (Ninth Circuit, 2010)
Nyle Hooper v. Lockheed Martin Corporation
688 F.3d 1037 (Ninth Circuit, 2012)
Thomas Berg v. Honeywell International, Inc.
502 F. App'x 674 (Ninth Circuit, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
226 F. Supp. 3d 962, 2016 WL 7478959, 2016 U.S. Dist. LEXIS 180021, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-honeywell-international-inc-akd-2016.