United States v. Richard K. Ehrlich and Lurline Gardens Limited Dividend Housing Partnership

643 F.2d 634, 28 Cont. Cas. Fed. 81,354, 1981 U.S. App. LEXIS 13990
CourtCourt of Appeals for the Ninth Circuit
DecidedApril 23, 1981
Docket79-3304
StatusPublished
Cited by25 cases

This text of 643 F.2d 634 (United States v. Richard K. Ehrlich and Lurline Gardens Limited Dividend Housing Partnership) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Richard K. Ehrlich and Lurline Gardens Limited Dividend Housing Partnership, 643 F.2d 634, 28 Cont. Cas. Fed. 81,354, 1981 U.S. App. LEXIS 13990 (9th Cir. 1981).

Opinions

EUGENE A. WRIGHT, Circuit Judge:

I. FACTS

Section 236 of the National Housing Act, 12 U.S.C. § 1715z-l (1976), authorizes the Secretary of Housing and Urban Development to insure mortgages and subsidize interest payments on behalf of the sponsors of low income housing projects. This case involves a project sponsored by Lurline Gardens, a limited partnership. Richard Ehrlich was Lurline’s sole general partner, and was the general contractor for the project.

An insurable mortgage is limited, in a case such as this, to 90% of the replacement costs of the project. Replacement costs include construction costs.

The interest subsidy reduces the sponsor’s interest payments to one percent of the amount of the mortgage and the larger the mortgage, the larger the subsidy.

HUD initially estimates the construction and other costs of a project to determine the maximum insurable mortgage. Upon completion of the project, the sponsor must submit a statement of actual costs to HUD. If the costs are less than estimated, the insurable mortgage is reduced, and the sponsor must repay a portion of the principal to the mortgagee.

Interest subsidies are paid directly to the mortgagee who submits a monthly voucher to HUD. It lists all mortgages held by him for which HUD has agreed to provide interest subsidies, and certifies that none is in default.

[636]*636HUD, Lurline Gardens, and a mortgagee entered into an “Agreement and Certification” in August 1971. Ehrlich signed the agreement on behalf of the partnership. HUD agreed to insure the mortgage and provide interest subsidies. The partnership

agree[d] that if it receives from the Mortgagee monies in excess of that permitted under the National Housing Act and the Regulations promulgated pursuant thereto, it will pay upon demand forthwith to the Mortgagee any such excess for application to the reduction of the then outstanding principal balance of the mortgage.

The Agreement recites that, other than Ehrlich’s role as general contractor, there was no identity of interest between the partnership, the general contractor, and the subcontractors. The partnership agreed to notify HUD of any identity of interest that was created. In that event, the Agreement provided:

For purposes of determining actual cost no profit or general overhead may be included in the subcontract unless [HUD] has in advance granted approval in writing of the subcontract and has approved a specific dollar amount or a specific percentage for profit and/or general overhead.

In August, 1972, the partnership submitted a Mortgagor’s Certificate of Actual Cost, and a Contractor’s Certificate of Actual Cost, both prepared by Ehrlich. The certificates overstated construction costs so that the partnership' would not have to repay a portion of the principal. HUD was then insuring a larger mortgage and providing larger interest subsidies than were authorized under the Act.

Ehrlich also certified falsely- that there was no identity of interest with any subcontractor on the project. He was the sole owner of one subcontractor, Topaz Supply Corporation.

In 1975, Ehrlich pleaded guilty to two counts of an indictment, based on these events, charging him with submitting false statements to a government agency. He admitted knowingly and intentionally inflating the costs of construction.

In April, 1978, HUD demanded that the partnership pay the excess principal to the mortgagee pursuant to the Agreement. The partnership did not comply.

HUD then initiated this action and obtained a summary judgment. The district court ordered specific performance of the Agreement, directed the partnership to reduce the principal on the mortgage, and assessed 76 forfeitures and double damages under the False Claims Act, Rev.Stat. §§ 3490, 3494 & 5438.

We affirm.

II. SPECIFIC PERFORMANCE

The district court directed the partnership to reduce the principal by $227,700. Ehrlich argues that summary judgment was inappropriate because there is a dispute as to the actual cost of the project, which is used to calculate the amount of the reduction. He also argues that HUD lacks standing and its action is barred by a statute of limitations.

The district court relied on an affidavit by William Willits, a HUD official, which set forth in detail HUD’s calculation of the actual cost of the project.

In his brief, Ehrlich objects to two aspects of this calculation. First, no markup was allowed on materials purchased from Topaz Supply Corporation. At oral argument, however, his counsel conceded that Ehrlich’s failure to disclose his identity of interest and obtain advance approval of the markup permitted HUD, under the express terms of the Agreement, to exclude it from actual costs.

Second, Ehrlich claims that a group of items identified as “Other Costs” is understated. He submitted an affidavit alleging that when the mortgage was first issued, “Other Costs” were $70,000 more than the figure Willits used. He did not specify any items that were omitted or understated, but simply alleged he did not understand the calculation.

[637]*637This does not defeat a motion for summary judgment. An exhibit to Willits’ affidavit set forth the specific items included in “Other Costs.” Ehrlich did not seek a continuance or use discovery procedures for additional information regarding the calculation. “Conclusory allegations, unsupported by factual data, do not create a triable issue of fact.” California ex rel. Department of Transportation v. United States ex rel. Department of Transportation, Federal Highway Administration, 561 F.2d 731, 733 n.4 (9th Cir. 1977) (citations omitted).

We see no merit to the argument that HUD lacked standing to enforce the partnership’s obligation to reduce the principal. HUD was a party to the Agreement, and the provision requiring reduction of the mortgage was for its benefit.

Nor is there merit to the argument that relief was barred by the statute of limitations. Ehrlich claims 28 U.S.C. § 2415(b) (1976) is applicable. It imposes a three-year limit on tort actions. Here, the substance of the claim sounds in contract, and if any limitations period applies,1 it is six-years. 28 U.S.C. § 2415(a) (1976). See United States v. Limbs, 524 F.2d 799, 801 (9th Cir. 1975). The action was timely brought.

III. FALSE CLAIMS ACT

A person who “present[s] or cause[s] to be presented” a claim against the United States, “knowing such claim to be false, fictitious, or fraudulent,” is subject to civil liability under the False Claims Act. Rev. Stat. §§ 3490, 3494 & 5438. See United States v. Bornstein, 423 U.S. 303, 305 n.l, 96 S.Ct. 523, 526 n.l, 46 L.Ed.2d 514 (1976).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Honeywell International, Inc.
226 F. Supp. 3d 962 (D. Alaska, 2016)
State v. Abbott Laboratories
2012 WI 62 (Wisconsin Supreme Court, 2012)
Coleman v. Hernandez
490 F. Supp. 2d 278 (D. Connecticut, 2007)
United States Ex Rel. Roby v. Boeing Co.
79 F. Supp. 2d 877 (S.D. Ohio, 1999)
United States v. Midwest Specialties, Inc.
142 F.3d 296 (Sixth Circuit, 1998)
Marathon Oil Co. v. Babbitt
938 F. Supp. 575 (D. Alaska, 1996)
United States ex rel. Hopper v. Anton
91 F.3d 1261 (Ninth Circuit, 1996)
United States v. Hercules, Inc.
929 F. Supp. 1418 (D. Utah, 1996)
United States v. Incorporated Village of Island Park
888 F. Supp. 419 (E.D. New York, 1995)
Ab-Tech Construction, Inc. v. United States
39 Cont. Cas. Fed. 76,668 (Federal Claims, 1994)
X Corp. v. Doe
816 F. Supp. 1086 (E.D. Virginia, 1993)
United States v. Board of Educ. of City of Union City
697 F. Supp. 167 (D. New Jersey, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
643 F.2d 634, 28 Cont. Cas. Fed. 81,354, 1981 U.S. App. LEXIS 13990, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-richard-k-ehrlich-and-lurline-gardens-limited-dividend-ca9-1981.