United States v. City of Detroit

25 F. App'x 384
CourtCourt of Appeals for the Sixth Circuit
DecidedJanuary 11, 2002
DocketNo. 01-1277
StatusPublished

This text of 25 F. App'x 384 (United States v. City of Detroit) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. City of Detroit, 25 F. App'x 384 (6th Cir. 2002).

Opinions

OPINION

NORRIS, Circuit Judge.

The district court in this case issued an order under the All Writs Act, 28 U.S.C. § 1651(a), directing the United States Army Corps of Engineers (“Corps”) to accept dredged material in order to prevent the frustration of a consent judgment designed to address water pollution problems in and around Detroit. For the reasons that follow, we vacate the order of the district court.

I.

In 1977, the United States brought suit against the City of Detroit, the Detroit Water and Sewerage Department (hereinafter the city and department will be referred to jointly as “Detroit”), and the State of Michigan, alleging that the Detroit wastewater treatment system was operating in violation of the Clean Water Act, 33 U.S.C. §§ 1251-1387, and its National Pollutant Discharge Elimination System (“NPDES”) permit. That year, the parties signed a consent judgment setting a schedule to bring the treatment plant into compliance. Detroit’s failure to comply led to a party-negotiated amended consent judgment in 1981 which contained a revised compliance schedule.

The State revised the NPDES permit in July 1997, and the city fell out of compliance. In 1998, the State issued a notice of violation to Detroit, which then entered into negotiations for a proposed administrative consent order. In August 2000, Detroit and the State negotiated a Second Amended Consent Judgment, which was approved by the district court, to bring Detroit into compliance.1 This is the order at issue in the instant case. Among other things, the order required Detroit to dredge and dispose of 146,000 cubic yards of sediment from Conner Creek, a channel connected to the Detroit River. Discharges from Detroit’s sewage treatment plant had contaminated the creek. Under the agreement, this dredging was to be completed “as soon as possible,” and definitely before the completion of a Combined Sewer Overflow basin that Detroit was building in the vicinity. The sediment was to be disposed of “in accordance with state [386]*386and federal requirements.” The United States Environmental Protection Agency (“EPA”) refused to participate in the negotiation of the agreement, explaining that it had not been part of the administrative proceedings.

Detroit had been planning to dredge Conner Creek before the project was added as a requirement in the consent judgment. In 1998, it had asked the Corps if it could dispose of the sediment at the Confined Disposal Facility (“CDF”) at Pointe Mouillee, which is a wetlands area on the western shore of Lake Erie. Pointe Mouillee, operated by the Corps on bottomland owned by Michigan, includes a state game area and a 3.5-mile dike built to contain dredged material from the Detroit and Rouge Rivers. The Confined Disposal Facility, which has a capacity of 18,600,000 cubic yards, was constructed in 1981 under the authority of a statute on soil disposal facilities, 33 U.S.C. § 1293a.

The Corps at this point refused to accept the Conner Creek sediment, citing the elevated concentrations of lead and cadmium in the material. Detroit next explored the idea of dewatering the dredged sediment at the edge of the creek and then transporting the sediment to a landfill. Vigorous community opposition to the prospect of a malodorous dewatering along the creek led Detroit to table this plan. Detroit then returned to the Corps and suggested putting the sediment in a containment cell at the Pointe Mouillee facility; the cell would be covered with clean material to prevent contamination of the environment. The Corps expressed concern over the level of contaminants but agreed to work with Detroit and Michigan to find a solution. Negotiations ensued. The Corps requested and received Michigan’s approval for the use of Pointe Mouillee for the sediment. The Corps then required Michigan to obtain the approval of the United States EPA and the United States Fish and Wildlife Service and to agree to hold the federal government harmless from liability arising out of the Conner Creek disposal. The Corps also insisted upon an Environmental Assessment to determine whether the disposal would comply with National Environmental Policy Act of 1969 (“NEPA”), 42 U.S.C. § 4332 et. seq., requirements. The Corps also directed Detroit to obtain a dredging permit, a permit already required by the Rivers and Harbors Appropriation Act of 1899, 33 U.S.C. § 403. Michigan responded to the Corps’ demands by refusing to obtain the concurrence of either EPA or the Fish and Wildlife Service on the ground that these approvals would take too much time.

Combined Sewer Overflow Basin

In the meantime, Detroit agreed to undertake another project that became linked to the dredging — the construction of a thirty-million gallon settling basin at Conner Creek to contain the combined sewer overflow (“CSC”) from industrial and sanitary sewage and stormwater runoff. The basin was required by Detroit’s NPDES permit for its sewage treatment plan. Under the state-issued permit. Detroit was to begin construction of the basin by January 1, 2001, and to complete it by January 1, 2005. The high cost of the project prompted Detroit to apply to the State Revolving Loan Fund, which required a project description and environmental studies. When Detroit presented its basin project description, the State required that Detroit include in the proposal its plans for the Conner Creek dredging (even though the dredging is not being funded by the state revolving fund, and Detroit maintained that the two projects were separate). In other words, Detroit could not get funding for the basin unless it had secured a place to put its Conner Creek sludge. The city claimed that, if it [387]*387did the basin project without state funding, there would be an additional cost to ratepayers of $40,000,000. Thus the time pressure invoked by the State and Detroit in the instant motion to compel the Corps’ acceptance of the sediment stems from the state-issued NPDES permit requiring Detroit to commence building the basin by January 1, 2001.2

District Court Order

On October 12, 2000, Michigan and Detroit filed a motion seeking an order to show cause why the Corps should not be ordered to accept the Conner Creek sediment. The district court concluded that the Corps was frustrating the August 2000 consent judgment, and it issued an order that “[t]he ACE [Army Corps of Engineers] accept dredged materials from Conner Creek for disposal at the Pointe Mouillee Confined Disposal FacEty.” United States v. Michigan, 122 F.Supp.2d 785, 793 (E.D.Mich.2000). The court contmued by rejecting the Corps’ conditions on the acceptance of the sediment:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. New York Telephone Co.
434 U.S. 159 (Supreme Court, 1977)
United States v. Mitchell
463 U.S. 206 (Supreme Court, 1983)
Hercules, Inc. v. United States
516 U.S. 417 (Supreme Court, 1996)
Lane v. Pena
518 U.S. 187 (Supreme Court, 1996)
A.E. Finley & Associates, Inc. v. United States
898 F.2d 1165 (Sixth Circuit, 1990)
Township of Ridley v. Blanchette
421 F. Supp. 435 (E.D. Pennsylvania, 1976)
Traveler's Insurance Company v. United States
283 F. Supp. 14 (S.D. Texas, 1968)
United States v. Michigan
122 F. Supp. 2d 785 (E.D. Michigan, 2000)
Golden v. Kelsey-Hayes Co.
73 F.3d 648 (Sixth Circuit, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
25 F. App'x 384, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-city-of-detroit-ca6-2002.