OPINION
Justice FLAHERTY, for the Court.
What constitutes an “apparatus * * * for carrying or using electricity” under G.L.1956 § 5-6-2? The Board of Examiners of Electricians (the board), the director of the Rhode Island Department of Labor and Training (labor department), and the Superior Court all determined that a steel support structure, erected by Unistrut Corporation (Unistrut), which was intended to support lighting and other electrical equipment is such an apparatus, and, therefore the law required that it be built by licensed electricians. Unistrut disagreed, and petitioned this Court for a writ of certiorari. We granted that petition, and, for the reasons set forth in this opinion, we quash the judgment of the Superi- or Court.
I
Facts and Procedural History
When Rhode Island Hospital was building a new emergency room, the general
contractor on the project contracted with Capeo Steel to do much of the framing work. Capeo Steel, in turn, hired Unistrut to erect a steel support system upon which certain surgical equipment, including lighting, would be mounted. The record reveals that Unistrut had been using carpenters to install these systems in buildings, including hospitals for more than sixty years. This particular job, however, did not prove to be uneventful.
During construction, Ron Leddy, an office manager for Local 99 of the International Brotherhood of Electrical Workers, telephoned Glenn Dusablon, Chief Electrical Investigator for the labor department, to complain that Unistrut employees were performing electrical work without the proper license or permit. Dusablon’s investigation of the construction of the steel support structure led him to conclude that Leddy was correct, and so he issued notices of violation to four individuals at the job site, Scott Waage, the project manager, and Raymond Parent, Mark Watson and Dean Wheeler (collectively, petitioners), on September 30, 2004.
Undeterred, Unistrut continued the construction, despite the notices that the work was in violation of the law. Consequently, Dusablon issued two more violations to petitioners on October 1 and 6, 2004, which similarly failed to dissuade Unistrut from continuing the assembly of the support structure.
The next thrust in this conflict consisted of cease-and-desist orders issued by Kathryn G. Serrecchia, assistant director of the labor department. These orders sought not only to halt the construction of the steel support system, but also purported to levy fines for the violations of § 5-6-2, under § 5-6-32.
Cease-and-desist orders were issued to each of the petitioners on October 5, 7 and 8, 2004; the accompanying fines totaled $19,200.
Nonetheless, following the advice of counsel, Unistrut completed the construction of the steel support structure.
The petitioners did not take the actions against them lying down; they appealed both the fines and the cease-and-desist orders to the director of the labor department (the director). Pursuant to § 5-6-32,
a hearing was held before the board
on November 17, 2004. At that hearing, the board heard testimony from Dusablon, David Cenci, chief electrical inspector for the City of Providence, David Riley, a municipal electrical inspector who worked on the Rhode Island Hospital job, Scott Patchan, national sales manager for Unis-trut, and Scott Waage, the project manager.
The record of the hearing reveals that the purpose of the steel structure Unistrut built was to support lights and other electrical equipment in the emergency room, which equipment would be attached by E.W. Audet & Sons, Inc., an electrical contractor. Also, it seems clear from the record that at the time Unistrut completed its work no electrical components had been installed on the structure. Finally, the record of the hearing established that the electrical code requires that electricians provide adequate support for any electrical devices, fixtures, or appliances they install.
Based on this testimony, the board made the following findings: (1) that the structure that Unistrut built was an “apparatus * * * for carrying or using electricity” as described in § 5-6-2;
(2) that Unistrut was required to obtain an electrical permit to install the structure; and (3) that the workers who installed the structure were required to be licensed electricians. Consequently, the board recommended to the director that both the cease-and-desist orders and, the fines be enforced.
The director accepted the board’s recommendation and affirmed both the cease-and-desist orders and the fines for all four petitioners in separate decisions, all of which were issued on December 10, 2004.
Unistrut plodded on and perfected appeals of the administrative decisions to the Superior Court pursuant to G.L.1956 § 42-S5-15.
In the appeals, Unistrut
challenged the validity of the fines, arguing that petitioners did not receive a hearing before the monetary sanctions were levied, as is required by § 5-6-32.
Also, petitioners contended that the board erred when it determined that the installation of the steel support system was electrical work that required a license under the statute. In a written decision dated March 28, 2006, a magistrate of the Superior Court ruled that the fines were imper-missibly levied because Unistrut had not been afforded a hearing before they were assessed.
However, he agreed with the labor department’s conclusion that the steel support structure was an apparatus covered by § 5-6-2. Thus, he affirmed the issuance of the cease-and-desist orders.
Judgment was entered in accordance with that decision on April 3, 2006.
Still unwilling to accept defeat, Unistrut petitioned this Court for a writ of certiora-ri on April 13, 2006, challenging the portion of the magistrate’s judgment that affirmed the board’s construction of § 5-6-2 that included the steel support system built at Rhode Island Hospital within the definition of apparatus under the statute. This Court granted that petition on May 23, 2006. This ease originally was argued before this Court on December 4, 2006, pursuant to an order directing the parties to appear and show cause why the case should not summarily be decided. After argument, we held that cause had been shown, and we directed the parties to submit full briefs and prepare further argument. The case finally reached us for plenary consideration on April 3, 2007.
II
Standard of Review
Free access — add to your briefcase to read the full text and ask questions with AI
OPINION
Justice FLAHERTY, for the Court.
What constitutes an “apparatus * * * for carrying or using electricity” under G.L.1956 § 5-6-2? The Board of Examiners of Electricians (the board), the director of the Rhode Island Department of Labor and Training (labor department), and the Superior Court all determined that a steel support structure, erected by Unistrut Corporation (Unistrut), which was intended to support lighting and other electrical equipment is such an apparatus, and, therefore the law required that it be built by licensed electricians. Unistrut disagreed, and petitioned this Court for a writ of certiorari. We granted that petition, and, for the reasons set forth in this opinion, we quash the judgment of the Superi- or Court.
I
Facts and Procedural History
When Rhode Island Hospital was building a new emergency room, the general
contractor on the project contracted with Capeo Steel to do much of the framing work. Capeo Steel, in turn, hired Unistrut to erect a steel support system upon which certain surgical equipment, including lighting, would be mounted. The record reveals that Unistrut had been using carpenters to install these systems in buildings, including hospitals for more than sixty years. This particular job, however, did not prove to be uneventful.
During construction, Ron Leddy, an office manager for Local 99 of the International Brotherhood of Electrical Workers, telephoned Glenn Dusablon, Chief Electrical Investigator for the labor department, to complain that Unistrut employees were performing electrical work without the proper license or permit. Dusablon’s investigation of the construction of the steel support structure led him to conclude that Leddy was correct, and so he issued notices of violation to four individuals at the job site, Scott Waage, the project manager, and Raymond Parent, Mark Watson and Dean Wheeler (collectively, petitioners), on September 30, 2004.
Undeterred, Unistrut continued the construction, despite the notices that the work was in violation of the law. Consequently, Dusablon issued two more violations to petitioners on October 1 and 6, 2004, which similarly failed to dissuade Unistrut from continuing the assembly of the support structure.
The next thrust in this conflict consisted of cease-and-desist orders issued by Kathryn G. Serrecchia, assistant director of the labor department. These orders sought not only to halt the construction of the steel support system, but also purported to levy fines for the violations of § 5-6-2, under § 5-6-32.
Cease-and-desist orders were issued to each of the petitioners on October 5, 7 and 8, 2004; the accompanying fines totaled $19,200.
Nonetheless, following the advice of counsel, Unistrut completed the construction of the steel support structure.
The petitioners did not take the actions against them lying down; they appealed both the fines and the cease-and-desist orders to the director of the labor department (the director). Pursuant to § 5-6-32,
a hearing was held before the board
on November 17, 2004. At that hearing, the board heard testimony from Dusablon, David Cenci, chief electrical inspector for the City of Providence, David Riley, a municipal electrical inspector who worked on the Rhode Island Hospital job, Scott Patchan, national sales manager for Unis-trut, and Scott Waage, the project manager.
The record of the hearing reveals that the purpose of the steel structure Unistrut built was to support lights and other electrical equipment in the emergency room, which equipment would be attached by E.W. Audet & Sons, Inc., an electrical contractor. Also, it seems clear from the record that at the time Unistrut completed its work no electrical components had been installed on the structure. Finally, the record of the hearing established that the electrical code requires that electricians provide adequate support for any electrical devices, fixtures, or appliances they install.
Based on this testimony, the board made the following findings: (1) that the structure that Unistrut built was an “apparatus * * * for carrying or using electricity” as described in § 5-6-2;
(2) that Unistrut was required to obtain an electrical permit to install the structure; and (3) that the workers who installed the structure were required to be licensed electricians. Consequently, the board recommended to the director that both the cease-and-desist orders and, the fines be enforced.
The director accepted the board’s recommendation and affirmed both the cease-and-desist orders and the fines for all four petitioners in separate decisions, all of which were issued on December 10, 2004.
Unistrut plodded on and perfected appeals of the administrative decisions to the Superior Court pursuant to G.L.1956 § 42-S5-15.
In the appeals, Unistrut
challenged the validity of the fines, arguing that petitioners did not receive a hearing before the monetary sanctions were levied, as is required by § 5-6-32.
Also, petitioners contended that the board erred when it determined that the installation of the steel support system was electrical work that required a license under the statute. In a written decision dated March 28, 2006, a magistrate of the Superior Court ruled that the fines were imper-missibly levied because Unistrut had not been afforded a hearing before they were assessed.
However, he agreed with the labor department’s conclusion that the steel support structure was an apparatus covered by § 5-6-2. Thus, he affirmed the issuance of the cease-and-desist orders.
Judgment was entered in accordance with that decision on April 3, 2006.
Still unwilling to accept defeat, Unistrut petitioned this Court for a writ of certiora-ri on April 13, 2006, challenging the portion of the magistrate’s judgment that affirmed the board’s construction of § 5-6-2 that included the steel support system built at Rhode Island Hospital within the definition of apparatus under the statute. This Court granted that petition on May 23, 2006. This ease originally was argued before this Court on December 4, 2006, pursuant to an order directing the parties to appear and show cause why the case should not summarily be decided. After argument, we held that cause had been shown, and we directed the parties to submit full briefs and prepare further argument. The case finally reached us for plenary consideration on April 3, 2007.
II
Standard of Review
This Court is the final arbiter of questions of statutory construction, and such questions are subject to
de novo
review by this Court.
Marques v. Pawtucket Mutual Insurance Co.,
915 A.2d 745, 747 (R.I.2007). When a statute is clear and unambiguous we are bound to ascribe the plain and ordinary meaning of the words of the statute and our inquiry is at an end.
Moore v. Ballard,
914 A.2d 487, 490 (R.I.2007). However, when a statute is susceptible of more than one meaning,
we employ our well-established maxims of statutory construction in an effort to glean the intent of the Legislature.
Tanner v. Town Council of East Greenwich,
880 A.2d 784, 796 (R.I.2005). Furthermore, when the administration of a statute has been entrusted to a governmental agency, deference is due to that agency’s interpretation of an ambiguous statute unless such interpretation is clearly erroneous or unauthorized.
Arnold v. Rhode Island Department of Labor and Training Board of Review,
822 A.2d 164, 169 (R.I.2003). But, when a statute is clear and unambiguous, we are not required to give any deference to the agency’s reading of the statute.
“[A] case is moot if the original complaint raised a justiciable controversy, but events occurring after the filing have deprived the litigant of a continuing stake in the controversy.”
School Committee of Johnston v. Santilli,
912 A.2d 941, 942 (R.I.2007) (mem.) (quoting
In re New England Gas Co.,
842 A.2d 545, 553 (R.I.2004)). This Court will not entertain moot eases unless they concern important rights, and the controversy is capable of repetition and will evade review.
Krivitsky v. Town of Westerly,
823 A.2d 1144, 1146-47 (R.I.2003).
Ill
Analysis
We note at the outset, and although it was not briefed or argued by either side, that this controversy is clearly moot. The construction project that precipitated this conflict has been completed. Thus, the cease-and-desist orders issued in an effort to stop that construction are of no import. Furthermore, the fines assessed by the labor department were vacated by the Superior Court, and that action has not been challenged here. As a result, neither party has a current stake in the outcome.
See Santilli
912 A.2d at 942. Therefore, before we reach the merits of this case, we first must address whether this controversy concerns important rights that are capable of repetition while evading review.
See Krivitsky,
823 A.2d at 1146-47. What is before us involves the right of individuals to earn a livelihood, arises in a situation certainly capable of repetition, and is likely to evade review because of the short period in which construction of these support systems is completed. Consequently, it is our opinion that this case should be reviewed despite its mootness.
Cf. id.
at 1147 (finding the case not moot because the license at issue would not have expired by the time of oral argument). Accordingly, we now turn to the question of whether the magistrate made an error of law when he affirmed the board’s interpretation of § 5-6-2.
When the board reached its decision, it relied heavily on the requirement, found in the National Electric Code, that an electrician provide adequate support for anything he installs.
Also, because the word “apparatus” is not defined by the statute, the board adopted a dictionary definition of that term, and it determined that the structure built by petitioners fit into that definition. Thus, because § 5-6-2 requires a licensed electrician to install an apparatus for carrying electricity, and because electricians are required to adequately support their electrical work, the board reached the conclusion that § 5-6-2 requires anyone installing an apparatus
that supports electrical fixtures be a licensed electrician.
When the magistrate reviewed the decision in the Superior Court appeal, he also examined the meaning of the word “apparatus.” In doing so, he consulted several dictionary definitions as well as a Ninth Circuit case in which the court decided whether a softball field, basketball court, and skating rink were “apparatus[es] intended for the recreation of children.”
United States v. Migi,
329 F.3d 1085, 1087 (9th Cir.2003). In that case, the Ninth Circuit defined apparatus as “a collection or set of materials * * * [or] * * * appliances * * * designed for a particular use.”
Id.
at 1088 (quoting Webster’s Third New International Dictionary 102 (unabridged 1986)).
Based on these definitions of the disputed term, the magistrate affirmed the agency interpretation of § 5-6-2 to include the Unistrut support within the definition of apparatus for carrying electricity, the installation of which must be by a licensed electrician.
Two cases decided by this Court discuss the process that this Court uses when addressing a question of statutory interpretation in the face of an agency interpretation of the statute:
Labor Ready Northeast, Inc. v. McConaghy,
849 A.2d 340 (R.I.2004), and
Rossi v. Employees’ Retirement System,
895 A.2d 106 (R.I.2006).
McConaghy,
849 A.2d at 342, involved .a dispute about whether Labor Ready was operating a check cashing business, and, therefore, was required to obtain a license from the Department of Business Regulation (DBR). Labor Ready, which operated a day-laborer agency, gave its employees an option of receiving their pay in the form of a voucher in lieu of a check.
Id.
Employees would insert these vouchers into a cash-dispensing machine, and they would receive their pay in currency, less one dollar and any change contained on the voucher, which was retained by Labor Ready as a service fee.
Id.
The critical question was whether the vouchers issued by Labor Ready met the definition of the term “instrument” under the check-cashing statute.
Id.
at 345. The DBR, the agency charged with administering the statute, had determined that the vouchers fell within the definition, but the Superior Court reversed that determination on appeal.
Id.
at 343. In the course of our review, we determined that the term “instrument” was ambiguous and capable of more than one reasonable interpretation, and, as a result, the DBR’s interpretation was entitled to deference and, therefore, should not have been reversed by the Superior Court because it was not clearly erroneous.
Id.
at 345-46.
Rossi,
895 A.2d at 108, involved a plaintiff who applied for an accidental disability pension from the State of Rhode Island. She had suffered a job-related injury, and had been out of work for a period of years before returning to her job.
Id.
When she did, she found that the day-to-day activities of the job aggravated her previous injuries to the point that she was unable to continue working.
Id.
at 109. When the retirement board reviewed her application for a disability pension, it interpreted the statute to require that the application be made within five years of the injury, or
within three years of a specific incident that reaggravated the injury.
Id.
Because her original injury was more than five years old and because she could not point to a specific incident within the previous three years that gave rise to her renewed disability, the retirement board rejected her claim.
Id.
The Superior Court affirmed that decision.
Id.
On appeal, we held that the retirement board had interpreted the statute erroneously to require a specific incident of reaggravation, and, as such, had failed to interpret the term “aggravate” to mean something different from “reinjure.” We held that such an interpretation was clearly wrong because the statute used the terms “aggravate” and “rein-jure” each as triggering events for the application of the statute, and to interpret “aggravate” to have the same definition as “reinjure” would make the use of the two terms redundant.
Id.
at 118. Therefore, we held that the Legislature clearly and unambiguously intended to create two different circumstances that would trigger the three-year period for applying for a pension when a previous on-the-job injury returns to prevent an employee from working.
Id.
Therefore, we did not give deference to the agency’s interpretation, and we reversed the judgment of the Superior Court and remanded the case to the retirement board for reconsideration of her application.
Id.
at 113-14.
In the case now before us, both the board and the Superior Court have interpreted the word apparatus, and have determined that the Unistrut support structure is an apparatus under the statute. We disagree. This is not a case in which we are faced with a statute susceptible of multiple reasonable meanings, and therefore are required to give deference to the agency interpretation.
See McConaghy,
849 A.2d at 845-46. There is no dispute that the structure erected by Unis-trut was an apparatus. However, the question that must be resolved is whether the Unistrut structure was an “apparatus * * * for carrying or using electricity.” Neither the board nor the Superior Court addressed that issue. Instead, the board determined that the fact that the Unistrut structure was an apparatus intended to support electrical work, coupled with the requirement that electricians adequately support their installations resulted in the conclusion that this structure was an “apparatus * * * for carrying or using electricity” under § 5-6-2. “[T]he true measure of a court’s willingness to defer to an agency’s interpretation of a statute ‘depends, in the last analysis, on the persuasiveness of the interpretation, given all the attendant circumstances.’ ”
United States v. 29 Cartons of
* * *
an Article of Food,
987 F.2d 33, 38 (1st Cir.1993) (quoting
Massachusetts Department of Education v. United States Department of Education,
837 F.2d 536, 541 (1st Cir.1988)). In our opinion, because the administrative body interpreted the term apparatus out of context and only in its general sense, and not as an “apparatus for * * * carrying or using electricity,” the judgment of the Superior Court must be reversed.
See Rossi,
895 A.2d at 113-14.
Furthermore, our review of the statute leads us to conclude that the language of the statute is clear and unambiguous. In
Migi,
329 F.3d at 1088, the Ninth Circuit determined that the basketball court, softball field and skating rink were apparatuses intended for recreational use because the plain and ordinary meaning of apparatus was a set of materials and appliances for a specific use, and that specific use — recreational purposes — was defined by the statute. Here, apparatus has the same plain meaning, and once again, the specific use is defined by the statute— carrying or using electricity. Support for
electrical equipment is not included as one of the uses of an apparatus that requires an electrician for installation in § 5-6-2. The uncontradicted testimony before the board established that when Unistrut completed its work no electrical components were attached to the structure. Thus, we hold that the statute clearly and unambiguously does not include within its ambit the work done by the carpenters employed by Unistrut, and the cease-and-desist orders must be vacated.
IV
Conclusion
For the reasons stated in this opinion, we quash the judgment of the Superior Court and order the return of the papers in this case thereto.