Unified School District No. 490 v. Celotex Corp.

629 P.2d 196, 6 Kan. App. 2d 346, 1981 Kan. App. LEXIS 299
CourtCourt of Appeals of Kansas
DecidedMay 29, 1981
Docket51,030
StatusPublished
Cited by64 cases

This text of 629 P.2d 196 (Unified School District No. 490 v. Celotex Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Unified School District No. 490 v. Celotex Corp., 629 P.2d 196, 6 Kan. App. 2d 346, 1981 Kan. App. LEXIS 299 (kanctapp 1981).

Opinions

Abbott, J.:

This appeal is from a judgment entered in an action by Unified School District No. 490, Butler County, Kansas (USD 490), for both actual and punitive damages, claiming the defendant The Celotex Corporation (Celotex) sold and Sunflower Roofing and Industries, Inc. (Sunflower), had installed a two-ply, built-up roofing system on the El Dorado High School building. USD 490 claimed recovery for fraud and breach of warranty. The jury returned a verdict in favor of USD 490 in the amount of $100,000 compensatory damages and $600,000 punitive damages. The compensatory damages were apportioned between Celotex and Sunflower, attributing $98,000 to Celotex and $2,000 to Sunflower. All of the $600,000 punitive damages award was assessed against Celotex. On the cross-claim of Sunflower against Celotex on a theory of fraud, the jury awarded Sunflower actual damages of $15,000 and punitive damages of $28,000. Celotex appeals from the judgment, alleging numerous errors.

To understand the issues, it is necessary to give some background of the events that occurred prior to the planning of the new high school at El Dorado. Most of the background is found in the voluminous record (more than 2,000 pages, and in excess of 200 exhibits), and some was furnished at oral argument. Barrett [349]*349Roofing Company (Barrett) was an established and well-respected manufacturer of roofing materials. At some unspecified time prior to this controversy, Barrett was purchased by Allied Chemical Corporation (Allied) and became the Barrett Division of Allied Chemical Corporation. The Barrett Division of Allied was not a separate corporation. In the late 1950’s or early 1960’s, the Barrett Division of Allied developed a two-ply, built-up roofing system. Prior to that development, the most commonly used built-up roofing system incorporated four plies of felt saturated with asphalt, which were applied in alternating layers. Each ply was mopped with hot asphalt and covered by a flood coat of hot asphalt into which gravel was embedded. Such a roof normally could be expected to give 20 years or more of satisfactory service. Allied referred to its new two-ply system as the Bond Ply system. When Allied began marketing the Bond Ply system in 1964, it advertised the system extensively as 1 + 1 = 4; i.e., that the two plies of Bond Ply equaled the conventional four-ply roof. The two-ply system was considerably more profitable to Allied than the existing four-ply roof system. The record reflects evidence that at least some experts of Allied were skeptical of the two-ply system prior to 1964, and that considerable difficulty was encountered with installed two-ply roofs, particularly in climates that experienced severe winter weather.

A number of significant events took place in 1967. At some point during the year, prior to August 31, 1967, Allied sold the Barrett Division to Celotex, a subsidiary of The Jim Walter Corporation. The sale was made pursuant to an agreement that Celotex assume all liabilities which the Barrett Division had as to previous sales. Following its purchase, most of the employees of the Barrett Division of Allied continued in the employment of Celotex. On March 21, 1966, USD 490 had employed The Shaver Partnership (Shaver) to provide architectural and engineering services for a new high school. Shaver then contracted with Prigmore & Allen, architects, for a portion of those services. Shaver specified the two-ply system for use on the high school roof. John Shaver testified he relied on representations of Celotex’s roofing specialists that the two-ply system was equal to or greater in strength and durability than the four-ply system. On May 4, 1967, USD 490 entered into a contract with Coonrod, Walz & Vollmer Construction Company, Inc. (Coonrod), [350]*350whereby it agreed to construct the El Dorado High School building. Coonrod contracted with Sunflower to roof the high school building. The materials used in the roofing included adhesive, asphalt, insulation and roofing material manufactured and supplied by Celotex.

The high school was occupied by USD 490 in the fall of 1968, and leaks developed shortly thereafter. In 1970, the roofing material began to split. Considerable money and effort were expended in an attempt to correct the roofing problems, all without success. Experts were employed by the school district in May of 1975 to determine the cause of the roofing problems.

USD 490 commenced this action on September 9, 1976. Of the multitude of pleadings filed, the only filing dates material to this case relate to Sunflower’s cross-claim against Celotex. Sunflower filed an answer on October 13, 1976, to USD 490’s petition. The answer requested indemnity from Celotex if Sunflower should be determined to be liable to the school district. Sunflower next filed on May 19,1978, what is labeled a cross-claim against Celotex. As we read that pleading, it amounts to nothing more than a prayer for indemnity from Celotex. A pretrial order was filed on October 20, 1978, in which Sunflower alleged that Celotex engaged in a course of conduct designed to prevent Sunflower from receiving knowledge of defects in the roofing material. On January 5, 1979, seventeen days prior to trial, Sunflower filed a second amended cross-claim against Celotex for fraud and requested actual and punitive damages. Celotex answered, setting up the statute of limitations as a defense to the cross-claim. Further facts will be supplied as they become relevant to the discussion of the various issues raised on appeal. Celotex raises 26 separate issues, some of which are more than a single issue. We have consolidated a number of the issues, and those not specifically mentioned herein have been examined and found to be without merit.

Celotex argues that the claims of USD 490 and Sunflower are barred by the applicable statutes of limitation. The roof began leaking in 1968 almost simultaneously with occupancy of the building. A series of repairs began in 1969 and ran for almost ten years. Two separate statutes apply.

The statute of limitations applicable to a claim sounding in breach of warranty is found in K.S.A. 84-2-725, which provides:

“(1) An action for breach of any contract for sale must be commenced within four years after the cause of action has accrued. . . .
[351]*351“(2) A cause of action accrues when the breach occurs, regardless of the aggrieved party’s lack of knowledge of the breach. A breach of warranty occurs when tender of delivery is made, except that where a warranty explicitly extends to future performance of the goods and discovery of the breach must await the time of such performance the cause of action accrues when the breach is or should have been discovered.”

The statute of limitations for claims arising out of fraud is found in K.S.A. 60-513(a), and provides in pertinent part:

“The following actions shall be brought within two (2) years:
“(3) An action for relief on the ground of fraud, but the cause of action shall not be deemed to have accrued until the fraud is discovered.”

We conclude that the statute of limitations did not run against USD 490. Statutes of limitation do not run against the state when the action arises out of the performance of a governmental function. State ex rel. Schneider v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Owens-Corning Fiberglas Corp. v. Malone
972 S.W.2d 35 (Texas Supreme Court, 1998)
Scheufler v. General Host Corp.
915 F. Supp. 236 (D. Kansas, 1995)
Hamilton County Board of Education v. Asbestospray Corp.
909 S.W.2d 783 (Tennessee Supreme Court, 1995)
Gillespie v. Seymour
877 P.2d 409 (Supreme Court of Kansas, 1994)
City of Wichita v. United States Gypsum Co.
828 F. Supp. 851 (D. Kansas, 1993)
McCaffree Financial Corp. v. Nunnink
847 P.2d 1321 (Court of Appeals of Kansas, 1993)
Rowan County Board of Education v. United States Gypsum Co.
418 S.E.2d 648 (Supreme Court of North Carolina, 1992)
Grove v. Orkin Exterminating Co.
855 P.2d 968 (Court of Appeals of Kansas, 1992)
Westlands Water Dist. v. Amoco Chemical Co.
953 F.2d 1109 (Ninth Circuit, 1992)
Westlands Water District v. Amoco Chemical Co.
953 F.2d 1109 (Ninth Circuit, 1991)
Diversified Financial Planners, Inc. v. Maderak
811 P.2d 1237 (Supreme Court of Kansas, 1991)
Brunett v. Albrecht
810 P.2d 276 (Supreme Court of Kansas, 1991)
Laramie County School District No. One ex rel. Brown v. Muir
808 P.2d 797 (Wyoming Supreme Court, 1991)
LARAMIE COUNTY SCH. DIST. 1 v. Muir
808 P.2d 797 (Wyoming Supreme Court, 1991)
District of Columbia v. OWENS-CORNING FIBERGLAS CORPORATION
572 A.2d 394 (District of Columbia Court of Appeals, 1990)
Olson v. Walker
781 P.2d 1015 (Court of Appeals of Arizona, 1989)
Miller v. Cudahy Company
858 F.2d 1449 (Tenth Circuit, 1988)
Miller v. Cudahy Co.
858 F.2d 1449 (Tenth Circuit, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
629 P.2d 196, 6 Kan. App. 2d 346, 1981 Kan. App. LEXIS 299, Counsel Stack Legal Research, https://law.counselstack.com/opinion/unified-school-district-no-490-v-celotex-corp-kanctapp-1981.