Ultimate Concrete, LLC v. United States

Procedural entryThis page is a short order in Ultimate Concrete, LLC v. United States. Read the opinion of the Court — 127 Fed. Cl. 77
United States Court of Federal Claims·Decided March 26, 2019·No. 14-549·Unpublished

Opinion

In the United States Court of Federal Claims No. 14-549C (Filed: March 26, 2019)

) Keywords: Contract Disputes Act ULTIMATE CONCRETE, LLC, ) (“CDA”), 41 U.S.C. § 7104; Contract ) Interpretation; Motion for Plaintiff, ) Reconsideration; RCFC 59(a). ) v. ) ) THE UNITED STATES OF AMERICA, ) ) Defendant. ) ) ) )

Thomas M. Keranen, Clark Hill PLC, Detroit, Michigan, for Plaintiff, with whom was Jeffrey M. Gallant, Clark Hill PLC.

James W. Poirier, Trial Attorney, Commercial Litigation Branch, Civil Division, U.S. Department of Justice, Washington, D.C., for Defendant, with whom were Claudia Burke, Assistant Director, Robert E. Kirschman, Jr., Director, and Joseph H. Hunt, Assistant Attorney General.

OPINION AND ORDER

KAPLAN, Judge.

Plaintiff Ultimate Concrete, LLC (“UC”) has moved for reconsideration of the Court’s January 10, 2019 Opinion and Order (ECF No. 139), in which the Court granted-in-part and denied-in-part UC’s motion for summary judgment as to certain of its claims in this action brought pursuant to the Contract Disputes Act, 41 U.S.C. § 7104 (“CDA”). For the reasons discussed below, UC’s motion is DENIED.

BACKGROUND

The Court previously set forth the facts of this case in its January 10 opinion. See Ultimate Concrete, LLC v. United States, 141 Fed. Cl. 463, 466–473 (2019) (“Ultimate Concrete I”). It therefore presumes familiarity with the case and provides only a brief factual overview below. The Court will focus exclusively on UC’s “REA 7-8-9” claim, which is the sole claim at issue in UC’s motion for reconsideration.

This case concerns a contract dispute between UC and the United States Section of the International Boundary and Water Commission (“IBWC”). In 2010, UC and IBWC entered into a contract under which UC was to “rehabilitate, renovate, and perform new construction on an existing levee on the Rio Grande River.” Id. at 465–66. The disputed question at issue in this motion for reconsideration is whether an amendment to the solicitation allowed UC to leave in place preexisting clay material placed on the levee by IBWC in-house crews in 2009 (“the 2009 clay”).

It is undisputed that the original specifications and drawings required the contractor to excavate the 2009 clay. Id. at 476. About one week before bids were due, IBWC issued an amended solicitation. Id. at 468. Among other changes, having received several questions about the 2009 clay—including its quality and quantity—IBWC added language to the solicitation specifications stating, in pertinent part: “Approximately 232,300 tons of impervious material has been placed on the levee and may be suitable embankment at the contractor’s discretion.” Id. UC interpreted this sentence to mean that it had the option of leaving the 2009 clay in place on the levee. Id. at 468–69. Based on this assumption, UC significantly revised its price downward immediately before submitting its bid. Id. at 469.

UC won the contract because it submitted the lowest bid. Id. As contract performance progressed, however, it became clear that UC and IBWC disagreed as to whether UC was required to excavate the 2009 clay or could permissibly leave it in place. According to the government, the language stating that the subject clay material “may be suitable embankment at the contractor’s discretion” meant that the contractor had the option to reuse the clay material by placing it back on the levee in the process of rebuilding the structure after the required excavation. Therefore, IBWC ordered UC to excavate the clay despite UC’s protests. Id. at 469– 70. UC complied with IBWC’s instructions, tracking all costs for what it perceived to be out-of- scope work. Id. at 470. UC later submitted a certified claim to the contracting officer and ultimately filed the present lawsuit, requesting an equitable adjustment in the amount of $10,354,216.06. Id. at 472. UC labeled this claim its “REA 7-8-9 claim” because it concerned a request for equitable adjustment (“REA”) on Typical Sections 7, 8, and 9 of the levee as denoted on the solicitation drawings.

In Ultimate Concrete I, the Court considered the arguments of the parties in their respective motions for summary judgment and found UC’s interpretation of the contract unreasonable. Id. at 474–79. Conversely, the Court concluded that the government’s interpretation was reasonable as a matter of law. Id. Accordingly, the excavation of the 2009 clay fell within the scope of the contract and UC was not entitled to an equitable adjustment. The Court denied UC’s motion for summary judgment as to its REA 7-8-9 claim and granted the government’s motion on the same claim. Id. at 482.

UC has now moved for reconsideration of this part of the Court’s ruling. For the reasons set forth below, UC’s motion for reconsideration is denied.

DISCUSSION

I. Standard for Granting a Motion for Reconsideration

Under Rule 59(a) of the Rules of the Court of Federal Claims, the Court may grant a motion for reconsideration “(A) for any reason for which a new trial has heretofore been granted

2 in an action at law in federal court; (B) for any reason for which a rehearing has heretofore been granted in a suit in equity in federal court; or (C) upon the showing of satisfactory evidence, cumulative or otherwise, that any fraud, wrong, or injustice has been done to the United States.”

To meet this standard, a party generally must demonstrate that the court has committed a “manifest error of law[] or mistake of fact.” Johnson v. United States, 126 Fed. Cl. 558, 560 (2016) (quoting Bishop v. United States, 26 Cl. Ct. 281, 286 (1992)). “[O]rdinarily” the moving party “must show either that an intervening change in controlling law has occurred, evidence not previously available has become available, or that [granting] the motion is necessary to prevent manifest injustice.” CBS Corp. v. United States, 75 Fed. Cl. 498, 501 (2007) (quotation omitted); see also Johnson, 126 Fed. Cl. at 560. Whether to grant reconsideration lies within the sound discretion of the court. See Yuba Nat. Res., Inc. v. United States, 904 F.2d 1577, 1583 (Fed. Cir. 1990). Because the standard for reconsideration is a high one, the court should not grant the motion unless the party has made “a showing of extraordinary circumstances which justify relief.” Biery v. United States, 818 F.3d 704, 711 (Fed. Cir. 2016) (quoting Caldwell v. United States, 391 F.3d 1226, 1235 (Fed. Cir. 2004)), cert. denied, 137 S. Ct. 389 (Mem.) (2016).

II. UC’s Motion

In its motion for reconsideration, UC does not argue that there has been an intervening change in controlling law or that previously unavailable evidence has become available. Its motion is predicated on an argument that the Court committed an error of law when, rather than applying what UC calls the “reasonable bidder” or “reasonable contractor” standard, it required UC to demonstrate that its interpretation of the contract was “correct.” Quoting Renda Marine, Inc. v. United States, 66 Fed. Cl. 639, 652 (Fed. Cl. 2005), UC observes that “a contractor ‘does not bear the burden of interpreting [the] contract [documents] correctly, only of interpreting [them] reasonably.’” Pl.’s Mot. for Reconsideration (“Pl.’s Mot.”) at 3, ECF No. 142 (alterations in original). UC’s argument lacks merit.

Free access — add to your briefcase to read the full text and ask questions with AI

Ultimate Concrete, LLC v. United States, (uscfc 2019).

Ultimate Concrete, LLC v. United States (Ultimate Concrete, LLC v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Caldwell, Iii v. United States
391 F.3d 1226 (Federal Circuit, 2004)
Liebherr Crane Corporation v. The United States
810 F.2d 1153 (Federal Circuit, 1987)
McAbee Construction, Inc. v. United States
97 F.3d 1431 (Federal Circuit, 1996)
Coast Federal Bank, Fsb v. United States
323 F.3d 1035 (Federal Circuit, 2003)
Biery v. United States
818 F.3d 704 (Federal Circuit, 2016)
Johnson v. United States
126 Fed. Cl. 558 (Federal Claims, 2016)
Magnus Pacific Corporation v. United States
133 Fed. Cl. 640 (Federal Claims, 2017)
Renda Marine, Inc. v. United States
66 Fed. Cl. 639 (Federal Claims, 2005)
CBS Corp. v. United States
75 Fed. Cl. 498 (Federal Claims, 2007)
Prati v. United States
82 Fed. Cl. 373 (Federal Claims, 2008)
Bishop v. United States
26 Cl. Ct. 281 (Court of Claims, 1992)