Ultimate Concrete, LLC v. United States

127 Fed. Cl. 77, 2016 WL 3606079
CourtUnited States Court of Federal Claims
DecidedJune 30, 2016
Docket16-152C
StatusPublished
Cited by3 cases

This text of 127 Fed. Cl. 77 (Ultimate Concrete, LLC v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ultimate Concrete, LLC v. United States, 127 Fed. Cl. 77, 2016 WL 3606079 (uscfc 2016).

Opinion

Post-Award Bid Protest; Independent Government Estimate; Unbalanced Bid; Responsiveness; Modification of Bid; Anti-Deficiency Act; Advanced Payment

OPINION

BRUGGINK, Senior Judge

This is a post-award bid protest. Plaintiff, Ultimate Concrete, LLC (“Ultimate”) alleges that the decision of the United States Army Corps of Engineers, Fort Worth District (“Agency” or “Corps”) to enter into a contract with Fortis Networks, Inc. (“Fortis”) was arbitrary and capricious and in violation of procurement law. Before the court are cross motions for judgment on the administrative record. Oral argument was held on April 5, 2016. For the reasons set forth below, and as we announced at the conclusion of argument, the court grants defendant’s motion and denies plaintiffs motion.

BACKGROUND

A. Factual History

In August of 2015, the Corps issued a small business solicitation for sealed bids whereby the winning bidder would provide approximately 2.5 miles of fencing, various service roads and culverts, and associated work along the United States-Mexico border near Anapra, New Mexico. Administrative Record (“AR”) 105, 276. The bid schedule contained a total of eleven contract line item numbers (“CLINs”). CLIN 0001 was identified as the base item and called for the removal and replacement of approximately 3,850 linear feet of fence and the construction of an associated patrol road, a retaining wall, culverts, and vehicle/drainage gates. AR 219. The time period to complete CLIN 0001 was originally set at 180 calendar days but was amended to extend the performance period to 210 days. AR 712-713. CLIN 0004 was identified as “Option 1 Fence Replacement” and called for the removal and replacement of additional 3,100 linear feet of fence as well as the construction of a patrol road, culverts, and gates. AR 220. Performance time for this option was listed as 120 days. CLIN 0007 was listed as “Option 2 Eastern Access Road” and called for the construction of an access road approximately 890 feet in length. Id. Performance time for this option was listed as 45 days. Id. The remaining eight CLINs encompassed various minor aspects of the work, including the project staging area and bond premiums. AR 219-21.

Although the Corps intended awarding both option items and noted that option work was ideally to be finished concurrent with completion with the base item, the agency realized that option work may have to commence after work on the base item commenced. AR 220. Accordingly, the agency intended to issue an individual notice to proceed (“NTP”) for the base item and each option item. Id. Indeed, in response to a query by plaintiff asking for clarification on the performance periods, the Corps noted that the period of performance for each item “will begin when the contractor receives the notice to proceed for that item. They will probably run simultaneously, but could require extension ... based upon when they are exercised.” AR 737.

The solicitation noted that the award would be made to the responsible bidder with the lowest overall price — no factors other than price would be considered in making the award. AR 220. Further, the solicitation stated that the Corps was under no obligation to exercise any of the option items and while the government intended to award all option items, there was no guarantee when they would be awarded, if at all. Id.

*80 The Corps ultimately received five sealed bids, including those submitted by plaintiff and intervenor. On September 11, 2015, the Corps held a public bid opening at Fort Worth, Texas. AR 803. Fortis submitted the lowest bid with a price of $10,086,116.00, while Ultimate submitted the second lowest bid at $10,393,119.00. Id. Both bids were lower than the independent government estimate (“IGE”) of $10,879,721.00. The following chart shows the breakdown of the major CLINs for both Fortis’ and Ultimate’s bid, along with the IGE:

[[Image here]]

Plaintiffs Motion for Judgment on the Administrative Record (“PMJAR”) at 8. As this chart illustrates, Fortis’ bid placed a far greater value in the optional item CLIN 0007. On September 14, 2015, the Corps requested by email that Fortis verify its bid price due to the imbalance in CLIN values. AR 808. The next day, Fortis replied “we have reviewed our submission and are confident we can [perjform for the stated price” and that “[w]e can fully complete all CLINs for our proposed price.” AR 821. Fortis noted that the imbalance was due to its calculation method — it had calculated a total price for the project work and placed all road work due to be completed under all CLINs into CLIN 0007. Id.

In response to Fortis’ verification, the Corps again contacted Fortis to explain that “[although we plan on awarding CLIN 0007 Option 2 ... at the time of contract award, notice to proceed (NTP) could be delayed as the Government must go complete condemnation procedures prior to issuing the NTP.” AR 819. Accordingly, the Corps cautioned Fortis that if the government was unable to acquire title to the land, there was a chance that CLIN 0007 would have to be terminated for convenience and that in such a situation, Fortis would not be able to bill for the amount it assigned to that item. AR 819-20. The Corps also informed Fortis that “[y]our bid cannot be altered, however you can withdraw your bid. If you do not withdraw your bid and we award the contract to you, you cannot bill for any of CLIN 0007 until after NTP has been issued for that CLIN and a percentage of that work has been completed and agreed upon by the Government as complete.” Id. .

Upon receiving this communication, Fortis conferred with its counsel and replied to the Corps, requesting that it be allowed to amend its bid in order to redistribute the CLIN numbers to be more balanced. AR 815-816. Between September 15 and September 24, 2016, Fortis submitted various materials to the Corps to support its assertion of a mistake-in-bid. FAR § 14.407-3 provides that if a bidder requests permission to correct a mistake, the agency may permit it to do so only if the bidder provides clear and convincing evidence establishing both the existence of the mistake and the bid actually intended. During that time period, the Corp drafted a memo to the Principal Assistant Responsible for Contracting (“PARC”) which analyzed both Fortis’ original bid and its assertion of a mistake-in-bid. AR 903-905. *81 With regard to the original bid, the Corps concluded that although the bid was mathematically imbalanced when compared to the IGE, it was not materially unbalanced such that it posed an unacceptable risk to the government that it would pay unreasonably high prices for the contract work. Id. Thus, the Corps concluded that rejection of the bid was unwarranted. Id. With regard to the mistake-in-bid, the Corps concluded that Fortis had demonstrated by clear and convincing evidence the existence of a mistake in the original bid with respect to cost allocation, and recommended that the PARC approve the request of bid correction. AR 904-905. On September' 25, 2015, the PARC confirmed that Fortis should be allowed to correct its original bid. AR 1411-12.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
127 Fed. Cl. 77, 2016 WL 3606079, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ultimate-concrete-llc-v-united-states-uscfc-2016.