Uganski v. Little Giant Crane & Shovel, Inc.

192 N.W.2d 580, 35 Mich. App. 88, 10 U.C.C. Rep. Serv. (West) 57, 1971 Mich. App. LEXIS 1416
CourtMichigan Court of Appeals
DecidedJuly 23, 1971
DocketDocket 8604
StatusPublished
Cited by19 cases

This text of 192 N.W.2d 580 (Uganski v. Little Giant Crane & Shovel, Inc.) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Uganski v. Little Giant Crane & Shovel, Inc., 192 N.W.2d 580, 35 Mich. App. 88, 10 U.C.C. Rep. Serv. (West) 57, 1971 Mich. App. LEXIS 1416 (Mich. Ct. App. 1971).

Opinion

Holbrook, P. J.

This action was brought for claimed damages suffered by plaintiff John Uganski, purchaser, against defendant-appellant Little Giant Crane & Shovel, Inc., manufacturer of the crane in question, and Great Lakes Equipment Company, local dealer who handled the sale of the crane to plaintiff. The action was based on express and implied warranties. The matter was heard in the Circuit Court for Muskegon County in a five-day trial that commenced April 29, 1969. The trial judge, the Honorable Albert J. Engel, wrote a very thorough 32-page opinion finding for plaintiff and against Little Giant only, in the sum of $37,863. Shortly thereafter, both plaintiff and Little Giant moved for new trials or modification of the judgment. After a full hearing, the trial court modified its former judgment, reducing the damages to $33,345.49.

The undisputed facts, are well stated in the trial court’s opinions, and we summarize them. Plaintiff was in the business of reclaiming, handling, and hauling scrap metal for several firms in and near Muskegon, Michigan. He also served customers by loading, unloading, and hauling tubing and pipe. Plaintiff owned a 1956 Lorain self-propelled 4x6 crane and a 1951 Unit self-propelled 4x4 crane. The first numeral indicates the number of power-driven wheels, and the second numeral indicates the total number of wheels on the crane. In early 1965, plaintiff desired to purchase another Lorain crane identical to the one he owned. He requested that *93 Great Lakes Equipment Company order it for him. They informed him this model was discontinued but they could get him a truck crane 1 within 6 to 8-1/2 months.

Subsequently, Mr. Hartman, representative of Great Lakes, and Mr. Williams, representative of Little Giant, met with plaintiff concerning purchase of a crane. Plaintiff explained he wanted a self-propelled 4x6 crane like his Lorain, but narrower so it could be driven over the highway, and also he would like the boom to be five feet longer and still do the work that he was doing with his Lorain. Mr. Williams observed plaintiff’s operations and talked with the operator of plaintiff’s Lorain. Mr. Williams first tried selling plaintiff their regular 4x4 model, but plaintiff would not have it. Mr. Williams returned to his headquarters and later contacted plaintiff and informed him they would manufacture a 4 x 6 crane as desired in about 30 to 45 days. Mr. Williams said it would be as operative and do the same work that the Lorain was doing — as well or better. The plaintiff entered into a purchase agreement with Little Giant for the crane described including a 54-inch magnet for $43,805. It was delivered to plaintiff on or about July 1, 1965, and a man from Little Giant accompanied the crane at the time of delivery. Donald Schmiedeknecht, plaintiff’s operator, drove the crane to Lakey’s Foundry. A great deal of noise was encountered in the motor and in the clutches; otherwise, it worked well until the next day when the operator had trouble getting it over some soft sand. Finally it was necessary to have it pushed by a bulldozer. To correct this defect, another gear was installed. It was unlike the Lorain in that it *94 was necessary for the operator to get out of the cab and onto the ground in order to shift it into the new gear. The noise in the motor remained and although softer linings were installed in two of the clutches in 1966, the screeching continued. A six-foot muffler was also installed but without significant lessening of noise. The Little Giant crane was only powered up and not down, whereas the Lorain had power both ways. This situation impeded all close work with the crane. Two additional sheaves were installed in the rigging to give greater control but even this failed to bring the control to the degree obtained in the Lorain. Safety glass was substituted for ordinary glass in the cab and a better operator’s seat was also installed. The stability of the Little Giant was not as good as the Lorain’s but, of course, the boom was five feet longer and the Little Giant was narrower. The facts concerning the basis for the revocation of acceptance by plaintiff are well stated by the trial judge in his written opinion, vis.:

“The remainder of the proofs in the case, aside from the issue of damages, devolves upon the mechanical operation of the power train of the Little Giant crane. The difficulties actually encountered are largely undisputed although the parties draw sharply differing conclusions as to the cause and seriousness of them. In general, the plaintiff has claimed that the successive failures of the power train from time to time were brought about by instability in the mounting of it within the unit and that taken as a whole, they are indicative of what was finally concluded by plaintiff to be a substantial defect in design which could not ever satisfactorily be resolved and which thus finally triggered the decision to revoke acceptance. On the other hand, the defendant Little Giant in general characterizes the series of difficulties as independent and *95 isolated problems, each capable of correction in an otherwise completely acceptable piece of equipment. It was also inferred, at least by Little Giant, that much of the difficulty was due to improper maintenance and abuse of the machine by plaintiff’s operator and maintenance man. However, none of the defendant’s witnesses was able to point out in what way any claim of poor maintenance affected the particular breakdown. With respect to the final breakdown, however, there was at least an inference that if the breakdown was caused by a brake lock or having the tires stuck in ice, the same ought to have been avoided by a careful operator. More of that later.

“In September of 1965, the Little Giant Crane developed gear trouble in the vertical drive assembly. It was necessary to tow the crane back to Great Lakes for repairs which took approximately three weeks. Jack Heglin, Little Giant’s serviceman, came to Muskegon from Iowa and the work which he performed on October 4, 5, 7, and 8 is outlined in Little Giant’s exhibit 11. In short, it was found at that time that two gears at the top of the vertical drive shaft had failed to mesh and were thus chipped and broken. A further check also revealed that the lower bevel gears were also broken and chipped although both upper and lower pinion gears were undamaged. By this time, there had been a number of complaints by plaintiff’s operator and by Little Giant service people that the verdical drive shaft assembly was ‘wallowing’, which the court understands is a particular form of vibration and movement. Mr. Sehmiedeknecht had already complained that it was necessary to tighten the bolts on the assembly daily and in his inspection of the assembly on October 7, 1965, serviceman Heglin reported to his company that the pinion shaft had quite a bit of end play, that the nuts on both ends were loose, and that the bearing end was ‘real loose’. These he tightened up in addi *96 tion to the other repairs set forth in Little Giant exhibit 11. On the first day back after these repairs, Uganski’s operator commenced to use it, but had only moved the machinery about two feet when the same difficulty immediately developed. Great Lakes brought out a wrecker or winch truck and had the crane once more brought in.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Transport Systems LLC v. United Roadlink LLC
Michigan Court of Appeals, 2025
Cuesta v. Classic Wheels, Inc.
818 A.2d 448 (New Jersey Superior Court App Division, 2003)
Heidtman Steel Products, Inc. v. Compuware Corp.
178 F. Supp. 2d 869 (N.D. Ohio, 2001)
Aluminum Line Products Co. v. Rolls-Royce Motors, Inc.
649 N.E.2d 887 (Ohio Court of Appeals, 1994)
Sullivan Industries, Inc. v. Double Seal Glass Co.
480 N.W.2d 623 (Michigan Court of Appeals, 1991)
Evans v. Cheek
584 N.E.2d 1236 (Ohio Court of Appeals, 1989)
City Nat. Bank of Charleston v. Wells
384 S.E.2d 374 (West Virginia Supreme Court, 1989)
Island Creek Coal Co. v. Lake Shore, Inc.
636 F. Supp. 285 (W.D. Virginia, 1986)
Warren v. Guttanit, Inc.
317 S.E.2d 5 (Court of Appeals of North Carolina, 1984)
McCullough v. Bill Swad Chrysler-Plymouth, Inc.
449 N.E.2d 1289 (Ohio Supreme Court, 1983)
Fabbrini Family Foods, Inc. v. United Canning Corp.
280 N.W.2d 877 (Michigan Court of Appeals, 1979)
Pavesi v. Ford Motor Company
382 A.2d 954 (New Jersey Superior Court App Division, 1978)
Drier v. Perfection, Inc.
259 N.W.2d 496 (South Dakota Supreme Court, 1977)
McMillan v. Meuser Material & Equipment Co.
541 S.W.2d 911 (Supreme Court of Arkansas, 1976)
Material Distributors, Inc. v. Acme Cabinet Corp.
70 Pa. D. & C.2d 203 (Philadelphia County Court of Common Pleas, 1975)
Vogue v. Shopping Centers, Inc.
228 N.W.2d 403 (Michigan Court of Appeals, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
192 N.W.2d 580, 35 Mich. App. 88, 10 U.C.C. Rep. Serv. (West) 57, 1971 Mich. App. LEXIS 1416, Counsel Stack Legal Research, https://law.counselstack.com/opinion/uganski-v-little-giant-crane-shovel-inc-michctapp-1971.