Trinity River Lumber Co. v. United States

66 Fed. Cl. 98, 2005 U.S. Claims LEXIS 168, 2005 WL 1459442
CourtUnited States Court of Federal Claims
DecidedJune 20, 2005
DocketNos. 02-943C, 02-944C
StatusPublished
Cited by6 cases

This text of 66 Fed. Cl. 98 (Trinity River Lumber Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trinity River Lumber Co. v. United States, 66 Fed. Cl. 98, 2005 U.S. Claims LEXIS 168, 2005 WL 1459442 (uscfc 2005).

Opinion

OPINION

BRUGGINK, Senior Judge.

This is an action for breach of contract. Plaintiffs, Trinity River Lumber Co. (“Trinity”) and Hagen & Sons (“Hagen”), allege that the United States Forest Service (“Forest Service”) breached contracts for the sale of timber. Pending are the parties’ cross-motions for summary judgment pursuant to Rule 56 of the Rules of the United States Court of Federal Claims (“RCFC”).

Plaintiffs’ motion addresses Counts I, II, and IV of the amended complaint.1 Count I alleges that the Forest Service breached the timber sale contracts by failing to permit plaintiffs to cut and remove all catastrophe-affected timber meeting utilization standards in their sale areas that could have been har[100]*100vested consistent with environmental standards. Count II alleges that the Forest Service’s failure to comply with the National Environmental Policy Act (“NEPA”), 42 U.S.C. §§ 4321-4370 (2000), and the National Forest Management Act (“NFMA”), 16 U.S.C. §§ 1600-1640 (2000), breached the implied contractual duties to cooperate and not to hinder performance. In Count TV, plaintiffs claim that defendant should pay plaintiffs for the lost value resulting from the deterioration of the catastrophically-affected timber.

Defendant cross moves as to the same counts. It asks the court to find that the Forest Service modified the contracts in a timely and appropriate manner; that following modification, the Forest Service properly suspended the contracts; and that plaintiffs are not entitled to compensation for unharvested deteriorated timber.

The ease was transferred to the undersigned on December 15, 2004. Oral argument was held on March 11, 2005. Following oral argument, the court requested that the parties file supplemental briefs. For the following reasons, we grant defendant’s cross-motion as to Count IV, as well as a portion of its motion with respect to Count I. The parties’ cross-motions are denied in all other respects.

BACKGROUND

Severe winter storms in 1995 and 1996 caused extensive tree damage to approximately 30,000 acres of Six Rivers National Forest (“Six Rivers”). This resulted in a large number of dead and dying trees and a greatly increased risk of fire. In 1997, the Forest Service developed a project to reduce the risk of fire by eliminating damaged, dead, or dying trees. To implement the project, the Forest Service entered into contracts for the sale of timber within certain areas of Six Rivers.

On July 30, 1998, the Forest Service awarded plaintiff Hagen contract No. 056716 for harvesting timber in a 306-acre area known as Griz. Hagen agreed to pay $133,500. The termination date was March 31, 1999. On August 4, 1998, the Forest Service awarded plaintiff Trinity contract No. 056724 for harvesting in a 204 acre area known as West Lone Pine (‘WLP”). Trinity agreed to pay $158,044. That contract had a termination date of March 31, 2000. The prices listed in the contracts were based on the estimated volume of timber in each area. Actual payments would be based on the volume removed. The contracts did not cover all of the timber within the Griz and West Lone Pine sale areas. Each sale area contained interspersed “harvest units.” Within those harvest units, certain timber was designated for cutting. Only this “designated timber” could be removed.

Plaintiffs started harvesting and removed most of the designated timber. But in the late summer and early fall of 1999, before they could finish, a wildfire, now known as the Megram Fire, burned over 120,000 acres of the Six Rivers and Shasta-Trinity National Forests in California. The Megram Fire burned through Griz and WLP on approximately September 28, 1999, causing extensive damage. Shortly after the Megram Fire, the Forest Service suspended operations on the sale to assess the fire’s impact.2 The parties agree that the Megram Fire caused catastrophic damage to both the Griz and WLP sale areas within the meaning of clause B2.133 (“Damaged by Catastrophe”) of the contracts.

Among the Forest Service’s responses was the establishment of two assessment teams: one team to perform an environmental analysis to remove hazard trees along the roads accessing burned areas (“roadside hazard trees”); another team to assess the effect of the Megram Fire upon the WLP and Griz sale areas.

In April 2001, following an environmental analysis and pursuant to clause B8.33 (“Modification for Catastrophe”), the parties modified the contracts so that plaintiffs could remove identified roadside hazard trees. They were removed from the WLP sale area by June 8, 2001, and from the Griz sale area by September 12, 2001.

[101]*101As to other timber, the Forest Service announced to the public in October 2000 that it intended to prepare an Environmental Impact Statement (“EIS”) for Phase I of the “Fuels Reduction for Community Protection” project (“Phase I”). Phase I would encompass most of the WLP and Griz sale areas, as well as a much larger area. The purpose would be to identify burned timber for salvage logging with the ultimate goal of protecting communities from wildfires. The Forest Service issued the EIS in June 2001, and the record of decision was signed on July 9, 2001. The same day the record of decision was signed, plaintiffs’ contracts were modified again. The modifications added to the contracts a portion of the burned timber within the sale areas. Plaintiffs began operations to remove the additional timber immediately.

Also on July 9, 2001, the Sierra Club and other environmental groups filed an administrative appeal with the Forest Service contesting the sufficiency of the EIS. Administrative appeals typically trigger automatic administrative stays of harvesting operations. This did not stop plaintiffs’ harvesting operations, however, because the Forest Service had issued, prior to the administrative appeal, an “Emergency Situation Determination and Exemption from Stay” (“ESD”) which exempted Phase I from automatic administrative stays. The next day, the environmental groups also filed suit in the United States District for the Northern District of California seeking injunctive relief to stop implementation of Phase I, including harvesting of burned timber by plaintiffs in the WLP and Griz sale areas. In response to the suit, Trinity and Hagen voluntarily suspended operations for forty-eight hours.

On July 12, 2001, the district court issued a temporary restraining order enjoining the Forest Service from taking any action under Phase I. The contracting officer'issued two identical letters to plaintiffs on July 19, 2001, notifying them that “to comply with the court order, under contract provision C6.01-Inter-ruption or Delay of Operations, this letter serves as your written notice to cease all operations under this contract.”

On the same day that it issued the letters notifying plaintiffs of the C6.01 suspensions, the Forest Service also withdrew the ESD, and the project was placed under the Forest Service’s appeals regulations. The effect of this was an automatic administrative suspension of the project while the appeal was resolved. This resulted in the environmental groups withdrawing them court action. Consequently, the suit was dismissed without prejudice.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Timber Products Co. v. United States
103 Fed. Cl. 225 (Federal Claims, 2011)
Jay Cashman, Inc. v. United States
88 Fed. Cl. 297 (Federal Claims, 2009)
Scott Timber, Inc. v. United States
86 Fed. Cl. 102 (Federal Claims, 2009)
Blue Lake Forest Products, Inc. v. United States
86 Fed. Cl. 366 (Federal Claims, 2009)
SGS-92-X003 v. United States
85 Fed. Cl. 678 (Federal Claims, 2009)
Renda Marine, Inc. v. United States
66 Fed. Cl. 639 (Federal Claims, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
66 Fed. Cl. 98, 2005 U.S. Claims LEXIS 168, 2005 WL 1459442, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trinity-river-lumber-co-v-united-states-uscfc-2005.