Tri County Industries, Inc. v. District of Columbia

200 F.3d 836, 339 U.S. App. D.C. 378, 2000 WL 10273
CourtCourt of Appeals for the D.C. Circuit
DecidedMarch 8, 2000
Docket99-7028
StatusPublished
Cited by18 cases

This text of 200 F.3d 836 (Tri County Industries, Inc. v. District of Columbia) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tri County Industries, Inc. v. District of Columbia, 200 F.3d 836, 339 U.S. App. D.C. 378, 2000 WL 10273 (D.C. Cir. 2000).

Opinion

Opinion for the court filed by Circuit Judge HENDERSON.

KAREN LeCRAFT HENDERSON, Circuit Judge:

This appeal arises from proceedings determining what damages, if any, appellant Tri County Industries, Inc. (Tri County) should be awarded to compensate for what this court previously determined to be the District of Columbia’s (District) violation of its fifth amendment right to procedural due process. See Tri County Indus., Inc. v. District of Columbia, 104 F.3d 455, 460-62 (D.C.Cir.1997). Following the first of two trials, the jury awarded $5,000,000. The trial court then granted a new trial, nisi remittitur to $1,000,000, which was refused. At the second trial, the district court admitted evidence excluded from the first and the jury returned nominal damages of $100. Tri County challenges the court’s order granting the District’s alternative motion for a new trial as well as several evidentiary rulings in the second trial and requests reinstatement of the first award or, in the alternative, a new trial due to allegedly erroneous evidentiary rulings during the second trial. For the reasons set forth below, we reverse the district court’s order of July 23, 1998 and reinstate the original jury verdict of $5,000,000.

I.

On February 26, 1993 Tri County obtained a building permit from the District authorizing conversion of an empty warehouse into a facility for its business of decontaminating soil tainted with oil and other hazardous materials. While securing the permit, Tri County also obtained an air quality permit as well as a waiver of the required environmental impact statement. Even several months after it obtained the necessary permits, however, it had not begun operating due to equipment delivery delays. On September 7 it received a District citation for storing soil at the facility without the required certificate of occupancy. 1 Tri County neither removed the soil nor paid the fine; consequently, the District issued a stop-work order on September 22. Tri County did not challenge the citation or order. Its failure to respond led to an order by the District Department of Consumer and Regulatory Affairs (DCRA) dated October 13, 1993 purporting to suspend Tri County’s building permit.

The building permit had already been suspended on September 20, however, when, prompted by a groundswell of community opposition to the project, Hampton Cross, acting DCRA director, summarily suspended Tri County’s building permit. *839 The DCRA sent Tri County a letter requesting further information on October 15, 1993 to which Tri County did not respond. On December 6 the DCRA sent another letter, this time rescinding the environmental impact statement waiver and threatening imminent revocation proceedings on the building permit. Tri County’s only response was to remove the soil that had caused the initial citation. Tri County’s counsel advised it that an appeal likely would be influenced by politics given the strong community opposition and that he could not guarantee when such an appeal would be heard. Given the high rental cost of the property in question and the necessity of purchasing, without delay, costly equipment in high demand, Tri County estimated the costs of an appeal at nearly $1,000,000. With no assurance of a prompt hearing and the prospect of a politically influenced review process, Tri County abandoned its project.

Tri County brought suit under 42 U.S.C. § 1983 and succeeded in its challenge to the September 20 suspension of its building permit when this court reversed the district court’s dismissal, holding that the suspension violated Tri County’s right to procedural due process. See Tri County Indus., 104 F.3d at 460-62. We remanded for consideration of damages. See id. at 462. The subsequent proceedings in the district court are at issue in this appeal.

The first trial began on April 14, 1998. Tri County presented evidence of its costs already incurred, evidence of lost profits through the testimony of a mechanical engineer and the report of an economist and evidence as to the local market demand for a soil treatment facility through the testimony of a geologist at an environmental consulting firm. The District largely accepted the testimony, often failing to object or seriously cross-examine. Instead, the District relied on its argument that Tri County failed to mitigate its damages when it refused to provide the information the DCRA requested and when it declined to challenge the stop-work and suspension orders. The District also sought to demonstrate that Tri County might not have been allowed to operate its facility because community opposition, arising largely out of concern over the facility’s effect on the health and safety of the community, would derail the regulatory procedures. Hindering its argument was the trial court’s exclusion or striking of evidence relating to health and safety concerns. See Joint Appendix (JA) 186-89. The court found the District’s permitting process had resolved the issues as a matter of law. See id. at 182-83, 189. In the end, the jury awarded $5,000,000.

The trial court denied the District’s post-trial motion for judgment as a matter of law but granted the alternative motion for a new trial, nisi remittitur to $1,000,-000. Addressing the District’s primary argument, the court ruled that the District had to establish both the standard for reasonable mitigation under the circumstances and that Tri County failed to meet it. The District failed to sustain that burden, particularly in light of Tri County’s evidence that it would have to spend nearly $1,000,000 to recoup its expenses of $536,421. The court reversed field, however, in reviewing the award for future damages which, assuming the $536,421 in costs were awarded, constituted $4,463,579 of the $11,628,174 figure Tri County presented to the jury. Emphasizing that Tri County did not “invest[ ] a penny to seek reinstatement of the unlawfully suspended building permit,” the court ruled that the District need not have established a reasonableness standard because Tri County’s failure to mitigate was unreasonable per se. District Court’s Memorandum Order filed July 23, 1998 (Memorandum Order), at 2. The court also found the lost profits evidence should not have been considered by the jury without the District having the chance to prove that the facility might not have been allowed to operate. Accordingly, the court found the estimate of lost profits “too speculative and remote” and, in any event, found the award “grossly excessive.” Id.

*840 Tri County declined the $1,000,000 remittitur and a second trial commenced on January 29,1999. In this trial, the district court allowed the District to admit the health and safety evidence originally excluded. This time the District challenged Tri County’s experts and offered the testimony of three new witnesses, one of whom refuted Tri County’s estimate of future profits. Another witness discussed a potential zoning bar to the facility and the third discussed health and safety hazards associated with soil remediation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dwain W. Tate - Adversary Proceeding
District of Columbia, 2020
State v. Dixon
2018 Ohio 4841 (Ohio Court of Appeals, 2018)
State v. Apanovitch (Slip Opinion)
2018 Ohio 4744 (Ohio Supreme Court, 2018)
Landis v. Tailwind Sports Corporation
District of Columbia, 2017
State v. Collier
2016 Ohio 4951 (Ohio Court of Appeals, 2016)
Adenariwo v. Federal Maritime Commission
808 F.3d 74 (D.C. Circuit, 2015)
National Railroad Passenger v. Veolia Transportation Services, Inc.
791 F. Supp. 2d 33 (District of Columbia, 2011)
Basken v. District of Columbia Board of Zoning Adjustment
946 A.2d 356 (District of Columbia Court of Appeals, 2008)
Pattee v. Georgia Ports Authority
512 F. Supp. 2d 1372 (S.D. Georgia, 2007)
Porter, Melvin v. Natsios, Andrew S.
414 F.3d 13 (D.C. Circuit, 2005)
State v. Luckett
761 N.E.2d 84 (Ohio Court of Appeals, 2001)
United States v. Schaffer
229 F.3d 284 (D.C. Circuit, 2000)
United States v. Schaffer, Archibald
240 F.3d 35 (D.C. Circuit, 2000)
Tri Cty Indust Inc v. DC
208 F.3d 1066 (D.C. Circuit, 2000)
Tri County Industries, Inc. v. District of Columbia
208 F.3d 1066 (D.C. Circuit, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
200 F.3d 836, 339 U.S. App. D.C. 378, 2000 WL 10273, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tri-county-industries-inc-v-district-of-columbia-cadc-2000.