Town of Norwood v. Federal Energy Regulatory Commission

476 F.3d 18, 2007 U.S. App. LEXIS 2301, 2007 WL 293071
CourtCourt of Appeals for the First Circuit
DecidedFebruary 2, 2007
Docket06-1658, 06-2054
StatusPublished
Cited by29 cases

This text of 476 F.3d 18 (Town of Norwood v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Norwood v. Federal Energy Regulatory Commission, 476 F.3d 18, 2007 U.S. App. LEXIS 2301, 2007 WL 293071 (1st Cir. 2007).

Opinion

BOUDIN, Chief Judge.

The Town of Norwood, Massachusetts (“Norwood”), which operates a municipal electric system serving local businesses and residents, seeks review of an order of the Federal Energy Regulatory Commission (“FERC”). The order sustained a contract termination charge contained in a tariff previously filed by New England Power Company (“NEPCO”). The background events have been the subject of prior litigation in this court, principally in Town of Norwood v. FERC (“Norwood I”), 202 F.3d 392 (1st Cir.2000), cert. denied, 531 U.S. 818, 121 S.Ct. 57, 148 L.Ed.2d 24 (2000).

For many years, NEPCO was a major power wholesaler in New England. It operated generating plants and a transmission network, and sold power wholesale to affiliated distribution companies (such as Massachusetts Electric Company, which served Massachusetts, and Narragansett Electric Company, which served Rhode Island) as well as to non-affiliated distributors like Norwood. Service to Norwood was provided under a long-term requirements contract of a kind then common in the utilities industry.

The contract, which began in 1983 and thereafter was extended by Norwood until October 2008, required NEPCO to supply, and Norwood to purchase, Norwood’s power requirements from NEPCO at rates provided by NEPCO’s Tariff No. 1. The contract could be terminated by Norwood without penalty but only upon seven years’ prior notice. The present litigation arises out of NEPCO’s action in providing, and Norwood’s decision to exercise, a new option permitting customers to terminate their contracts early.

Beginning in late 1996, in response to legislative and regulatory initiatives to promote competition and consumer choice in the electric power industry, NEPCO made a series of regulatory filings. Among these were settlements offered by NEPCO to NEPCO’s distributor customers — both affiliates and non-affiliates (including Nor-wood) — permitting them to terminate their NEPCO requirements contracts earlier than otherwise permitted, upon payment of a contract termination charge.

The aim was to allow distributors flexibility to choose new suppliers while permitting NEPCO to recover its “stranded costs” — that is, investments made by NEPCO to meet the projected long-term requirements of its distributor customers. 1 The proposed settlement terms also provided that NEPCO would offer its affiliates, but not Norwood, low (but gradually escalating) “wholesale standard offer” rates for power without the need for a contract; the affiliates were required to offer corresponding retail standard offer rates to their retail customers, but Nor-wood, as a municipal utility, was not. Mass. Gen. Laws ch. 164, § 47A.

*21 Additionally, as part of its restructuring, NEPCO sought approval from FERC to sell virtually all of its non-nuclear generating facilities. The buyer, USGen New England, Inc., agreed to assume responsibility for providing the “wholesale standard offer” service to NEPCO’s affiliates who terminated, and agreed not to raise rates for NEPCO’s remaining distributor customers, including Norwood. New Eng. Power Co., 1998 WL 89673, 82 F.E.R.C. 61,179, at 61,658-60 (1998) (“New Eng. Power VII ”), reh’g denied, 1998 WL 385144, 83 F.E.R.C. 61,275 (1998) (“New Eng. Power VIII ”).

FERC approved the settlement offers and divestiture over Norwood’s objection. 2 NEPCO’s three affiliated customers and three of its unaffiliated municipal customers opted to accept NEPCO’s settlement offer, to terminate early, and to pay the contract termination charge. Other non-affiliates opted to continue to purchase their power requirements from NEPCO at Tariff No. 1 rates through the contractual seven-year notice period for termination.

Norwood was unwilling to take either course of action. It did not want to continue buying power at Tariff No. 1 rates when its distributor “competitors” had been offered lower non-contract rates; it viewed such an arrangement as discriminatory. Nor did it want to pay a contract termination charge for NEPCO’s stranded costs; because it purchased its transmission services from Boston Edison, not NEPCO, it fell outside the stranded cost obligations imposed by FERC under Order No. 888. 3

Instead, Norwood notified NEPCO on March 4, 1998, that on April 1 it would unilaterally terminate its contract with NEPCO — without giving the required seven years’ notice — and switch to a different power supplier. NEPCO then filed a tariff amendment to its Tariff No. 1 permitting any of its remaining distributor customers, including Norwood, to terminate their requirements contracts on thirty days’ notice upon the payment of a contract termination charge (“CTC”) whose formula was specified in the tariff amendment. Norwood I, 202 F.3d at 397.

This CTC was calculated using a formula that would enable NEPCO to recover the revenues that it would have collected had a terminating customer continued to pay the tariff rate then in effect through the end of the contract term. The CTC equaled the number of years remaining on the contract (L) multiplied by the difference between the expected annual revenue from the terminating customer based on the rates in effect at the time of termination (R) 4 and the estimated market val *22 ue of the released capacity (M); that is, CTC = L x(R-M). The CTC was capped so as not to exceed the terminating customer’s contribution to NEPCO’s fixed power supply costs; the tariff defined that contribution as L multiplied by the difference between R and NEPCO’s annual average fuel costs with respect to the customer.

This CTC was in several respects less favorable than the contract termination charge applied to settling customers: it did not provide the terminating customer a credit for the recovery of costs associated with NEPCO’s business, for example, through the profitable divestiture of generating plants; and it did not update (“true-up”) the formula values to reflect actual, rather than projected, market values for released capacity. New Eng. Power Co., 1998 WL 246647, 83 F.E.R.C. 61,174, at 61,723 nn. 5, 13 (1998) (“New Eng. Power IX”), reh’g denied, 1998 WL 452339, 84 F.E.R.C. 61,175 (1998) (“New Eng. Power X ”); New Eng. Power V, 1998 WL 203156, 83 F.E.R.C. at 61,419 n. 5.

In proceedings before FERC, Norwood objected to the tariff amendment on a number of grounds, including claims that it violated the “stranded cost recovery” provisions of FERC Order No. 888, and that the disparities between the CTC offered to Norwood and the CTC offered to settling customers constituted an “undue preference” in violation of the Federal Power Act. 16 U.S.C. § 824d(b) (1994).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
476 F.3d 18, 2007 U.S. App. LEXIS 2301, 2007 WL 293071, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-norwood-v-federal-energy-regulatory-commission-ca1-2007.