Town of Lyndon v. Burnett's Contracting Co.

413 A.2d 1204, 138 Vt. 102, 1980 Vt. LEXIS 1125
CourtSupreme Court of Vermont
DecidedFebruary 5, 1980
Docket302-78
StatusPublished
Cited by16 cases

This text of 413 A.2d 1204 (Town of Lyndon v. Burnett's Contracting Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Lyndon v. Burnett's Contracting Co., 413 A.2d 1204, 138 Vt. 102, 1980 Vt. LEXIS 1125 (Vt. 1980).

Opinion

Daley, J.

This is an appeal from a judgment against defendants for breach of a bid proposal and bid bond. The court awarded plaintiff damages in the amount of the bid bond, as provided in the liquidated damages clauses of the proposal and bond. Defendants appeal.

In 1975, defendant Burnett’s Contracting Co., Inc. (Burnett) submitted a bid to plaintiff, Town of Lyndon, on Contract No. 2 for the construction of interceptor sewers and force mains. This bid was bonded by defendant Hartford Accident and Indemnity Company (Hartford). By submitting the bid proposal, Burnett agreed that it would not revoke its bid within sixty consecutive days after the opening of the bids, and that it would sign the contract agreement if its bid was accepted. By bonding this bid, defendant Hartford assumed secondary liability for any breach of the bid proposal by Burnett.

The bid proposals were opened on July 16, 1975. Shortly thereafter, plaintiff notified defendant Burnett of its intent to accept defendant’s bid. Although Burnett had assumed that plaintiff possessed all easements necessary for completion of the job, soon after its bid was accepted it discovered that plaintiff lacked 14 easements.

By August 27, plaintiff still lacked 8-9 easements. On that date, two letters crossed in the mail. In one, plaintiff notified defendant as to the time and place of the contract signing. In the other, Burnett notified plaintiff that, because of the lack of necessary easements, “we cannot enter into a contract to perform the proposed project.”

Plaintiff replied that it would proceed with the scheduled contract signing, and that it was prepared to execute the contract in accordance with the bid proposal. Nonetheless, the contract was never executed by defendant Burnett. Furthermore, defendant Hartford rejected plaintiff’s demand for payment on the bid bond.

Plaintiff brought this action for breach of contract against Burnett and Hartford in superior court. Burnett counter *105 claimed against plaintiff for breach of an agreement to obtain all necessary easements, and for fraudulent misrepresentation. At the close of the trial, the court granted plaintiff’s motion to dismiss the counterclaim. Subsequently, by order of September 26, 1978, the court entered judgment in plaintiff’s favor against both defendants.

The defendants join in three principal claims here:

1. That plaintiff breached an agreement, which goes to the essence of the contract, by not having all necessary easements in hand when the bid was accepted (or, at the latest, when Burnett was to have signed the contract), and therefore Burnett was excused from performance;
2. That the contract should be rescinded because Burnett entered into it under a unilateral mistake of fact, not resulting from any negligence on Burnett’s part, and not arising without fault on the part of the plaintiff; and
3. That Burnett should be relieved of its obligation to perform because performance was impossible.

In addition, defendant Burnett claims error in the dismissal of its counterclaim for breach of contract and fraudulent misrepresentation.

The claim that defendants are excused because plaintiff breached an agreement to have all easements in hand by the date the contract was to be signed fails because plaintiff made no such agreement. Defendants rely on § 6.16 of the contract, which states in part: “The Contractor is advised that copies of all permanent and temporary easements and' rights-of-way for work done under this contract are on file at the municipal office.” Defendants argue that this provision bound plaintiff to have all easements for the entire job on file at the municipal office prior to execution of the Contract-Failure to have these easements, according to defendants, breached the essence of the contract because Burnett’s bid assumed a particular cost-efficient sequence of work, which was made impossible by the absence of key easements. The plaintiff, on the other hand, argues that the provision means only that all easements that the town has acquired to date *106 are available at the office for inspection, but not that the town has acquired all easements that will ever be needed for the job.

The meaning of a contract is to be determined by examination of every material part, in order to form a harmonious whole. Cross-Abbott Co. v. Howard’s, Inc., 124 Vt. 439, 441, 207 A.2d 134, 137 (1965); Breding v. Champlain Marine & Realty Co., 106 Vt. 288, 296, 172 A. 625, 628 (1934). Several other sections of the contract contradict Burnett’s interpretation of § 6.16. Section 4.3 specifies that the sequence of the work “shall be subject to the approval of the Engineer who shall have authority to direct that changes be made in such sequence where public necessity or welfare shall require,” and that the engineer’s approval or direction does not affect the contractor’s responsibility for the work. Section 4.13 provides for commencement of work within ten days after receipt of the owner’s notice to proceed, “at such points as the Engineer may approve.” Most important, however, is the express contradiction of Burnett’s interpretation of § 6.16, contained in § 4.14:

The Owner may delay the beginning of the work or any part thereof if the necessary lands or rights-of-way for such work shall not have been obtained. The Contractor shall have no claim for damages on account of such delay, but shall be entitled to ... additional time____

It is true, as defendants argue, that § 6.16 is one of the special conditions which, according to § 6.1, control whenever there is a conflict with another provision. If possible, however, a contract must be construed to give effect to every part, and therefore this Court will avoid constructions that render ineffectual any part of the language of a contract. Haberman v. Department of Employment Security, 136 Vt. 573, 575, 396 A.2d 141, 142 (1978) (per curiam); Furlon v. Haystack Mountain Ski Area, Inc., 136 Vt. 266, 269, 388 A.2d 403, 405 (1978). Section 6.16, when read in conjunction with § 4.14, simply means that all easements that have been acquired are on file; it does not mean that all easements for the entire project are on file. This construction avoids any conflict between the provisions, and gives effect to *107 the instrument as a harmonious whole. Finally, even had defendants’ view prevailed, we fail to see how defendants were harmed by the lack of several easements, because the contract as a whole does not allow the contractor absolute control over the sequence of its work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Malone 118 Main St v. Hugos Restaurant
Vermont Superior Court, 2026
von Trapp CU Permit
Vermont Superior Court, 2014
Inkel v. Pride Chevrolet-Pontiac, Inc.
2008 VT 6 (Supreme Court of Vermont, 2008)
Manosh v. First Mountain Vermont, L.P.
2004 VT 122 (Supreme Court of Vermont, 2004)
Asbury v. Crawford Electric Cooperative, Inc.
51 S.W.3d 152 (Missouri Court of Appeals, 2001)
Wenzel v. Brault's Mobile Homes, Inc.
566 A.2d 993 (Supreme Court of Vermont, 1989)
Isbrandtsen v. North Branch Corp.
556 A.2d 81 (Supreme Court of Vermont, 1988)
Thomas v. Olds
556 A.2d 62 (Supreme Court of Vermont, 1988)
Pennconn Enterprises, Ltd. v. Huntington
538 A.2d 673 (Supreme Court of Vermont, 1987)
Spaulding v. Cahill
505 A.2d 1186 (Supreme Court of Vermont, 1985)
In Re Handy
481 A.2d 1051 (Supreme Court of Vermont, 1984)
In Re Vermont Health Service Corp.
482 A.2d 294 (Supreme Court of Vermont, 1984)
Rutz v. Essex Junction Prudential Committee
457 A.2d 1368 (Supreme Court of Vermont, 1983)
City of Barre v. Town of Orange
417 A.2d 939 (Supreme Court of Vermont, 1980)
Helm v. Helm
415 A.2d 1333 (Supreme Court of Vermont, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
413 A.2d 1204, 138 Vt. 102, 1980 Vt. LEXIS 1125, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-lyndon-v-burnetts-contracting-co-vt-1980.