Town Concrete Pipe of Washington, Inc. v. Redford

717 P.2d 1384, 43 Wash. App. 493
CourtCourt of Appeals of Washington
DecidedApril 23, 1986
Docket13534-1-I
StatusPublished
Cited by16 cases

This text of 717 P.2d 1384 (Town Concrete Pipe of Washington, Inc. v. Redford) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town Concrete Pipe of Washington, Inc. v. Redford, 717 P.2d 1384, 43 Wash. App. 493 (Wash. Ct. App. 1986).

Opinion

Ringold, A.C.J.

Appellant, Walter E. Heller and Company, appeals the trial court's judgment that respondent, Art Redford d/b/a Redford Construction Company, is entitled to $20,000 damages as unjust enrichment.

This case presents three issues for consideration. Can a construction lender defeat a contractor's claim under RCW 60.04.210 by refusing to make further disbursements and foreclosing on the security? Did enactment of RCW 60.04-.210 abolish unjust enrichment as a remedy available to contractors against lenders? Did the court err in concluding that the doctrine of unjust enrichment was applicable to the facts of this case? We conclude that damages for unjust enrichment are not available here and reverse.

In August 1979, Heller, as lender, entered into a written agreement with the borrower, Rainier Pacific Industries, to loan $850,000 to finance Rainier Pacific's development of lots for a residential subdivision called Killarney Glen. The loan funds were to be advanced upon certain conditions as set forth in the loan agreement. A note and deed of trust were executed by Rainier Pacific to secure the transaction.

*495 The major advance of $294,000 was used by Rainier Pacific to purchase the land for development at Killarney Glen. In total, $385,537 was advanced by Heller to Rainier Pacific through January 31, 1980. Thereafter, Rainier Pacific defaulted on its loan obligations and no further funds were advanced by Heller.

In October 1980, 9 months after the last loan advance, Rainier Pacific entered into a contract with Redford to perform construction work at Killarney Glen. Though Redford knew that Rainier Pacific was having difficulties restructuring its loan with Heller, Redford commenced work in February 1981 at the urging of Rainier Pacific. Rainier Pacific promised Redford would get payment. Heller simply indicated that the loan was in the process of being restructured. Redford was also aware that another contractor had a lien against the development and that this lien was causing problems for Rainier Pacific in obtaining its loan proceeds. On March 16, 1981, Redford met with Rainier Pacific to discuss this problem. Rainier Pacific continued in default.

In early April 1981, Redford requested a set-aside letter from Heller. Without having received this letter, Redford began laying pipe and completed a major part of the work between April 28 and May 22, 1981. On or about May 21, 1981, Redford was informed that Rainier Pacific remained in default, that the loan was not restructured, and the set-aside letter would not be forthcoming.

Redford stopped work on May 22, 1981. A stop notice was filed on May 27, 1981, and two amended stop notices dated June 23 and July 6, 1981, were subsequently filed. These notices advised Heller that Redford had not been paid.

Heller commenced nonjudicial foreclosure proceedings on its deed of trust against the Killarney Glen property in fall 1982. On February 25, 1983, Heller obtained title by trustee's sale.

Redford sued Rainier Pacific for breach of contract and *496 Heller for unjust enrichment. 1 At trial, Redford obtained a stipulated judgment against Rainier Pacific in the amount of $103,332.10. The court also entered judgment against Heller in the amount of $20,000 based upon Redford's claim of unjust enrichment. Heller appealed and Redford cross-appealed.

Claim Under RCW 60.04.210 2

The stop notice provision, RCW 60.04.210, was devised to provide additional security to those who furnish labor or materials in the erection or improvement of buildings. Under the statute, a potential claimant may give notice to a *497 construction lender that payment by the borrower is more than 5 days overdue. RCW 60.04.210(2). The lender then has three options:

First, if the lender chooses to allow further draws upon the construction loan fund, he "shall withhold" funds to satisfy the stop notice from these "next and subsequent draws." Second, if the lender chooses to continue draws without withholding funds for the stop notice, he suffers the "penalty" of Section 2(6), and his mortgage is subordinated to the subsequent mechanics' lien of the stop notice claimant "to the extent of the interim or construction financing wrongfully disbursed, but in no event in an amount greater than the sums ultimately determined to be due the potential lien claimant by a court of competent jurisdiction, or more than the sum stated in the notice, whichever is less." Third, the lender may avoid the effect of the stop notice altogether by making no further loan advances and foreclosing his mortgage. In this last situation, the PLC's only recourse is to his mechanics' lien which will have no enhanced priority by reason of the stop notice.

(Footnotes omitted.) Note, Mechanics' Lien: The "Stop Notice" Comes to Washington, 49 Wash. L. Rev. 685, 695-96 (1974).

Redford contends that since the third option is not specifically provided by the statute, it may not be used. RCW 60.04.210(4). This argument fails for a number of reasons.

First, nothing in the statute itself prohibits the lender from exercising his right to foreclose on a deed of trust when the borrower is in default. So, this court should not imply such a prohibition. Cf. Cordell v. Regan, 23 Wn. App. 739, 746, 598 P.2d 416 (1979). Second, lien statutes are in derogation of the common law and should be strictly construed. Burns v. Miller, 42 Wn. App. 801, 803, 714 P.2d 1190 (1986); Shope Enters. v. Kent Sch. Dist., 41 Wn. App. 128, 133, 702 P.2d 499 (1985). The provisions of the stop notice statute should not be expanded beyond its explicit language. Last, the Legislature's intent to provide an additional protection for a potential lien claimant is not violated by strict interpretation of the statute. As a general *498 rule, it may be undesirable for a lender to foreclose before a project is finished. Note, supra at 696. The reason is " [mjore often than not, the market value of a partially constructed building will be substantially less than the total cost of the labor and material which has already been incorporated into its construction." J.G. Plumbing Serv., Inc. v. Coastal Mortgage Co., 329 So.

Related

Brian Fisse, App. v. Heather M. Garvie, Resp.
Court of Appeals of Washington, 2015
In Re The Estate Of: Homer R. House
Court of Appeals of Washington, 2014
CC&H Investments v. Rcs Northwest, LLC
Court of Appeals of Washington, 2013
Pacific Continental Bank v. Soundview 90, LLC
273 P.3d 1009 (Court of Appeals of Washington, 2012)
Williams v. ATHLETIC FIELD, INC.
261 P.3d 109 (Washington Supreme Court, 2011)
Ehsani v. McCullough Family Partnership
159 P.3d 407 (Washington Supreme Court, 2007)
Seattle Mortgage Co. v. Unknown Heirs of Daisy Gray
136 P.3d 776 (Court of Appeals of Washington, 2006)
Lumberman's of Washington, Inc. v. Barnhardt
949 P.2d 382 (Court of Appeals of Washington, 1997)
Richard F. Kline, Inc. v. Signet Bank
651 A.2d 442 (Court of Special Appeals of Maryland, 1995)
Schumacher Painting Co. v. First Union Management, Inc.
850 P.2d 1361 (Court of Appeals of Washington, 1993)
Emerald City Electric & Lighting, Inc. v. Jensen Electric, Inc.
846 P.2d 559 (Court of Appeals of Washington, 1993)
Seattle-First National Bank v. Westwood Lumber, Inc.
829 P.2d 1152 (Court of Appeals of Washington, 1992)
Lynch v. Deaconess Medical Center
776 P.2d 681 (Washington Supreme Court, 1989)
Trane Co. v. Randolph Plumbing & Heating
722 P.2d 1325 (Court of Appeals of Washington, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
717 P.2d 1384, 43 Wash. App. 493, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-concrete-pipe-of-washington-inc-v-redford-washctapp-1986.