Richard F. Kline, Inc. v. Signet Bank

651 A.2d 442, 102 Md. App. 727, 1995 Md. App. LEXIS 4
CourtCourt of Special Appeals of Maryland
DecidedJanuary 4, 1995
DocketNo. 618
StatusPublished
Cited by9 cases

This text of 651 A.2d 442 (Richard F. Kline, Inc. v. Signet Bank) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Richard F. Kline, Inc. v. Signet Bank, 651 A.2d 442, 102 Md. App. 727, 1995 Md. App. LEXIS 4 (Md. Ct. App. 1995).

Opinion

WENNER, Judge.

Richard F. Kline, Inc. (Kline) appeals from a judgment of the Circuit Court for Frederick County. On appeal, Kline presents but one question:

“Whether Kline has a cause of action against Signet for unjust enrichment when Kline continued to perform valuable work on a real estate development project after Signet had declared the developer in default, but when Kline had not received notice of this, and when Signet was aware of Kline’s on-going work, paid no one for it, and recorded an increase in the value of its collateral in the project of $900,000.00 before Kline became aware of the Signet declaration of default and stopped work?”

We shall answer “no,” and affirm the judgment of the circuit court.

FACTS

In 1990, a partnership, Coventry Venture Associates1 (Coventry), was formed for the purpose of developing a project in Frederick County known as Lake Coventry. To finance the project, Coventry received a construction loan from Signet. Coventry then subcontracted with Kline for excavation, paving, and utility work. Before entering into the contract, Kline contacted Signet to ensure that the project’s budget was sufficient to cover the work to be performed by Kline. Receiving an affirmative answer, Kline entered into a contract with Coventry and work progressed without incident until 1991.

The year 1991 began with the two individuals most involved in the Coventry partnership accusing one another of various improprieties. Consequently, Signet notified Coventry that it would disburse no more funds from the interest reserve account to pay interest on the loan until the dispute was settled. When Coventry failed to make the interest payments, [730]*730Signet declared the loan to be in default.2 Signet subsequently instituted foreclosure proceedings, and placed an advertisement of the foreclosure sale in the local newspaper. Coventry brought the interest up-to-date prior to the sale, however, and Signet cancelled the foreclosure sale. Signet then began negotiating a new agreement with Coventry.

During these negotiations, Kline proceeded with the work required by its contract with Coventry until Coventry failed to make the April 1991 progress payment. Kline stopped work on the project in June 1991, and sought a mechanic’s lien on the project. And, unable to reach a new agreement with Coventry, Signet resumed foreclosure proceedings. Before Kline could obtain a mechanic’s lien, Coventry entered into bankruptcy, although Signet was granted relief from the automatic stay and proceeded with the foreclosure sale. At the foreclosure sale in April 1992, a subsidiary of Signet purchased the property. Shortly after it purchased the project, it was sold by the subsidiary at a substantial loss. Signet ultimately lost approximately $2,500,000 on the project.

Having been unable to obtain a mechanic’s lien, Kline filed a complaint in the Circuit Court for Frederick County seeking to recover from Signet the total sums unpaid under its contract with Coventry. Kline and Signet moved for summary judgment. In an Opinion and Order filed on 7 March 1994, the circuit court granted Signet’s motion for summary judgment and denied Kline’s. Kline then noted this appeal.

DISCUSSION

When reviewing the grant of a motion for summary judgment, we must determine whether the trial court was legally correct in granting the motion. Heat & Power v. Air Products, 320 Md. 584, 592, 578 A.2d 1202 (1990). “All inferences must be resolved against the moving party when a [731]*731determination is made as to whether a factual dispute exists. This is true even if the underlying facts are undisputed.” Berkey v. Delia, 287 Md. 302, 304-305, 413 A.2d 170 (1980). On the other hand, a claim of unjust enrichment requires a trial court to determine whether a contract between the parties should be implied as a matter of law; in other words, whether a quasi contract exists. Where the facts are undisputed, whether a quasi contract exists is a question of law that may be decided on a motion for summary judgment. Bloom-garden v. Coyer, 479 F.2d 201, 211 (D.C.1973).

I.

We have not before considered an unpaid subcontractor’s claim that a construction lender was unjustly enriched where the subcontractor was unable to obtain a mechanic’s lien or seek damages for breach of contract because the general contractor was in bankruptcy. As we said in Everhart v. Miles, 47 Md.App. 131, 136, 422 A.2d 28 (1980):

Unjust enrichment is defined as
the unjust retention of a benefit to the loss of another, or the retention of money or property of another against the fundamental principles of justice or equity and good conscience. A person is enriched if he has received a benefit, and he is unjustly enriched if retention of the benefit would be unjust. Unjust enrichment of a person occurs when he has and retains money or benefits which in justice and equity belong to another.

See 66 AmJur2d Restitution and Applied Contracts, § 3 (1973) (footnote omitted).

The situation we are here facing, however, differs from that in Everhart v. Miles because Signet neither owned nor retained the Lake Coventry project. Signet’s construction loan was secured by a mortgage on the project.

In Yost v. Early, 87 Md.App. 364, 589 A.2d 1291 (1991), we recently reiterated the three part test for unjust enrichment:

Under Maryland law, to sustain a claim under the doctrine of unjust enrichment, three elements must be established:
[732]*7321. A benefit conferred upon the defendant by the plaintiff;
2. An appreciation or knowledge by the defendant of the benefit; and
3. The acceptance or retention by the defendant of the benefit under such circumstances as to make it inequitable for the defendant to retain the benefit without payment of its value.

Id. at 387, 589 A.2d 1291. Kline contends that the doctrine of unjust enrichment applies in the case at hand, even though Signet did not own the property on which Lake Coventry was being developed. Consequently, we shall address whether Kline’s claim for unjust enrichment is appropriate under the circumstances now before us.

II.

The circuit court found that the requirements for establishing unjust enrichment set out in Yost were controlling. In endeavoring to determine the meaning of “benefit” and “unjust” as used in Yost, and finding no Maryland precedent, the circuit court relied upon Meehan v. Cheltenham Township, 410 Pa. 446, 189 A.2d 593 (1963) and D.A. Hill Co. v. CleveTrust Realty, 524 Pa. 425,

Related

Sims Agency v. GEICO
Fifth Circuit, 2025
Bel Air Carpet v. Korey Homes Bldg Grp
249 Md. App. 109 (Court of Special Appeals of Maryland, 2021)
Royal Investment Group, LLC v. Wang
961 A.2d 665 (Court of Special Appeals of Maryland, 2008)
FISCHER ORGANIZATION, INC. v. Landry's Seafood Restaurants, Inc.
792 A.2d 349 (Court of Special Appeals of Maryland, 2002)
Froelich v. Erickson
96 F. Supp. 2d 507 (D. Maryland, 2000)
County Commissioners v. J. Roland Dashiell & Sons, Inc.
747 A.2d 600 (Court of Appeals of Maryland, 2000)
Seafarers Welfare Plan v. Philip Morris
27 F. Supp. 2d 623 (D. Maryland, 1998)
Bennett Heating & Air Conditioning, Inc. v. NationsBank of Maryland
674 A.2d 534 (Court of Appeals of Maryland, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
651 A.2d 442, 102 Md. App. 727, 1995 Md. App. LEXIS 4, Counsel Stack Legal Research, https://law.counselstack.com/opinion/richard-f-kline-inc-v-signet-bank-mdctspecapp-1995.