T.J.D. Construction Co. v. City of New York

295 A.D.2d 180, 743 N.Y.S.2d 111, 2002 N.Y. App. Div. LEXIS 6132
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJune 13, 2002
StatusPublished
Cited by7 cases

This text of 295 A.D.2d 180 (T.J.D. Construction Co. v. City of New York) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
T.J.D. Construction Co. v. City of New York, 295 A.D.2d 180, 743 N.Y.S.2d 111, 2002 N.Y. App. Div. LEXIS 6132 (N.Y. Ct. App. 2002).

Opinion

—Order, Supreme Court, New York County (Charles Ramos, J.), entered March 2, 2001, which, in an action for delay damages by a contractor against defendant City, granted defendant’s motion for summary judgment dismissing the complaint, unanimously affirmed, without costs.

Plaintiffs argument that the delay caused by defendant’s testing and correction of equipment design defects was not contemplated, and that the contract’s no-damages-for-delay clause therefore does not apply, is refuted by contract provisions that, as correctly construed by the IAS court, called for the work to be done in two stages and for successful testing between the stages, so that a portion of the plant would always be in operation (see, Phoenix Contr. Corp. v New York City Health & Hosps. Corp., 118 AD2d 477, lv denied 68 NY2d 606). Nor is an issue of fact raised as to whether the complained of delay was caused by defendant’s bad faith or gross negligence in planning the project and scheduling the work, or that the seven-month delay was so unreasonable as to connote defendant’s abandonment of the contract (see, Corinno Civetta Constr. Corp. v City of New York, 67 NY2d 297, 309, 312-313). If anything, the delay connoted an active and good-faith attempt by defendant to rectify defects in the equipment used in the first stage of the upgrade that were first revealed by tests performed in the middle of the contract. Even if defendant should have anticipated such unsatisfactory test results by reason of information it had prior to the contract, and failed to take adequate account thereof, at worst the poor planning and scheduling of which plaintiff complains “amounted to no more than inept administration” within the scope of the no-damages-for-delay clause (S.N. Tannor, Inc. v A.F.C. Enters., 276 AD2d 363, 364). Concur—Williams, P.J., Andrias, Lerner, Rubin and Friedman, JJ.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tougher Industries, Inc. v. Dormitory Authority
130 A.D.3d 1393 (Appellate Division of the Supreme Court of New York, 2015)
LoDuca Associates, Inc. v. PMS Construction Management Corp.
91 A.D.3d 485 (Appellate Division of the Supreme Court of New York, 2012)
Plato General Construction Corp./EMCO Tech Construction Corp. JV, LLC v. Dormitory Authority
89 A.D.3d 819 (Appellate Division of the Supreme Court of New York, 2011)
Travelers Casualty & Surety Co. v. Dormitory Authority-State
735 F. Supp. 2d 42 (S.D. New York, 2010)
Law Co., Inc. v. Mohawk Const. & Supply Co.
702 F. Supp. 2d 1304 (D. Kansas, 2010)
Blue Water Environmental, Inc. v. Incorporated Village of Bayville
44 A.D.3d 807 (Appellate Division of the Supreme Court of New York, 2007)
Bat- Jac Contracting, Inc. v. New York City Housing Authority
1 A.D.3d 128 (Appellate Division of the Supreme Court of New York, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
295 A.D.2d 180, 743 N.Y.S.2d 111, 2002 N.Y. App. Div. LEXIS 6132, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tjd-construction-co-v-city-of-new-york-nyappdiv-2002.