Timothy Wilkins v. Laguna Bay Condominium Association, Inc.

CourtCourt of Appeals of Texas
DecidedSeptember 17, 2020
Docket13-19-00108-CV
StatusPublished

This text of Timothy Wilkins v. Laguna Bay Condominium Association, Inc. (Timothy Wilkins v. Laguna Bay Condominium Association, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Timothy Wilkins v. Laguna Bay Condominium Association, Inc., (Tex. Ct. App. 2020).

Opinion

NUMBER 13-19-00108-CV

COURT OF APPEALS

THIRTEENTH DISTRICT OF TEXAS

CORPUS CHRISTI - EDINBURG

TIMOTHY WILKINS, Appellant,

v.

LAGUNA BAY CONDOMINIUM ASSOCIATION, INC., Appellee.

On appeal from the 445th District Court of Cameron County, Texas.

MEMORANDUM OPINION Before Chief Justice Contreras and Justices Benavides and Longoria Memorandum Opinion by Justice Benavides

By two issues, appellant Timothy Wilkins appeals the jury verdict in favor of

appellee Laguna Bay Condominium Association, Inc. (Laguna Bay). Wilkins alleges that

there was (1) legally and (2) factually insufficient evidence to support the judgment. We

affirm. I. BACKGROUND

This case arises from a long-standing disagreement between Wilkins and Laguna

Bay. This appeal derives from the third lawsuit between the parties.

In 2009, Wilkins purchased North Unit 203 at Laguna Bay in South Padre Island,

Texas. His unit, as well as others in the complex, were damaged by Hurricane Dolly. Due

to water leaks in his unit, Wilkins and another condo owner, Gregory Kunkle, 1 filed suit

against Laguna Bay (first suit). In October 2013, the parties entered into a settlement

agreement (the Agreement) in which Laguna Bay agreed to certain terms and conditions.

Important to this case are the following sections:

3.A. [Laguna Bay] agrees to make the repairs, and further investigations called for, and any additional repairs recommended as a result of the further investigations in the July 9, 2013 Final Report of WJE [Wiss, Janney, Elstner Associates, Inc.] within 36 months of the date of this [Agreement], except if that becomes impossible by force majeure or by Acts of God. However, the prioritization and sequence of the work, and the selection of available options, shall be up to the discretion of the [Laguna Bay] Board after consultation with WJE. Notwithstanding the foregoing, any repairs that the [Laguna Bay] Board and the Homeowners deem economically unfeasible do not have to be made.

B. Notwithstanding A above, within 6 months of the date of the approval of this [Agreement] by the Homeowners, if such approval is obtained, the [Laguna Bay] shall:

1. Secure a report from Bob Fudge, P.E., on what repairs are needed to repair leaks to Plaintiffs’ Units; and

2. Effect such repairs at [Laguna Bay’s] expense.

....

D. The [Laguna Bay] will specify to Plaintiffs, within 60 days of the date of the [Agreement], which available sliding glass doors Plaintiffs may

1 Kunkle was not a party to any of the subsequent lawsuits between Wilkins and Laguna Bay. 2 use on their Units.

G. Plaintiffs shall be responsible for their pro-rata share of any assessments required for the [Laguna Bay] to comply with No.’s A, B & C above.

In 2015, Wilkins filed a second lawsuit (current suit) alleging noncompliance with

the requirements of the Agreement. His amended petition also alleged that Laguna Bay

requested a repair assessment of $91,316 from each of the owners. Laguna Bay filed a

counter-claim against Wilkins for breach of contract and covenants and requested

declaratory relief. Wilkins refused to pay the repair assessment because he stated that

Laguna Bay did not perform contractually under the Agreement, but alleged that Laguna

Bay made repairs to other units in the complex.2 The trial court granted a temporary

injunction enjoining Laguna Bay from collecting the assessment from Wilkins and from

foreclosing on Wilkins’s condo while this case proceeded.3

Trial on the merits proceeded. Wilkins testified that Unit 203 had been foreclosed

on and that was how he came to purchase it. He stated that there was water damage to

the unit after Hurricane Dolly and he notified Laguna Bay, but nothing came of it. Wilkins

explained that is why he initiated the first lawsuit in 2013, which resulted in the Agreement.

He signed the Agreement in October 2013 and received $10,000 from Laguna Bay, which

he believed was for “fees and expenses” due to the lawsuit. Wilkins believed that Laguna

2 Wilkins’s first amended petition alleged “Specifically, though not by way of limitation, Defendants have failed and refused to comply with their obligations under Sections 3.B.2, 3.D of the [Agreement].”

3 Laguna Bay appealed the temporary injunction to this Court and we affirmed the trial court’s

granting of the injunction. See Burkholder v. Wilkins, 504 S.W.3d 485 (Tex. App.—Corpus Christi–Edinburg 2016, no pet.). 3 Bay had an “obligation to repair” his condo at “its expense.” He testified that his family

had never been able to use the condo, he was never able to rent it out until recently after

Laguna Bay finished repairs on the entire building, and he incurred significant legal fees

from this lawsuit. Wilkins stated he last used the condo in 2011 and last rented it in 2013.

He estimated the weekly rental fee was $1450 and based on the determination of 184

weeks unoccupied, he lost approximately $266,800 in rental income.

Wilkins testified that he has not repaired his unit because once when he previously

had repaired it, the damage returned due to the water leaks. Wilkins had PuroClean, a

mold remediation company, evaluate his condo and they estimated $64,165.87 to repair

the mold damage. Wilkins also stated that Laguna Bay had the WJE report in July 2013,

before the Agreement was signed, so it knew what the “issues” and damages were before

it entered into the Agreement. Wilkins explained that he turned the electricity off to the

unit because he “didn’t want to pay for what he couldn’t use,” but disagreed with Laguna

Bay that the damage got worse after he disconnected the electricity. Wilkins testified that

he was “angry” Laguna Bay “broke the deal” in the Agreement. He explained that Laguna

Bay had the Fudge report in December 2013, which found the issues and offered

solutions, but did nothing to make any repairs.

On cross-examination, Wilkins said there was some damage in 2009, but it was

not as severe as it was currently. He also admitted he had Joe Villarreal, a contractor

Laguna Bay used, look at the unit after an upstairs neighbor had a water heater leak, but

stated he never repaired the damage because he did not get any money for the repair.

Wilkins explained that he sent Laguna Bay an email in January 2015 that he was going

4 to do a complete remediation of his unit to “get a reaction” and notify it that it was in

“breach of the [A]greement” and he was going to sue. He agreed with Laguna Bay that in

order to repair the water leaks, the source needed to be located, but Wilkins stated that

Laguna Bay “also have to look for it.” He disagreed that all the water damage was coming

from “above” as Laguna Bay stated; he stated there was also water penetrating the stucco

from the sides. Wilkins agreed that even though the homeowners agreed to pay the

assessment, he still had not paid it and also had an outstanding balance on his

homeowner association (HOA) fees.

Joseph Furcron with Furcron Property Management Company testified that he

manages Laguna Bay. He agreed that Wilkins’s estimate of $1450 for a weekly rental

seemed reasonable, but explained that rentals are at best forty to fifty percent occupancy,

not over seventy-five percent occupancy as Wilkins estimated. Furcron also agreed that

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Golden Eagle Archery, Inc. v. Jackson
116 S.W.3d 757 (Texas Supreme Court, 2003)
Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Long Trusts v. Griffin
222 S.W.3d 412 (Texas Supreme Court, 2006)
Dow Chemical Co. v. Francis
46 S.W.3d 237 (Texas Supreme Court, 2001)
Maritime Overseas Corp. v. Ellis
971 S.W.2d 402 (Texas Supreme Court, 1998)
GTE Mobilnet of South Texas Ltd. Partnership v. Pascouet
61 S.W.3d 599 (Court of Appeals of Texas, 2001)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
C.W. 100 Louis Henna, Ltd. v. El Chico Restaurants of Texas, L.P.
295 S.W.3d 748 (Court of Appeals of Texas, 2009)
B & W SUPPLY, INC. v. Beckman
305 S.W.3d 10 (Court of Appeals of Texas, 2009)
Henry v. Masson
333 S.W.3d 825 (Court of Appeals of Texas, 2010)
Hernandez v. Gulf Group Lloyds
875 S.W.2d 691 (Texas Supreme Court, 1994)
Hanks v. GAB Business Services, Inc.
644 S.W.2d 707 (Texas Supreme Court, 1982)
Editorial Caballero, S.A. De C v. v. Playboy Enterprises, Inc.
359 S.W.3d 318 (Court of Appeals of Texas, 2012)
Bartush-Schnitzius Foods Co. v. Cimco Refrigeration, Inc.
518 S.W.3d 432 (Texas Supreme Court, 2017)
Maurice Sloan II v. Goldberg B'Nai B'rith Towers
577 S.W.3d 608 (Court of Appeals of Texas, 2019)
MKM Engineers, Inc. v. Guzder
476 S.W.3d 770 (Court of Appeals of Texas, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Timothy Wilkins v. Laguna Bay Condominium Association, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/timothy-wilkins-v-laguna-bay-condominium-association-inc-texapp-2020.