James Burkholder, Mike Morgan, Joe Urbanek, Melissa Grebb, Ruthie Ewers, Benjamin Bujanda, Fred Cordova, and Laguna Bay Condominium Association, Inc. v. Timothy Wilkins

504 S.W.3d 485, 2016 Tex. App. LEXIS 11345, 2016 WL 6124662
Court of Appeals of Texas·Decided October 20, 2016·No. NUMBER 13-16-00273-CV·Published·Cited by 11 cases

Opinion

*488 OPINION

Opinion by Justice Rodriguez

This appeal concerns the trial court’s order granting a temporary injunction in favor of the appellee Timothy Wilkins, who owns a unit in the Laguna Bay Condominiums on South Padre Island. The injunction restrained the appellants—the Laguna Bay Condominium Association, Inc. and several of its board members 1 (collectively, the COA)—from collecting a special assessment of $91,316 from Wilkins and, by extension, from foreclosing on his condo. This sum allegedly represented Wilkins’s share of the cost to restore the Laguna Vista complex in the wake of Hurricane Dolly.

The COA brings this accelerated, interlocutory appeal of the temporary injunction. By its first and second issues on appeal, the COA argues that Wilkins failed to show two elements required to justify a temporary injunction—specifically, showing that in the absence of an injunction, he would suffer irreparable injury for which he had no adequate remedy at law. By a third issue, the COA argues that the trial court erred in assessing the “balance of equities” within the injunction calculus. We affirm.

I. Background

In 2013, Wilkins filed a separate lawsuit against the COA after his condo allegedly sustained water damage during Hurricane Dolly. Wilkins reached a settlement agreement with the COA (the Settlement). 2

Wilkins filed this lawsuit in 2015, principally alleging that the COA had breached the Settlement by failing to make repairs to his unit within six months of a given date, as the Settlement required. Wilkins contended that rather than repairing his unit, the COA instead repaired several other units and common areas in the complex and then sent him a special assessment of $91,316 for the cost of the repairs. The Settlement reads in relevant part:

A. The [COA] agrees to make the repairs, and further investigations, called for, and any additional repairs recommended as a result of the further investigations, in July 9, 2013, Final Report of [WJE Engineering] within 36 months of the date of this Settlement Agreement, except if that becomes impossible by force majeure or by Acts of God. However, the prioritization and sequence of the work, and the selection of available options, shall be up to the discretion of the [COA] Board after consultation with [WJE Engineering]. Notwithstanding the foregoing, any repairs that the [COA] Board and the Homeowners deem economically unfeasible do not have to be made.
B. Notwithstanding A above, within 6 months of the date of the approval of this Settlement Agreement by the Homeowners, if such approval is obtained, the [COA] shall:
1. Secure a report from Bob Fudge, PE, on what repairs are needed to repair leaks to Plaintiffs’ Units; and
2. Effect such repairs at the [COA]’s expense.
*489 C. The [COA] will specify to Plaintiffs, within 60 days of the date of this Settlement Agreement, which available sliding glass doors Plaintiffs may use on their Units.
G. Plaintiffs shall be ■ responsible for their pro-rata share -of any assess- ■ ments required ■ for the [COA] to comply with No.’s A, B & C above.

The record discloses that the homeowners voted to approve the Settlement in 2013 and'the report of professional engineer Bob Fudge was delivered on December 23, 2013. However, it is undisputed that the COA did not complete repairs to Wilkins’s unit within six months of December 23 and that the COA had not repaired his unit as of the filing of this appeal. According to Wilkins, the continued presence of moisture in the unsealed and unre-paired condo had caused further water damage and the development of mold, which prevented Wilkins from living in or renting out the condo. Wilkins also contends that the COA never indicated which sliding glass doors would meet the COA’s specifications pursuant to section D. Wilkins refused to pay the COA’s special assessment of $91,316 for the common-area repairs, and he began to withhold COA dues. In response, the COA allegedly attempted to foreclose on Wilkins’s condo. Wilkins then filed this suit, alleging breach of contract, breach of fiduciary duty, and multiple forms of fraud.

Soon after he initiated this suit, Wilkins submitted an application for temporary injunction seeking to prevent the COA from collecting the special assessment or foreclosing on his condo, among other things. 3 In support of his application for temporary injunction, Wilkins submitted evidence in-eluding his own affidavit, the Settlement, the special assessment, photos of water damage and mold, discovery responses, Fudge’s engineering report, and a proposal by an environmental remediation company to address mold and moisture problems.

In response, the COA did not dispute that it had agreed to repair Wilkins unit and had made other commitments in the Settlement. The COA instead argued that when it entered thé Settlement, it had not realized the extent of the necessary repairs; engineers had subsequently determined that the complex would need to be repaired, in sequence, from the top to the bottom. Since Wilkins’s unit was on the second floor out of seven, the COA urged that it was impracticable to adhere to the Settlement. The COA contended that Wilkins should instead be made to follow this top-down repair, plan, which had purportedly been adopted by all of the twenty-nine other condo owners. Wilkins’s share of this repair plan would be $91,316. The COA offered no evidence to support these arguments.

After the hearing, the trial court granted a temporary injunction and incorporated findings of fact into its order. Among other things, the court found that the COA intended to engage in collection efforts including a foreclosure sale on Wilkins’s real property and that Wilkins would likely succeed on the merits of his suit. The court also found that if the injunction were not granted, then the COA’s proposed course of action would tend to render any judgment in this case ineffectual, would threaten irreparable injury, and would leave Wilkins with no adequate remedy at law. The court also found that the injunction would *490 be consistent with preservation of the status quo, the public interest, and the balance of equities—specifically, that Wilkins’s potential injury if the injunction were erroneously denied would outweigh any injury to the COA that could occur if the injunction were erroneously granted. This interlocutory appeal followed.

II. Standard op Review

We review the trial court’s decision to grant a temporary injunction for a clear abuse of discretion. Butnaru v. Ford Motor Co., 84 S.W.3d 198, 204 (Tex. 2002); Walling v. Metcalfe, 863 S.W.2d 56, 58 (Tex. 1993) (per curiam).

Free access — add to your briefcase to read the full text and ask questions with AI

James Burkholder, Mike Morgan, Joe Urbanek, Melissa Grebb, Ruthie Ewers, Benjamin Bujanda, Fred Cordova, and Laguna Bay Condominium Association, Inc. v. Timothy Wilkins, 504 S.W.3d 485, 2016 Tex. App. LEXIS 11345, 2016 WL 6124662 (Tex. Ct. App. 2016).

504 S.W.3d 485 (James Burkholder, Mike Morgan, Joe Urbanek, Melissa Grebb, Ruthie Ewers, Benjamin Bujanda, Fred Cordova, and Laguna Bay Condominium Association, Inc. v. Timothy Wilkins) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

in the Estate of Reymundo De La Rosa
Court of Appeals of Texas, 2022
Barney Donalson v. City of Canton, Texas
Court of Appeals of Texas, 2020