Thyssen, Inc. v. Calypso Shipping Corp.

310 F.3d 102, 2002 A.M.C. 2332, 2002 U.S. App. LEXIS 20459
CourtCourt of Appeals for the Second Circuit
DecidedSeptember 26, 2002
Docket01-9044
StatusPublished
Cited by100 cases

This text of 310 F.3d 102 (Thyssen, Inc. v. Calypso Shipping Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thyssen, Inc. v. Calypso Shipping Corp., 310 F.3d 102, 2002 A.M.C. 2332, 2002 U.S. App. LEXIS 20459 (2d Cir. 2002).

Opinion

310 F.3d 102

THYSSEN, INC., Plaintiff-Appellant,
v.
CALYPSO SHIPPING CORP., S.A., A.M. Nomikos Maritime Agencies, S.A., In Personam, M/V Markos N, Official Number 9897, her engines, boilers, tackle, equipment, appurtenances, etc., in rem, Defendants-Appellees.

Docket No. 01-9044.

United States Court of Appeals, Second Circuit.

Argued: August 9, 2002.

Decided September 26, 2002.

Steven P. Calkins, Kingsley, Kingsley & Calkins, Hicksville, NY, for plaintiff-appellant.

Richard V. Singleton, Healy & Baillie, LLP, New York, NY, for defendants-appellees.

Before: CALABRESI, POOLER, and SOTOMAYOR, Circuit Judges.

BACKGROUND

PER CURIAM.

Plaintiff-appellant Thyssen, Inc. ("Thyssen") contracted for a cargo of steel coils and the cargo's delivery to the United States with a Hong Kong company, Metalsrussia, on October 26, 1996. Delivery was to be completed by January 31, 1997. Metalsrussia arranged to ship the coils by subchartering the MARKOS N from Western Bulk Carriers, which had previously chartered the ship from its owner, Defendant-appellee Calypso Shipping Corp., S.A. ("Calypso").1 The MARKOS N charter agreement (or charter party) between Metalsrussia and Western Bulk Carrier is at the center of this dispute.

Two bills of lading issued for Thyssen's cargo from an agent of Western Bulk Carriers on January 23 and 24, 1997, referencing the above-mentioned charter party. Both bills of lading contain, as the first condition of carriage, the provision: "All terms and conditions, liberties and exceptions to the Charter Party, dated as over-leaf, including the Law and Arbitration Clause, are herewith incorporated."

When the coils arrived in the United States, they were damaged by rust. Despite the damage, Western Bulk Carriers was paid by Metalsrussia, which was in turn paid in full by Thyssen. The dispute now is between Thyssen and the vessel's owners and managers and the ship itself in rem.

Thyssen brought suit in the Southern District of Texas on March 5, 1997, which issued a warrant for the arrest of the MARKOS N and ordered expedited discovery to allow inspection of the vessel. In exchange for the release of the ship, Thyssen accepted a "Club Letter of Undertaking" from the vessel's insurer, which promised to pay up to $600,000 in the event of a final judgment for the plaintiff. The letter reserved all defenses.

The parties agreed to transfer the action to the Southern District of New York in August of 1997. On March 11, 1998, a little more than one year after the alleged damage took place, Calypso filed an answer on behalf of itself and the vessel. The answer raised a number of defenses, including a claim that its liability was limited to $500 per package under the Carriage of Goods by Sea Act ("COGSA"). The answer did not mention the arbitration clause. In November 1998, Thyssen, seeking to dismiss defendant's per-package defense, moved for partial summary judgment. In response, Calypso filed its opposition to Thyssen's motion and, arguing that the incorporated bill of lading required that disputes be resolved by arbitration in London under English law, made a cross-motion to stay the proceedings pursuant to the Federal Arbitration Act.

The district court (Mukasey, J.) stayed the federal court proceedings. It found (1) that Thyssen's bill of lading incorporated the London arbitration clause of the MARKOS N charter party between Western Bulk Carriers and Metalsrussia; (2) that there was adequate evidence of the incorporation by reference of a written arbitration provision into the charter party; (3) that the charter party contained a "broad" arbitration clause sufficient to bind nonsignatories; (4) that Thyssen's in rem action against the vessel was arbitrable; (5) that Calypso had not waived its right to arbitrate the dispute by allowing the litigation to proceed; and (6) that whether Thyssen's claims were time-barred was a matter for the arbitrator to decide.

London arbitrators were appointed, but the parties agreed to allow the Commercial Court in London to decide whether or not Thyssen's claims were time-barred. (English law, like COGSA, includes a one-year time bar on damaged-goods claims.) That court decided that the claims were indeed time-barred and, finding that the delay was Thyssen's fault and doubting Thyssen's claims that it had tried and failed to obtain copies of the charter parties, refused to exercise its discretion under the English Arbitration Act to grant an extension. The Commercial Court thereupon dismissed Thyssen's claims in a decision that Thyssen did not appeal.

The case returned to the federal district court, which confirmed the arbitration award and finally disposed of all of Thyssen's claims. In so doing, the court turned aside arguments by Thyssen that (1) the arbitration was aborted and should therefore be voided pursuant to 9 U.S.C. § 10(a)(4), and (2) that since arbitrators have no in rem jurisidiction under English law, any contractual clause purporting to force London arbitration of in rem claims would be void under COGSA, 46 U.S.C. § 1303(8).

Thyssen appeals these two decisions of the district court on four grounds: (1) Calypso waived arbitration by waiting as long as it did before raising its right to arbitrate. (2) Dismissal of Thyssen's in rem action against the MARKOS N deprived Thyssen of a remedy. (3) Requiring London arbitration of Thyssen's in rem claims violates COGSA § 3(8).(4) The arbitration clause in the charter party should not be enforced, because neither party to the bill of lading was a signatory of the charter party, and because Thyssen was unaware of the charter party's contents.

DISCUSSION

I. Waiver

We review de novo a district court's decision regarding waiver of a party's right to arbitrate, but we review the factual findings on which the district court relied for clear error. See S & R Co. of Kingston v. Latona Trucking, Inc., 159 F.3d 80, 83 (2d Cir.1998).

"[T]here is a strong presumption in favor of arbitration[, and] waiver of the right to arbitration is not to be lightly inferred." Coca-Cola Bottling Co. v. Soft Drink and Brewery Workers Union Local 812, 242 F.3d 52, 57 (2d Cir.2001) (internal quotation marks omitted). "An inquiry into whether an arbitration right has been waived is factually specific and not susceptible to bright line rules." Cotton v. Slone, 4 F.3d 176, 179 (2d Cir.1993). Generally, waiver is more likely to be found the longer the litigation goes on, the more a party avails itself of the opportunity to litigate, and the more that party's litigation results in prejudice to the opposing party. Leadertex, Inc. v. Morganton Dyeing & Finishing Corp.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
310 F.3d 102, 2002 A.M.C. 2332, 2002 U.S. App. LEXIS 20459, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thyssen-inc-v-calypso-shipping-corp-ca2-2002.