The Colombia

197 F. 661, 1912 U.S. Dist. LEXIS 1473
CourtDistrict Court, S.D. Alabama
DecidedJune 4, 1912
DocketNo. 1,293
StatusPublished
Cited by15 cases

This text of 197 F. 661 (The Colombia) is published on Counsel Stack Legal Research, covering District Court, S.D. Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Colombia, 197 F. 661, 1912 U.S. Dist. LEXIS 1473 (S.D. Ala. 1912).

Opinion

TOUDMIN, District Judge.

This is a suit to recover the contract price for certain materials furnished and repairs done on the steamship Colombia under a contract made between the master of said steamship and the libelant. The contract price to be paid for said material and work was $2,783, which said sum is claimed to be due and unpaid.

[662]*662The libelant agreed to do the repairs,- as per specifications, for the sum named, “work to be completed in twelve running days,” and also agreed “to pay a demurrage as per specifications.” The specifications provided that-:

“Should .the contractor exceed the time mentioned he must pay the ship a demurrage, at a rate of $100.00 for each and every day he is in excess of his contracted time.”

The claimant sets up in answer to libelant’s claim that said work was not completed by the libelant iñ the time specified in the contract, but that libelant was 29% days in excess of said contracted time in completing the work. .Claimant claims that by the terms of said contract there is due to him by the libelant demurrage as agreed, to wit, at the rate of $100 a day, making the sum of $2,950, being an amount of $167 in excess, of the sum claimed by the libelant. On the trial it was admitted that the work done by libelant was dohe to the satisfaction of the master and representatives of the steamship. It was also admitted that the number of days in completing the work was 29% days in excess of the contracted time; and it was further admitted that nothing had been paid libelant for the work done. The claimant abandoned so much of his claim as was in excess of that of the libelant, to wit, the sum of $167.

The court will always seek to ascertain the true and real intention of the contracting parties, giving due weight to the language or words used in the contract, in view of the circumstances and conditions under which it was made. Turner v. City of Fremont (C. C.) 159 Fed. 221; Keeble v. Keeble, 85 Ala. 552, 5 South. 149. The agreement in this case was that the work would be completed in 12 running days, and, should the contractor exceed the time mentioned, he would pay the ship a demurrage at a rate of $100 for each and every day he was in excess of his contracted time. The vessel was not under charter, and was not. otherwise employed at the time the contract was made. She had been engaged in the fruit trade in this-port under charter to an importer of bananas. That charter had expired a few days before the contract for the repairs of the vessel was made. It was the dull season for the importation of bananas into this port. There were several fruit vessels besides the Colombia without charter or other employment at the time the contract involved in this case was made. Other vessels than the Colombia were also laid up and undergoing repairs by the libelant at the same time. The •contract provides that the libelant shall pay a demurrage for each and every day in excess of the time mentioned in the contract in which he was to complete the work.

[1] “Demurrage” in its technical and popular signification is compensation for the delay of a ship in her employment or voyage. It is a sum fixed by contract, or, if the amount of compensation is not so fixed, implied for the delay or detention of a vessel in the strict sense of the term, in the loading and unloading of cargo. The term “demurrage” is commonly applied to the damages sustained by such delay or detention. “Demurrage,” in the proper sense of the term,. [663]*663is an allowance or a reward to a vessel in compensation for the earnings she is improperly caused to lose. It is a proper element- of damages, but can only be allowed when profits have either actually been lost, or may be reasonably supposed to have been lost, and their amount is previously fixed by contract, or is proven with reasonable certainty. 9 Am. & Eng. Encyc. of Law (2d Ed.) 222; The Conqueror, 166 U. S. 110-125, 17 Sup. Ct. 510, 41 L. Ed. 937. It has been said that “demurrage is only an extended freight or reward to the vessel in compensation for the earnings she is improperly caused to lose.” Donaldson v. McDowell, 1 Holmes, 290, Fed. Cas. No. 3,985. As a general rule, courts of admiralty have allowed the demurrage stipulated, unless the loss to the ship is shown to be less. 1 Pars. Ship. & Adm. 313; Carver Carr, by Sea, 609; New York & N. E. R. Co. v. Church, 58 Fed. 600, 7 C. C. A. 384. “To entitle the owner to demurrage there must be a pecuniary loss, or at least a reasonable certainty of pecuniary loss. It does not follow as a matter of necessity that anything is due for the detention of a vessel whilst under repair.” There would be where a voyage was lost or where the vessel would have been beneficially employed. The Conqueror, supra; The Clarence, 3 W. Rob. 283; 9 Am. & Eng. Encyc. of Law, supra; The Saginaw (D. C.) 95 Fed. 703.

[2] It is to be presumed that the parties to the contract well knew the legal meaning and popular signification of the term “demurrage,” and that they used it in its legal and popular sense and meaning. If so, their contract should be construed as an agreement that the libelant would pay to the ship such sum as damages as would compensate her for the earnings she should be caused to lose by the libel-ant’s default. Such is, in my opinion, the correct and just interpretation of the contract in this instance.

It does not appear, in this case, that the ship lost anything by her detention whilst under repairs. The proof is that she had no engagement or voyage interrupted by the detention; that she was not under charter; had no charter or employment offered her during the period of her detention, and made no effort to get a charter. The master of the ship testified that he told Bogue, the manager of libelant’s company at some time (whether before or after the expiration of the time in which the work was to be completed is not very clear, the evidence of the master of said steamship and of Bogue on the subject being in conflict, the one claiming it was before and the other that it was after) that he had better look out, as the ship might get a charter at any time; and Bogue stated that the master said, if so, he would have to pay demurrage. The master denied saying anything about demurrage. But the witnesses agreed that the master at that time said that the owner (who resides in Norway)' was working hard to get a charter.

August Kling, the president of the libelant company, testified that a few days after they had entered upon the work of repairs, and were working night and day, the master of the ship came to the shop and told him it was not necessary to do any night work, that they would [664]*664not be held responsible for demurrage “except the ship got a charter,” and that she had no' charter then. The master denied making this statement. It, however, appeared from the evidence that they thereafter ceased working at night.

In my view of the case, it is unnecessary for me to endeavor to reconcile the conflicting statements of these witnesses. If the statements , referred to were made by the master, as testified to by Kling and Bogue, they did not constitute an alteration or modification of the contract. But I think they, in connection with the conduct of the libelant in regard to the work, would tend to show or indicate how the parties themselves construed the contract, and which, in my judgment, is the correct construction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barrie School v. Patch
933 A.2d 382 (Court of Appeals of Maryland, 2007)
Ferraina v. Industrial Health Care Co., No. Cvh-6214 (Feb. 24, 2000)
2000 Conn. Super. Ct. 1972 (Connecticut Superior Court, 2000)
Howarth v. Feeney, 86-3543 (1992)
Superior Court of Rhode Island, 1992
Trans-Asiatic Oil Ltd., S.A. v. Apex Oil Company
804 F.2d 773 (First Circuit, 1986)
Enro Maritime Enterprises, Inc. v. S.T. Richard C. Sauer
320 F. Supp. 788 (S.D. New York, 1970)
Norwalk Door Closer Co. v. Eagle Lock & Screw Co.
220 A.2d 263 (Supreme Court of Connecticut, 1966)
Roberts v. North Negros Sugar Co.
18 F. Supp. 767 (D. Maryland, 1937)
Rispin v. Midnight Oil Co.
291 F. 481 (Ninth Circuit, 1923)
City of Los Angeles v. Shafer
200 P. 384 (California Court of Appeal, 1921)
Northwestern Terra Cotta Co. v. Caldwell
234 F. 491 (Eighth Circuit, 1916)
Bailey v. Manufacturers' Lumber Co.
224 F. 806 (S.D. New York, 1915)
Sheffield-King Milling Co. v. Domestic Science Baking Co.
19 Ohio N.P. (n.s.) 497 (Court of Common Pleas of Ohio, Hamilton County, 1914)
Rasmussen v. Home Industry Iron Works
199 F. 990 (Fifth Circuit, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
197 F. 661, 1912 U.S. Dist. LEXIS 1473, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-colombia-alsd-1912.