Tennessee ex rel. Leech v. Dole

749 F.2d 331, 53 U.S.L.W. 2315
CourtCourt of Appeals for the Sixth Circuit
DecidedNovember 29, 1984
DocketNo. 83-5499
StatusPublished
Cited by15 cases

This text of 749 F.2d 331 (Tennessee ex rel. Leech v. Dole) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tennessee ex rel. Leech v. Dole, 749 F.2d 331, 53 U.S.L.W. 2315 (6th Cir. 1984).

Opinion

MERRITT, Circuit Judge.

This case is in effect a fight between the State of Tennessee and the United States over damages the State has recovered from bid riggers on federally funded road projects. Brought by the State against federal road officials for injunctive and declaratory relief, the principal questions are whether the relationship between the State as a federal grant recipient and its federal grantor is governed by the law of restitution or unjust enrichment under federal common law principles and whether jurisdiction of such issues resides exclusively in the Court of Claims, rather than the District Courts, under the Tucker Act. We hold that the State’s claims to all the money recovered, though outside the Tucker Act, are contrary to applicable legal principles of unjust enrichment arising from benefits conferred by mistake; and we remand the ease to the District Court to weigh the equities of the parties in order to determine the precise amount of the State’s recovery owed as restitution to the federal government.

I.

The process of federal highway construction funding proceeds through several stages. Congress authorizes a division of funds for each state according to a statutory formula. These funds are initially maintained in an account called an “unpro-grammed balance account” administered by the Federal Highway Administration of the Department of Transportation. In order to draw on the account, the state must first have its highway program approved and then later have its plans for individual projects approved. Once a project is approved a bookkeeping entry is made shifting the funds into a project account. After the project is bid out by the state, federal road officials must approve the award of the bid. A project agreement is then executed with the state. The agreement obligates the government to reimburse the [333]*333state for a share of the construction costs — usually ninety percent on interstate highway projects and seventy-five percent on most other projects. There are various rules regarding the lapse of unexpended funds, and in recent years the Secretary has imposed an inflation-fighting or a deficit-fighting ceiling on each state’s expenditures in an amount less than the Congressional authorization. In 1982, for example, Congress authorized $171 million for Tennessee; but the Secretary’s ceiling limited Tennessee to $144 million.

After the Justice Department obtained criminal convictions against approximately 70 firms and individuals for bid rigging on Tennessee road projects in violation of the Sherman Antitrust Act, the Tennessee Attorney General entered into settlements with some of the contractors for approximately $12 million. The State admits that a significant portion of this amount is attributable to the contribution of the federal government to state highway projects, although the record is unclear as to the exact amount of the settlements, the amount so far collected and the amount attributable to the federal contribution. The theory of the settlements is that the bid rigging contractors fixed the prices paid by the State on highway projects and that the State paid highway construction contract prices higher than the prices that otherwise would have prevailed. The federal officials would not have funded the projects, and the State would not have accepted the bids, had they known that the bid prices were the result of contractor collusion.

When the State initiated its investigation, antitrust Assistant Attorney General Lit-vack advised Tennessee Attorney General Leech that his office “had no interest in Tennessee's efforts to recover any over charges due to bid rigging on federal highway construction projects” and that Tennessee’s efforts to recover “were matters for the State and its officials.”

Despite these assurances from the Antitrust Division, in mid-1981, more than a year after the State investigation and settlement process had begun, federal highway officials wrote a series of letters addressed to various Tennessee officials, including the Commissioner of Transportation and the Attorney General, seeking information concerning settlements made for the purpose of determining how much of the settlement should be attributed to the federal share contributed to highway projects. The State officials in response consistently took the position that “we have researched the law in this matter,” and “we cannot discern any legal basis” for the claim of the federal road officials that the federal government should “participate in the State antitrust settlement fund.”

When State officials refused to give federal road officials the information they requested regarding the settlements, the federal officials computed from the information they had in their files a sum in excess of $4.5 million that they claimed must be set off against current highway funds allocated to the State of Tennessee, thereby reducing the State’s funding on current projects. The federal officials took the position, however, that “the sums subtracted from the current billings” — the $4.5 million setoff — “can be restored to the unpro-grammed balance” of funds for future highway construction projects in Tennessee.

The federal officials now take the position that this method of handling the $4.5 million setoff will have the effect of reducing current year federal highway funding for Tennessee road projects but will increase by precisely the same amount road funds for Tennessee’s use in future years. The State disputes this contention. It claims that under the Highway Act the State will have to come up with approximately twenty-five percent in matching funds, or $1,200,000, in order to get the benefit in future years of the $4.5 million that will be taken by the setoff from the State’s settlement funds. The State further contends that the $4.5 million setoff is expressly “subject to available obligation authority” and that it is unlikely that the State will actually receive the benefit of the $4.5 million credit in future years in light [334]*334of the ceilings now being imposed. The record is unclear as to the actual effect, in dollars and cents, of the $4.5 million setoff against current funding because it is unclear how much of this money will be restored in future years.

A stalemate occurred in the negotiations between the parties, and the State filed this action in January, 1983. In its complaint the State claimed that the federal government is not entitled to any portion of the settlement fund and requested that the District Court enjoin the federal defendants from taking any administrative action to retrieve by setoff the federal share of such recoveries.

The defendants opposed the injunction on the grounds that the action is in effect a suit on a contract with the United States for more than $10,000 and that under the Tucker Act only the Court of Claims has jurisdiction of such contract actions. On the merits the defendants argued that federal policy and common law legal principles of restitution require that when a state recovers over-charges on federal aid highway projects, the federal share of the recovered sum must be credited back to the projects on which the over-charges occurred. The defendants argued that only by such a credit could the federal share of road construction programs be kept within statutory limits set out in the Highway Act, 23 U.S.C. § 120

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
749 F.2d 331, 53 U.S.L.W. 2315, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tennessee-ex-rel-leech-v-dole-ca6-1984.