Swann & Weiskopf, Ltd. v. Meed Associates, Inc.

711 N.E.2d 395, 304 Ill. App. 3d 970, 238 Ill. Dec. 292, 1999 Ill. App. LEXIS 294
CourtAppellate Court of Illinois
DecidedApril 29, 1999
Docket1-98-3496
StatusPublished
Cited by21 cases

This text of 711 N.E.2d 395 (Swann & Weiskopf, Ltd. v. Meed Associates, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Swann & Weiskopf, Ltd. v. Meed Associates, Inc., 711 N.E.2d 395, 304 Ill. App. 3d 970, 238 Ill. Dec. 292, 1999 Ill. App. LEXIS 294 (Ill. Ct. App. 1999).

Opinion

JUSTICE WOLFSON

delivered the opinion of the court:

Confronted with the claim that its contribution counts were barred by the statute of limitations, Swann & Weiskopf, Ltd. (Swann), offers two reasons why its action against Meed Associates, Inc. (Meed), should survive — the discovery rule and the equitable estoppel doctrine. Neither works. We affirm the trial court’s order granting summary judgment to Meed.

FACTS

In 1985, Swann agreed to provide design services for S.B. Holdings at the Libertyville Manor Extended Care Facility. Swann subcontracted Bernard Orzechowski (Orzechowski) and his company, Meed, to design a storm water removal system for the Libertyville project.

In 1998, Swann’s project manager Jim Leyden (Leyden) testified at a deposition. Leyden said: Swann had hired Meed on several occasions and contacted Meed for civil engineering on the project because, “Meed Associates performed high-quality engineering work.” Meed’s work included designing the “mechanical, plumbing and storm water retention” systems.

Shortly after the project was completed in 1989, S.B. Holdings notified Swann of the project’s flooding problems. Swann dispatched Leyden and Orzechowski to investigate, and Orzechowski concluded earth mounds around the project site contributed to the flooding problems. When asked if he agreed with Orzechowski’s opinion, Leyden responded:

“Meed Associates knew the location of the earth mounds. It was brought to their attention as per our site plan and also on some *** previous correspondence that we’ve talked about between the Village of Libertyville and Meed Associates.
[Orzechowski] was required to include the calculations for water retention from any contributory area off of those earth mounds. That much I do know.”

“[0]n or about October 12 of ‘89,” Swann learned S.B. Holdings had hired an engineering firm, Albert Halff Associates (Halff), which “was questioning the design of the storm water removal system.” In an October 12, 1989, letter from Halff to S.B. Holdings, which Swann representatives read that month, Halff was “critical” of Meed’s design of the storm water removal system. Halff concluded the eight-inch storm water pipe shown in the plans was insufficient to handle storm water at the project site.

Orzechowski responded to Halff s October 12, 1989, letter with a December 14, 1989, letter to Swann:

“1. Storm water sewer sizes, slopes and materials meet all governing code requirements, at time of original plan and permit submittals.
2. Storm water retention was in compliance with all governing codes at the time of original plan and permit submittals.
3. Flooding problem [at the project site] was as a result of the earth mound ***. The earth mound resulted in the creation of rerouted storm water flow and possible blockage of water flow in the storm sewer system, due to soil erosion.”

On April 18, 1990, S.B. Holdings filed a complaint against Swann in Lake County circuit court, alleging the storm water removal system was defectively designed. S.B. Holdings and Swann chose to arbitrate their case.

At a February 15, 1991, arbitration hearing, attorneys for S.B. Holdings and Swann discussed the design of the storm water removal system. According to S.B. Holdings’ attorney, “The issues presented, however, in the claim are more directed towards the design of that [storm water removal] system than they are in the actual construction of that system.” When asked by an arbitrator to summarize the issues in the case, S.B. Holdings’ attorney repeated: “There is an issue related to the design of the storm water retention system ***.” Swann’s attorney, of course, was present.

During the arbitration case, Orzechowski assisted Swann and its independent engineering expert, Kathleen Rafter (Rafter). The record does not reveal when Swann retained Rafter. Orzechowski still defended the design of the storm water removal system and his earth mound theory explaining the flooding problems. But Orzechowski subsequently retreated from his earlier opinions.

In a 1998 deposition, Orzechowski testified: Around March 12, 1994, Orzechowski spoke with Swann’s attorney and mentioned he and Rafter had discovered a defect in his design of the storm water removal system.

“The inadequacy of the sewer size was something that [Rafter] and myself, I’d say, discovered at the same time.
Before that we had no reason to believe or — my assumption was that the initial flooding was as a result of this improper — the state just wasn’t the same. It was not as per the plans. This [earth] mound in my mind was the contributing factor until I heard differently ***.”

Before Rafter discovered his design defect, Orzechowski believed “the system designed was installed as per plan and was adequate.” After Rafter’s conclusions, Orzechowski acknowledged “certain portions of the storm water removal system were inadequately sized.”

In July 1994, the arbitration panel ordered Swann to pay $477,239 to S.B. Holdings to remedy the flooding problem. On February 21, 1995, Swann filed a “Complaint for Contribution” against Meed. Meed responded with an affirmative defense based on the limitations period. Swann filed an amended complaint, adding a breach of contract count to its contribution count. Meed filed a summary judgment motion, again based on the limitations period. Swann responded, arguing the discovery rule and the estoppel doctrine saved its complaint from a limitations period defense. On August 17, 1998, the trial court granted summary judgment to Meed. This appeal followed.

DECISION

Summary judgment is appropriate if the record shows “that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” 735 ILCS 5/2—1005(c) (West 1994). Summary judgment “is a drastic means of disposing of litigation and should only be allowed when the right of the moving party is clear and free from doubt.” Loyola Academy v. S&S Roof Maintenance, Inc., 146 Ill. 2d 263, 271, 586 N.E.2d 1211 (1992), citing Purtill v. Hess, 111 Ill. 2d 229, 240, 489 N.E.2d 867 (1986). The trial court must construe the pleadings, depositions, admissions, and affidavits strictly against the moving party and liberally in favor of the nonmoving party. Loyola Academy, 146 Ill. 2d at 271.

We review de novo the trial court’s decision to grant summary judgment. La Salle National Bank v. Skidmore, Owings & Merrill, 262 Ill. App. 3d 899, 902, 635 N.E.2d 564 (1994).

Swann makes two contentions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McMahan v. Sol Holland Co., Inc.
2023 IL App (1st) 211367-U (Appellate Court of Illinois, 2023)
Dubin v. Levenfeld Pearlstein, LLC
2021 IL App (1st) 200369-U (Appellate Court of Illinois, 2021)
M&S Industrial Co., Inc. v. Allahverdi
2018 IL App (1st) 172028 (Appellate Court of Illinois, 2018)
Newell v. Newell
942 N.E.2d 776 (Appellate Court of Illinois, 2011)
Hollander, Jacque v. Brown, James
457 F.3d 688 (Seventh Circuit, 2006)
Boxdorfer v. DaimlerChrysler Corp.
396 F. Supp. 2d 946 (C.D. Illinois, 2005)
Lama v. Preskill
Appellate Court of Illinois, 2004
In Re Mut. Life Ins. Co. of New York Premium Lit.
299 F. Supp. 2d 4 (D. Massachusetts, 2004)
Continental Casualty Co. v. American National Bank & Trust Co.
768 N.E.2d 352 (Appellate Court of Illinois, 2002)
Harris v. Old Kent Bank
Appellate Court of Illinois, 2000
Guzman v. C.R. Epperson Construction, Inc.
722 N.E.2d 1223 (Appellate Court of Illinois, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
711 N.E.2d 395, 304 Ill. App. 3d 970, 238 Ill. Dec. 292, 1999 Ill. App. LEXIS 294, Counsel Stack Legal Research, https://law.counselstack.com/opinion/swann-weiskopf-ltd-v-meed-associates-inc-illappct-1999.