Swann & Weiskopf, Ltd. v. Meed Associates, Inc.

Procedural entryThis page is a short order in Swann & Weiskopf, Ltd. v. Meed Associates, Inc.. Read the opinion of the Court — 304 Ill. App. 3d 970
Appellate Court of Illinois·Decided April 29, 1999·No. 1-98-3496·Published

Opinion

FOURTH DIVISION

April 29, 1999

No. 1-98-3496

SWANN & WEISKOPF, LTD., )  APPEAL FROM THE

)  CIRCUIT COURT OF

Plaintiff-Appellant, )  COOK COUNTY.

)

v. )  95 L 2659

)

MEED ASSOCIATES, INC., an Illinois )

corporation, )  HONORABLE

)  KENNETH L. GILLIS,

Defendant-Appellee. )  JUDGE PRESIDING.

JUSTICE WOLFSON delivered the opinion of the court:

Confronted with the claim that its contribution counts were barred by the statute of limitations, Swann & Weiskopf, Ltd. (Swann) offers two reasons why its action against Meed Associates, Inc. (Meed) should survive--the discovery rule and the equitable estoppel doctrine.  Neither works.  We affirm the trial court's order granting summary judgment to Meed.

FACTS

In 1985, Swann agreed to provide design services for S.B. Holdings at the Libertyville Manor Extended Care Facility.  Swann subcontracted Bernard Orzechowski (Orzechowski) and his company, Meed, to design a storm water removal system for the Libertyville project.

In 1998, Swann's project manager Jim Leyden (Leyden) testified at a deposition.  Leyden said:

Swann had hired Meed on several occasions, and contacted Meed for civil engineering on the project because, "Meed

Associates performed high-quality engineering work."  Meed's work included designing the "mechanical, plumbing and storm water retention" systems.

Shortly after the project was completed in 1989, S.B. Holdings notified Swann of the project's flooding problems.  Swann dispatched Leyden and Orzechowski to investigate, and Orzechowski concluded earth mounds around the project site contributed to the flooding problems.  When asked if he agreed with Orzechowski's opinion, Leyden responded:

"Meed Associates knew the location of the earth mounds.  It was brought to their attention as per our site plan and also on some *** previous correspondence that we've talked about between the Village of Libertyville and Meed Associates.

[Orzechowski] was required to include the calculations for water retention from any contributory area off of those earth mounds.  That much I do know."

"[O]n or about October 12 of '89," Swann learned S.B. Holdings had hired an engineering firm, Albert Halff Associates (Halff), who "*** was questioning the design of the storm water removal system ***."  In an October 12, 1989, letter, from Halff to S.B. Holdings, which Swann representatives read that month, Halff was "critical" of Meed's design of the storm water removal system.  Halff concluded the eight-inch storm water pipe shown in the plans was insufficient to handle storm water at the project site.

Orzechowski responded to Halff's October 12, 1989, letter with a December 14, 1989, letter to Swann:

"1. Storm water sewer sizes, slopes and materials meet  all governing code requirements, at time of              original plan and permit submittals.

2. Storm water retention was in compliance with all      governing codes at the time of original plan and         permit submittals.

3. Flooding problem [at the project site] was as a       result of the earth mound ***.  The earth mound          resulted in the creation of rerouted storm water         flow and possible blockage of water flow in the          storm sewer system, due to soil erosion."

On April 18, 1990, S.B. Holdings filed a complaint against Swann in Lake County Circuit Court, alleging the storm water removal system was defectively designed.  S.B. Holdings and Swann chose to arbitrate their case.

At a February 15, 1991, arbitration hearing, attorneys for S.B. Holdings and Swann discussed the design of the storm water removal system.  According to S.B. Holdings' attorney, "The issues presented, however, in the claim are more directed towards the design of that [storm water removal] system than they are in the actual construction of that system."  When asked by an arbitrator to summarize the issues in the case, S.B. Holdings' attorney repeated: "There is an issue related to the design of the storm water retention system ***."  Swann's attorney, of course, was present.

During the arbitration case, Orzechowski assisted Swann and its independent engineering expert Kathleen Rafter (Rafter).  The record does not reveal when Swann retained Rafter.  Orzechowski still defended the design of the storm water removal system and his earth mound theory explaining the flooding problems.  But Orzechowski subsequently retreated from his earlier opinions.

In a 1998 deposition, Orzechowski testified:

Around March 12, 1994, Orzechowski spoke with Swann's attorney and mentioned he and Rafter had discovered a defect in his design of the storm water removal system.

"The inadequacy of the sewer size was something that [Rafter] and myself, I'd say, discovered at the same time.

Before that we had no reason to believe or--my assumption was that the initial flooding was as a result of this improper--the state just wasn't the same.  It was not as per the plans.  This [earth] mound in my mind was the contributing factor until I heard differently ***."

Before Rafter discovered his design defect, Orzechowski believed "*** the system designed was installed as per plan and was adequate."  After Rafter's conclusions, Orzechowski acknowledged "*** certain portions of the storm water removal system were inadequately sized[.]"

In July 1994, the arbitration panel ordered Swann to pay $477,239 to S.B. Holdings to remedy the flooding problem.  On February 21, 1995, Swann filed a "Complaint for Contribution" against Meed.  Meed responded with an affirmative defense based on the limitations period.  Swann filed an amended complaint, adding a breach of contract count to its contribution count.  Meed filed a summary judgment motion, again based on the limitations period.  Swann responded, arguing the discovery rule and the estoppel doctrine saved its complaint from a limitations period defense.  On August 17, 1998, the trial court granted summary judgment to Meed.  This appeal followed.

DECISION

Summary judgment is appropriate if the record shows "*** that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law."  735 ILCS 5/2-1005(c) (West 1994).  Summary judgment "*** is a drastic means of disposing of litigation and should only be allowed when the right of the moving party is clear and free from doubt."   Loyola Academy v. S&S Roof Maintenance, Inc. , 146 Ill. 2d 263, 271, 586 N.E.2d 1211 (1992)(citing Purtill v. Hess , 111 Ill. 2d 229, 240, 489 N.E.2d 867 (1986)).  The trial court must construe the pleadings, depositions, admissions, and affidavits strictly against the moving party and liberally in favor of the non-moving party.   Loyola Academy , 146 Ill. 2d at 271.

We review de novo

Free access — add to your briefcase to read the full text and ask questions with AI

Swann & Weiskopf, Ltd. v. Meed Associates, Inc., (Ill. Ct. App. 1999).

Swann & Weiskopf, Ltd. v. Meed Associates, Inc. (Swann & Weiskopf, Ltd. v. Meed Associates, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Hochbaum v. Casiano
686 N.E.2d 626 (Appellate Court of Illinois, 1997)
Knox College v. Celotex Corp.
430 N.E.2d 976 (Illinois Supreme Court, 1981)
Beynon Building Corp. v. National Guardian Life Insurance
455 N.E.2d 246 (Appellate Court of Illinois, 1983)
LaSalle Nat. Bank v. SKIDMORE, OWINGS
635 N.E.2d 564 (Appellate Court of Illinois, 1994)
Butler v. Mayer, Brown and Platt
704 N.E.2d 740 (Appellate Court of Illinois, 1998)
Axia, Inc. v. I. C. Harbour Construction Co.
501 N.E.2d 1339 (Appellate Court of Illinois, 1986)
Purtill v. Hess
489 N.E.2d 867 (Illinois Supreme Court, 1986)
Flint v. Court Appointed Special Advocates of Du Page County, Inc.
674 N.E.2d 831 (Appellate Court of Illinois, 1996)
Henderson v. Jones Bros. Construction Corp.
602 N.E.2d 16 (Appellate Court of Illinois, 1992)
Schiller v. Kucaba
203 N.E.2d 710 (Appellate Court of Illinois, 1964)
York v. Village of Wilmette
498 N.E.2d 712 (Appellate Court of Illinois, 1986)
Jackson Jordan, Inc. v. Leydig, Voit & Mayer
633 N.E.2d 627 (Illinois Supreme Court, 1994)
Freeport Memorial Hospital v. Lankton, Ziegele, Terry & Associates, Inc.
525 N.E.2d 194 (Appellate Court of Illinois, 1988)
Nolan v. Johns-Manville Asbestos
421 N.E.2d 864 (Illinois Supreme Court, 1981)
Senior Housing, Inc. v. Nakawatase, Rutkowski, Wyns & Yi, Inc.
549 N.E.2d 604 (Appellate Court of Illinois, 1989)
Board of Library Directors v. Skidmore
574 N.E.2d 869 (Appellate Court of Illinois, 1991)
Loyola Academy v. S & S Roof Maintenance, Inc.
586 N.E.2d 1211 (Illinois Supreme Court, 1992)
County of Du Page v. Graham, Anderson, Probst & White, Inc.
485 N.E.2d 1076 (Illinois Supreme Court, 1985)